GSA GRANDEUR A and B Wing
by G S A CONSTRUCTIONS · PimpripadaMALAD East, Mumbai 400063Also near Goregaon East, Dindoshi malad east
What’s in the report? →Possession date of GSA GRANDEUR A and B Wing (MahaRERA P51800033045): 31 December 2027, moved from 31 December 2024 (36 months later). It has 37 homes (1 BHK and 2 BHK, 425–670 sq ft carpet), 80% sold or booked. No complaints on MahaRERA. How to check it yourself
Registered on MahaRERA under P51800033045, and currently active.
Source: MahaRERA website — records for P51800033045, read and compiled by GharKundli. Facts as filed on MahaRERA, no opinions.
What do you want to know about GSA GRANDEUR A and B Wing?
Title report MahaRERA par nahi dikh rahi. Kya poochna hai?Tap a question. We’ll answer you on WhatsApp, free.
How the possession date of GSA GRANDEUR A and B Wing has moved
31 December 2024
Completion date given when the project was registered
31 December 2027
Extended at the builder's request (MahaRERA application EA24122518952)
Reason the builder gave MahaRERA:
“a) Initially, we had an approved plan from Municipal Corporation of Greater Mumbai for Wing A only. Later on, we purchased adjacent plot admeasuring 389 Sq Mts and amalgamated the existing approved plan. b) We obtained the amalgamated plan…” Read the full reason
“a) Initially, we had an approved plan from Municipal Corporation of Greater Mumbai for Wing A only. Later on, we purchased adjacent plot admeasuring 389 Sq Mts and amalgamated the existing approved plan. b) We obtained the amalgamated plan for Wing A for 22 Floors and Wing B for 14 Floors. c) The amalgamation of approved plan with the local authority took around 6-8 Months approximately. d) The construction of Wing A is completed and applied for issue of occupancy certificate from local authority. e) We have applied for sanction of further Eight Floors i.e., 15th to 22nd Floors in Wing B to…”
Source: GSA GRANDEUR A and B Wing’s extension records on MahaRERA (P51800033045), read by GharKundli in October 2026. The builder’s reasons are quoted as filed. Your own possession date is the one in your agreement for sale.
What builders tell MahaRERA when they’re late: 14,973 applications analysed →GharKundli’s full report on GSA GRANDEUR A and B Wing
Read from every filing on MahaRERA when you open it
- Risk & trust score, every point explained
- What the title report says about the land
- Each complaint and court case, and how it ended
- Construction pace against the December 2027 deadline
- Agreement clauses weaker than the RERA model
- Escrow audit, loans and the builder's record
- Questions to get answered in writing before you pay
- MahaRERA registration
- P51800033045
- Status
- Registered and active
- Builder
- G S A CONSTRUCTIONS
- Location
- PimpripadaMALAD East, Mumbai · 400063
- Project type
- Residential / Group Housing
- Registered on
- 3 Feb 2022
- Completion date at registration
- December 2024
- Latest completion date
- December 2027
- Delay so far
- 36 months
- Homes
- 37
- Sold or booked
- 80%
- Towers
- 1
- Complaints on MahaRERA
- 0
- Court cases listed
- 0
- Title report on file
- Not found
- Builder's other MahaRERA projects
- 1
Construction progress of GSA GRANDEUR A and B Wing, as filed by the builder
What the builder has reported to MahaRERA, as GharKundli read it in October 2026. GharKundli’s full report compares it with the deadline.
| Tower / wing | Plinth | Slabs (structure) | Internal work | Lifts, fire & electrical |
|---|---|---|---|---|
| GSA GRANDEUR, B-WING | 100% | 48% | 35% | 5% |
Commencement certificate (CC), as filed on MahaRERA
- GSA GRANDEUR, B-WING: covers 21 floors
Want to know when this changes? Kundli Watch sends a free WhatsApp update on GSA GRANDEUR A and B Wing every 1–2 months.
GSA GRANDEUR A and B Wing: buildings, flats and land, as filed on MahaRERA
| Type | Carpet area (sq ft) | Units |
|---|---|---|
| 1 BHK | 425 | 19 |
| 2 BHK | 670 | 18 |
| Office Space | 425 | 1 |
- Buildings: GSA GRANDEUR, B-WING (27 floors, 38 units)
- Land: 389 sq m (about 0.1 acres) · sanctioned built-up 1,260 sq m · recreational space 58 sq m
- Land, as filed: CTS NO-610A/1A/1Apt, S NO-267, Hissa No1/1part
- Map: the location the builder filed on MahaRERA · Get directions
The builder’s record and reviews
G S A Constructions has 2 projects on MahaRERA since 2017, this one included. Of the 2 GharKundli has checked: 2 still being built, 2 past the promised date (typically 37 months late). 3 complaints on MahaRERA across 1 project.
Read Google reviews of GSA GRANDEUR A and B Wing →Reviews on Google are opinions by Google users; GharKundli doesn’t check them.
Kundli Watch
GSA GRANDEUR A and B Wing: buyers & owners
Free: a construction progress update on WhatsApp every 1–2 months, and straight away when anything changes on MahaRERA — a later completion date, new complaints, a red flag. Your number stays private: never shown to other members or the builder.
Be the first to watch this project.
How are you connected to this project?
Watching needs only WhatsApp or your number. Bought here? No document needed now. From the builder’s team? Join to answer buyers’ questions; you never see members’ details. Owners and the builder’s team sign in with a one-time code, then come straight back here.
Common questions about GSA GRANDEUR A and B Wing
What is the possession date of GSA GRANDEUR A and B Wing?
According to GharKundli's check of MahaRERA records (updated October 2026), the latest completion date filed on MahaRERA for GSA GRANDEUR A and B Wing in PimpripadaMALAD East, Mumbai is 31 December 2027 — 36 months later than 31 December 2024, the date given at registration.
The date has already moved 36 months. Will it move again? Check the real pace of construction →
Is the builder's possession date different from the MahaRERA date for GSA GRANDEUR A and B Wing?
Builders and listing sites often quote an earlier "target" date for handover. The completion date GSA GRANDEUR A and B Wing's builder has filed on MahaRERA, the official one, is 31 December 2027, already 36 months later than the 31 December 2024 given at registration, per GharKundli's check of MahaRERA records. If possession is late, what counts under RERA (Section 18) is the possession date written in your agreement for sale.
Why was the possession date of GSA GRANDEUR A and B Wing extended?
According to GharKundli's check of MahaRERA records (updated October 2026), GSA GRANDEUR A and B Wing's builder applied to MahaRERA to extend the completion date once: to 31 December 2027, giving the reason "a) Initially, we had an approved plan from Municipal Corporation of Greater Mumbai for Wing A only. Later on, we purchased adjacent plot admeasuring 389 Sq Mts and amalgamated the existing approved plan. b) We obtained the amalgamated plan for Wing A for 22 Floors and Wing B for 14 Floors. c) The amalgamation of approved plan with the local authority took around 6-8 Months approximately. d) The construction of Wing A is completed and applied for issue of occupancy certificate from local authority. e) We have applied for sanction of further Eight Floors i.e., 15th to 22nd Floors in Wing B to…".
What is the RERA number of GSA GRANDEUR A and B Wing?
According to GharKundli's check of MahaRERA records (updated October 2026), the MahaRERA registration number of GSA GRANDEUR A and B Wing in PimpripadaMALAD East, Mumbai is P51800033045.
Is GSA GRANDEUR A and B Wing registered with MahaRERA?
According to GharKundli's check of MahaRERA records (updated October 2026), GSA GRANDEUR A and B Wing is registered as P51800033045 and its status is "Registered and active".
What is the current construction status of GSA GRANDEUR A and B Wing? How much work is done?
According to GharKundli's check of MahaRERA records (updated October 2026), GSA GRANDEUR A and B Wing's status on MahaRERA is "Registered and active". As filed by the builder, slab work on GSA GRANDEUR, B-WING is 48% done and internal work 35%. GharKundli's full report compares construction progress with the deadline.
Does GSA GRANDEUR A and B Wing have complaints on MahaRERA?
No complaints were listed on MahaRERA as of October 2026, per GharKundli's weekly check.
Is GSA GRANDEUR A and B Wing safe to buy?
According to GharKundli's check of MahaRERA records (updated October 2026), GSA GRANDEUR A and B Wing is registered on MahaRERA as P51800033045, its completion date has moved 36 months since registration and no complaints are listed against it. GharKundli doesn't call a project safe or unsafe from these numbers alone: its full report gives a risk & trust score with every point explained.
How much GST is payable on a flat in GSA GRANDEUR A and B Wing?
GSA GRANDEUR A and B Wing is under construction, so GST applies to a new flat: 5% of the price, with no input tax credit. The lower 1% rate is only for "affordable" homes: carpet area up to 60 sq m (about 646 sq ft) in the Mumbai region, and price up to ₹45 lakh. Some flats in GSA GRANDEUR A and B Wing are 425 sq ft carpet, small enough for 1% if the price is ₹45 lakh or less. There is no GST on stamp duty or registration, and none once the occupancy certificate is issued.
What is the stamp duty and registration cost for a flat in GSA GRANDEUR A and B Wing?
For a flat in GSA GRANDEUR A and B Wing (Mumbai), stamp duty is 6% of the agreement value, or of the ready reckoner value if that's higher, including 1% Metro Cess. A woman buying in her own name pays 5%. Registration is 1% of the value, capped at ₹30,000. On a ₹1 crore flat that's about ₹6 lakh in stamp duty plus ₹30,000 registration. GharKundli's property cost calculator works it out for your price: gharkundli.com/tools/property-cost-calculator
Has GSA GRANDEUR A and B Wing received its OC? Is it ready to move in?
Not yet. According to GharKundli's check of MahaRERA records (updated October 2026), GSA GRANDEUR A and B Wing is still under construction, with 31 December 2027 as the latest completion date filed on MahaRERA. A flat is ready to move in only once the occupancy certificate (OC) is issued, after construction is complete.
Is GSA GRANDEUR A and B Wing a redevelopment or SRA project?
According to GharKundli's check of MahaRERA records (updated October 2026), GSA GRANDEUR A and B Wing is a redevelopment: 11 of its flats are set aside for existing occupants (rehab), and the rest are for sale.
Has GSA GRANDEUR A and B Wing uploaded its title report on MahaRERA?
According to GharKundli's check of MahaRERA records (updated October 2026), no title report for GSA GRANDEUR A and B Wing was found on MahaRERA. Builders are expected to upload one; before booking, ask the builder for the advocate's title certificate in writing.
No title report is on MahaRERA for this project. See which documents are missing →
How can I get updates if GSA GRANDEUR A and B Wing's possession date changes?
The latest dates are on GSA GRANDEUR A and B Wing's MahaRERA page (P51800033045). GharKundli's Kundli Watch sends a free WhatsApp update on GSA GRANDEUR A and B Wing every 1–2 months, and straight away when anything changes on MahaRERA: a later completion date, new complaints or a red flag. Your number is never shown to the builder.
How many floors does GSA GRANDEUR A and B Wing have?
According to GharKundli's check of MahaRERA records (updated October 2026), GSA GRANDEUR A and B Wing has one building filed: GSA GRANDEUR, B-WING with 27 floors and 38 units.
What are the flat sizes (carpet area) in GSA GRANDEUR A and B Wing?
According to GharKundli's check of MahaRERA records (updated October 2026), the builder has filed these homes for GSA GRANDEUR A and B Wing: 1 BHK: 425 sq ft carpet (19 homes); 2 BHK: 670 sq ft carpet (18 homes). Carpet area is the usable floor area inside the walls, as defined under RERA.
How big is the land of GSA GRANDEUR A and B Wing?
According to GharKundli's check of MahaRERA records (updated October 2026), GSA GRANDEUR A and B Wing stands on 389 sq m of land (about 0.1 acres), with 1,260 sq m of sanctioned built-up area and 58 sq m of recreational open space.
What is the track record of GSA GRANDEUR A and B Wing's builder?
According to GharKundli's check of MahaRERA records (updated October 2026), G S A Constructions has 2 projects on MahaRERA since 2017, this one included. Of the 2 GharKundli has checked: 2 still being built, 2 past the promised date (typically 37 months late). 3 complaints on MahaRERA across 1 project. GharKundli's full report covers the builder's record in detail.
What are the reviews of GSA GRANDEUR A and B Wing?
Google Maps has reviews of GSA GRANDEUR A and B Wing written by Google users; GharKundli links to them on this page but doesn't check them. For facts rather than opinions: no complaints are listed on MahaRERA, and Kundli Watch shows verified owners of the project.
What is the address and pincode of GSA GRANDEUR A and B Wing?
GSA GRANDEUR A and B Wing by G S A CONSTRUCTIONS is in PimpripadaMALAD East, Mumbai, pincode 400063 (near Goregaon East, Dindoshi malad east), Maharashtra, and is registered on MahaRERA as P51800033045, per GharKundli's check of MahaRERA records. Its land is filed as CTS NO-610A/1A/1Apt, S NO-267, Hissa No1/1part. GharKundli lists all 151 MahaRERA projects in Goregaon East (400063).
How many flats are in GSA GRANDEUR A and B Wing, and how many are sold?
According to GharKundli's check of MahaRERA records (updated October 2026), GSA GRANDEUR A and B Wing has 37 homes in 1 tower registered on MahaRERA, and 80% of them are sold or booked.
When was GSA GRANDEUR A and B Wing registered on MahaRERA?
According to GharKundli's check of MahaRERA records (updated October 2026), GSA GRANDEUR A and B Wing was registered on MahaRERA on 3 February 2022. GharKundli did not find a title report on the land on file there.
Does GSA GRANDEUR A and B Wing have any legal issues or court cases?
No court cases are listed for GSA GRANDEUR A and B Wing on MahaRERA, per GharKundli's check of MahaRERA records (updated October 2026).
Who is the builder / developer of GSA GRANDEUR A and B Wing?
According to GharKundli's check of MahaRERA records (updated October 2026), the builder is G S A CONSTRUCTIONS, which has 1 other project registered on MahaRERA.
Check it yourself on MahaRERA
- How to check the possession date of GSA GRANDEUR A and B Wing
- How to find and verify a MahaRERA number
- How to check construction status on MahaRERA
- Occupancy certificate (OC): what to check before possession
- Possession delayed? Work out the interest the builder owes
- How to file a MahaRERA complaint against a builder
- Where MahaRERA complaints are: the data
- Why builders ask MahaRERA for more time: the data
All projects with possession due in 2027 in Mumbai Suburban →
Other projects in Borivali
- Saffronwoods CHSL
- Parshuram Heights
- Avirahi Elegance
- L&T Realty Ahana Tower A
- L&T Realty Ahana Tower B
- Rashmi Icon
- Shraddha Skyline
- LA SERENA Tower 5, Tower 6 and Tower 7
Other projects by G S A CONSTRUCTIONS
Data compiled by GharKundli (gharkundli.com) from MahaRERA public records, as of October 2026. Check the project’s MahaRERA page for the latest filings. Not legal advice.