Self-Redevelopment of Jeevan Smriti CHS Ltd.
by JEEVAN SMRITI CO-OPERATIVE HOUSING SOCIETY LTD. · Pahadi, Goregaon, Mumbai
Possession date of Self-Redevelopment of Jeevan Smriti CHS Ltd.: 31 July 2027, moved from 31 December 2024 (27 months later). This is the latest completion date the builder has filed on MahaRERA. How to check it yourself
Registered on MahaRERA under P51900033146, and currently active. Its completion date has moved from December 2024 to July 2027: 27 months at the builder's request, plus MahaRERA's automatic 4-month extension for all eligible projects.
Source: GharKundli’s check of MahaRERA records, October 2026.
What do you want to know about Self-Redevelopment of Jeevan Smriti CHS Ltd.?
How the possession date of Self-Redevelopment of Jeevan Smriti CHS Ltd. has moved
31 December 2024
Completion date given when the project was registered
31 December 2025
Extended at the builder's request (MahaRERA application EXT51900025498)
Reason the builder gave MahaRERA:
“I, Mr. Prasanna Diwakar Samant, hereby declare the following with respect to the project “Self-Redevelopment of Jeevan Smriti CHS Ltd.” bearing registration number P51900033146 registered under MahaRERA Accordingly, we, along with our Proje…” Read the full reason
“I, Mr. Prasanna Diwakar Samant, hereby declare the following with respect to the project “Self-Redevelopment of Jeevan Smriti CHS Ltd.” bearing registration number P51900033146 registered under MahaRERA Accordingly, we, along with our Project Management Consultant (PMC), prepared and submitted a proposal to secure financing from Mumbai District Central Co-op. Bank Limited, which was a viable funding source for self-redevelopment projects. However, during the COVID-19 pandemic, the Reserve Bank of India (RBI) imposed restrictions on Mumbai District Central Co-op. Bank Limited, preventing it…”31 March 2027
Extended at the builder's request (MahaRERA application EA10082622081)
Reason the builder gave MahaRERA:
“Dear Sir/Ma’am, We, Jeevan Smriti CoOperative Housing Society Ltd, hereby declare the following with respect to the project “SelfRedevelopment of Jeevan Smriti CHS Ltd” bearing registration number P51900033146 registered under MahaRERA 1.…” Read the full reason
“Dear Sir/Ma’am, We, Jeevan Smriti CoOperative Housing Society Ltd, hereby declare the following with respect to the project “SelfRedevelopment of Jeevan Smriti CHS Ltd” bearing registration number P51900033146 registered under MahaRERA 1. Status of Work Completed: We are pleased to inform you that we have completed the 100% of RCC (Reinforced Cement Concrete) work for the building. Currently, we are undertaking the Balance, finishing work, which includes plastering, flooring, electrical fittings, and other essential internal and external works. 2. Expected Timeline for Completion: We are…”31 July 2027
MahaRERA's automatic 4-month extension for all eligible projects, not the builder's request
Source: Self-Redevelopment of Jeevan Smriti CHS Ltd.’s extension records on MahaRERA (P51900033146), read by GharKundli in October 2026. The builder’s reasons are quoted as filed. Your own possession date is the one in your agreement for sale.
What builders tell MahaRERA when they’re late: 14,973 applications analysed →GharKundli’s full report on Self-Redevelopment of Jeevan Smriti CHS Ltd.
Read from every filing on MahaRERA when you open it
- Risk & trust score, every point explained
- What the title report says about the land
- Each complaint and court case, and how it ended
- Construction pace against the July 2027 deadline
- Agreement clauses weaker than the RERA model
- Escrow audit, loans and the builder's record
- Questions to get answered in writing before you pay
- MahaRERA registration
- P51900033146
- Status
- Registered and active
- Builder
- JEEVAN SMRITI CO-OPERATIVE HOUSING SOCIETY LTD.
- Location
- Pahadi, Goregaon, Mumbai · 400603
- Project type
- Residential / Group Housing
- Registered on
- 9 Feb 2022
- Completion date at registration
- December 2024
- Latest completion date
- July 2027
- Delay so far
- 27 months
- MahaRERA's automatic extension
- +4 months (force majeure, all eligible projects)
- Homes
- 21
- Sold or booked
- 100%
- Towers
- 1
- Complaints on MahaRERA
- 0
- Court cases listed
- 0
- Title report on file
- Not found
Construction progress of Self-Redevelopment of Jeevan Smriti CHS Ltd., as filed by the builder
What the builder has reported to MahaRERA, as GharKundli read it in October 2026. GharKundli’s full report compares it with the deadline.
| Tower / wing | Plinth | Slabs (structure) | Internal work | Lifts, fire & electrical |
|---|---|---|---|---|
| JEEVAN SMRITI | 100% | 100% | 90% | 75% |
Commencement certificate (CC), as filed on MahaRERA
Latest CC order on MahaRERA: dated 27/10/2023.
Want to know when this changes? Kundli Watch sends a free WhatsApp update on Self-Redevelopment of Jeevan Smriti CHS Ltd. every month.
Self-Redevelopment of Jeevan Smriti CHS Ltd.: buildings, flats and land, as filed on MahaRERA
| Type | Carpet area (sq ft) | Units |
|---|---|---|
| 2 BHK | 551 – 750 | 13 |
| 1 BHK | 400 – 421 | 7 |
| 3 BHK | 1,033 | 1 |
- Buildings: JEEVAN SMRITI (9 floors, 21 units)
- Car parking: 15 covered
- Land: 504 sq m (about 0.1 acres) · sanctioned built-up 1,252 sq m
The builder’s record and reviews
Not enough of this builder’s other MahaRERA projects have reached their promised date to judge yet.
Read Google reviews of Self-Redevelopment of Jeevan Smriti CHS Ltd. →Reviews on Google are opinions by Google users; GharKundli doesn’t check them.
Kundli Watch
Self-Redevelopment of Jeevan Smriti CHS Ltd.: buyers & owners
Free: a WhatsApp update every month on this project, and straight away when anything changes on MahaRERA — a later completion date, new complaints, a red flag. Your number stays private: never shown to other members or the builder.
Be the first to watch this project.
How are you connected to this project?
Bought here? No document needed now. From the builder’s team? Join to answer buyers’ questions; you never see members’ details. You’ll sign in with a one-time code, then come straight back here.
Common questions about Self-Redevelopment of Jeevan Smriti CHS Ltd.
What is the possession date of Self-Redevelopment of Jeevan Smriti CHS Ltd.?
According to GharKundli's check of MahaRERA records (updated October 2026), the latest completion date filed on MahaRERA for Self-Redevelopment of Jeevan Smriti CHS Ltd. in Pahadi, Goregaon, Mumbai is 31 July 2027 — 27 months later than 31 December 2024, the date given at registration, plus MahaRERA's automatic 4-month extension for all eligible projects.
Is the builder's possession date different from the MahaRERA date for Self-Redevelopment of Jeevan Smriti CHS Ltd.?
Builders and listing sites often quote an earlier "target" date for handover. The completion date Self-Redevelopment of Jeevan Smriti CHS Ltd.'s builder has filed on MahaRERA, the official one, is 31 July 2027, already 27 months later than the 31 December 2024 given at registration, per GharKundli's check of MahaRERA records. If possession is late, what counts under RERA (Section 18) is the possession date written in your agreement for sale.
Why was the possession date of Self-Redevelopment of Jeevan Smriti CHS Ltd. extended?
According to GharKundli's check of MahaRERA records (updated October 2026), Self-Redevelopment of Jeevan Smriti CHS Ltd.'s builder applied to MahaRERA to extend the completion date 2 times: to 31 December 2025, giving the reason "I, Mr. Prasanna Diwakar Samant, hereby declare the following with respect to the project “Self-Redevelopment of Jeevan Smriti CHS Ltd.” bearing registration number P51900033146 registered under MahaRERA Accordingly, we, along with our Project Management Consultant (PMC), prepared and submitted a proposal to secure financing from Mumbai District Central Co-op. Bank Limited, which was a viable funding source for self-redevelopment projects. However, during the COVID-19 pandemic, the Reserve Bank of India (RBI) imposed restrictions on Mumbai District Central Co-op. Bank Limited, preventing it…"; to 31 March 2027, giving the reason "Dear Sir/Ma’am, We, Jeevan Smriti CoOperative Housing Society Ltd, hereby declare the following with respect to the project “SelfRedevelopment of Jeevan Smriti CHS Ltd” bearing registration number P51900033146 registered under MahaRERA 1. Status of Work Completed: We are pleased to inform you that we have completed the 100% of RCC (Reinforced Cement Concrete) work for the building. Currently, we are undertaking the Balance, finishing work, which includes plastering, flooring, electrical fittings, and other essential internal and external works. 2. Expected Timeline for Completion: We are…". MahaRERA also added its automatic 4-month extension for all eligible projects.
What is the RERA number of Self-Redevelopment of Jeevan Smriti CHS Ltd.?
According to GharKundli's check of MahaRERA records (updated October 2026), the MahaRERA registration number of Self-Redevelopment of Jeevan Smriti CHS Ltd. in Pahadi, Goregaon, Mumbai is P51900033146.
Is Self-Redevelopment of Jeevan Smriti CHS Ltd. registered with MahaRERA?
According to GharKundli's check of MahaRERA records (updated October 2026), Self-Redevelopment of Jeevan Smriti CHS Ltd. is registered as P51900033146 and its status is "Registered and active".
What is the construction status of Self-Redevelopment of Jeevan Smriti CHS Ltd.?
According to GharKundli's check of MahaRERA records (updated October 2026), Self-Redevelopment of Jeevan Smriti CHS Ltd.'s status on MahaRERA is "Registered and active". As filed by the builder, slab work on JEEVAN SMRITI is 100% done and internal work 90%. GharKundli's full report compares construction progress with the deadline.
Does Self-Redevelopment of Jeevan Smriti CHS Ltd. have complaints on MahaRERA?
No complaints were listed on MahaRERA as of October 2026, per GharKundli's weekly check.
Is Self-Redevelopment of Jeevan Smriti CHS Ltd. safe to buy?
According to GharKundli's check of MahaRERA records (updated October 2026), Self-Redevelopment of Jeevan Smriti CHS Ltd. is registered on MahaRERA as P51900033146, its completion date has moved 27 months since registration and no complaints are listed against it. GharKundli doesn't call a project safe or unsafe from these numbers alone: its full report gives a risk & trust score with every point explained.
How can I get updates if Self-Redevelopment of Jeevan Smriti CHS Ltd.'s possession date changes?
The latest dates are on Self-Redevelopment of Jeevan Smriti CHS Ltd.'s MahaRERA page (P51900033146). GharKundli's Kundli Watch sends a free WhatsApp update on Self-Redevelopment of Jeevan Smriti CHS Ltd. every month, and straight away when anything changes on MahaRERA: a later completion date, new complaints or a red flag. Your number is never shown to the builder.
How many floors does Self-Redevelopment of Jeevan Smriti CHS Ltd. have?
According to GharKundli's check of MahaRERA records (updated October 2026), Self-Redevelopment of Jeevan Smriti CHS Ltd. has one building filed: JEEVAN SMRITI with 9 floors and 21 units.
What are the flat sizes (carpet area) in Self-Redevelopment of Jeevan Smriti CHS Ltd.?
According to GharKundli's check of MahaRERA records (updated October 2026), the builder has filed these homes for Self-Redevelopment of Jeevan Smriti CHS Ltd.: 2 BHK: 551 to 750 sq ft carpet (13 homes); 1 BHK: 400 to 421 sq ft carpet (7 homes); 3 BHK: 1033 sq ft carpet (1 homes). Carpet area is the usable floor area inside the walls, as defined under RERA.
How much parking does Self-Redevelopment of Jeevan Smriti CHS Ltd. have?
According to GharKundli's check of MahaRERA records (updated October 2026), the builder has filed 15 covered car parking spaces for Self-Redevelopment of Jeevan Smriti CHS Ltd..
How big is the land of Self-Redevelopment of Jeevan Smriti CHS Ltd.?
According to GharKundli's check of MahaRERA records (updated October 2026), Self-Redevelopment of Jeevan Smriti CHS Ltd. stands on 504 sq m of land (about 0.1 acres), with 1,252 sq m of sanctioned built-up area.
Where can I read reviews of Self-Redevelopment of Jeevan Smriti CHS Ltd.?
Google Maps has reviews of Self-Redevelopment of Jeevan Smriti CHS Ltd. written by Google users; GharKundli links to them on this page but doesn't check them. For facts rather than opinions: no complaints are listed on MahaRERA, and Kundli Watch shows verified owners of the project.
Where is Self-Redevelopment of Jeevan Smriti CHS Ltd.?
Self-Redevelopment of Jeevan Smriti CHS Ltd. by JEEVAN SMRITI CO-OPERATIVE HOUSING SOCIETY LTD. is in Pahadi, Goregaon, Mumbai (pincode 400603), Maharashtra, and is registered on MahaRERA as P51900033146, per GharKundli's check of MahaRERA records.
How many homes are in Self-Redevelopment of Jeevan Smriti CHS Ltd.?
According to GharKundli's check of MahaRERA records (updated October 2026), Self-Redevelopment of Jeevan Smriti CHS Ltd. has 21 homes in 1 tower registered on MahaRERA, and 100% of them are sold or booked.
When was Self-Redevelopment of Jeevan Smriti CHS Ltd. registered on MahaRERA?
According to GharKundli's check of MahaRERA records (updated October 2026), Self-Redevelopment of Jeevan Smriti CHS Ltd. was registered on MahaRERA on 9 February 2022. GharKundli did not find a title report on the land on file there.
Are there court cases on Self-Redevelopment of Jeevan Smriti CHS Ltd.?
No court cases are listed for Self-Redevelopment of Jeevan Smriti CHS Ltd. on MahaRERA, per GharKundli's check of MahaRERA records (updated October 2026).
Who is the builder of Self-Redevelopment of Jeevan Smriti CHS Ltd.?
According to GharKundli's check of MahaRERA records (updated October 2026), the builder is JEEVAN SMRITI CO-OPERATIVE HOUSING SOCIETY LTD..
Check it yourself on MahaRERA
- How to check the possession date of Self-Redevelopment of Jeevan Smriti CHS Ltd.
- How to find and verify a MahaRERA number
- How to check construction status on MahaRERA
- Occupancy certificate (OC): what to check before possession
- Possession delayed? Work out the interest the builder owes
- How to file a MahaRERA complaint against a builder
- Where MahaRERA complaints are: the data
- Why builders ask MahaRERA for more time: the data
All projects with possession due in 2027 in Thane →
Other projects in Borivali
- SAFFRONWOODS CHSL
- L&T Realty Ahana Tower B
- PARSHURAM HEIGHTS
- L&T Realty Ahana Tower A
- AVIRAHI ELEGANCE
- RASHMI ICON
- MARU MANSION
- SHRADDHA SKYLINE
Data compiled by GharKundli (gharkundli.com) from MahaRERA public records, as of October 2026. Check the project’s MahaRERA page for the latest filings. Not legal advice.