ATTHIS at L and T Realty Elixir Reserve
by Larsen & Toubro Ltd. (Realty Division) · Powai, Mumbai
Possession date of ATTHIS at L and T Realty Elixir Reserve: 30 September 2027, moved from 30 June 2025 (23 months later). This is the latest completion date the builder has filed on MahaRERA. How to check it yourself
Registered on MahaRERA under P51800033618, and currently active. Its completion date has moved from June 2025 to September 2027: 23 months at the builder's request, plus MahaRERA's automatic 4-month extension for all eligible projects. 1 complaint is listed against it on MahaRERA.
Source: GharKundli’s check of MahaRERA records, October 2026.
What do you want to know about ATTHIS at L and T Realty Elixir Reserve?
How the possession date of ATTHIS at L and T Realty Elixir Reserve has moved
30 June 2025
Completion date given when the project was registered
31 May 2027
Extended at the builder's request (MahaRERA application EA05052620832)
Reason the builder gave MahaRERA: “I state that the completion work of the said project had been delayed beyond project completion date due to certain common infrastructure work which are being executed and certain mitigating circumstance”
30 September 2027
MahaRERA's automatic 4-month extension for all eligible projects, not the builder's request
Source: ATTHIS at L and T Realty Elixir Reserve’s extension records on MahaRERA (P51800033618), read by GharKundli in October 2026. The builder’s reasons are quoted as filed. Your own possession date is the one in your agreement for sale.
What builders tell MahaRERA when they’re late: 14,973 applications analysed →GharKundli’s full report on ATTHIS at L and T Realty Elixir Reserve
Read from every filing on MahaRERA when you open it
- Risk & trust score, every point explained
- What the title report says about the land
- Each of the 1 complaint and 2 court cases, and how it ended
- Construction pace against the September 2027 deadline
- Agreement clauses weaker than the RERA model
- Escrow audit, loans and the builder's record
- Questions to get answered in writing before you pay
- MahaRERA registration
- P51800033618
- Status
- Registered and active
- Builder
- Larsen & Toubro Ltd. (Realty Division)
- Location
- Powai, Mumbai · 400072
- Project type
- Residential / Group Housing
- Registered on
- 2 Mar 2022
- Completion date at registration
- June 2025
- Latest completion date
- September 2027
- Delay so far
- 23 months
- MahaRERA's automatic extension
- +4 months (force majeure, all eligible projects)
- Homes
- 190
- Sold or booked
- 87%
- Towers
- 1
- Complaints on MahaRERA
- 1
- Court cases listed
- 2
- Title report on file
- Not found
- Builder's other MahaRERA projects
- 24
Construction progress of ATTHIS at L and T Realty Elixir Reserve, as filed by the builder
What the builder has reported to MahaRERA, as GharKundli read it in October 2026. GharKundli’s full report compares it with the deadline.
| Tower / wing | Plinth | Slabs (structure) | Internal work | Lifts, fire & electrical |
|---|---|---|---|---|
| ATTHIS at L and T Realty Elixir Reserve | 100% | 100% | 50% | 80% |
Commencement certificate (CC), as filed on MahaRERA
- ATTHIS at L and T Realty Elixir Reserve: covers 9 floors
Want to know when this changes? Kundli Watch sends a free WhatsApp update on ATTHIS at L and T Realty Elixir Reserve every month.
ATTHIS at L and T Realty Elixir Reserve: buildings, flats and land, as filed on MahaRERA
| Type | Carpet area (sq ft) | Units |
|---|---|---|
| 2 BHK | 632 – 1,708 | 142 |
| 3 BHK | 996 | 48 |
- Buildings: ATTHIS at L and T Realty Elixir Reserve (31 floors, 190 units)
- Land: 998 sq m (about 0.2 acres) · sanctioned built-up 16,899 sq m
The builder’s record and reviews
Larsen & Toubro Ltd Realty Division (a group of 3 linked companies) has 38 projects on MahaRERA since 2017, this one included. Of the 38 GharKundli has checked: 10 finished, 9 within the promised date and 1 needed more time (typically 5 months); 25 still being built, 5 past the promised date (typically 12 months late); 3 lapsed. 93 complaints on MahaRERA across 18 projects.
Read Google reviews of ATTHIS at L and T Realty Elixir Reserve →Reviews on Google are opinions by Google users; GharKundli doesn’t check them.
Kundli Watch
ATTHIS at L and T Realty Elixir Reserve: buyers & owners
Free: a WhatsApp update every month on this project, and straight away when anything changes on MahaRERA — a later completion date, new complaints, a red flag. Your number stays private: never shown to other members or the builder.
Be the first to watch this project.
How are you connected to this project?
Bought here? No document needed now. From the builder’s team? Join to answer buyers’ questions; you never see members’ details. You’ll sign in with a one-time code, then come straight back here.
Common questions about ATTHIS at L and T Realty Elixir Reserve
What is the possession date of ATTHIS at L and T Realty Elixir Reserve?
According to GharKundli's check of MahaRERA records (updated October 2026), the latest completion date filed on MahaRERA for ATTHIS at L and T Realty Elixir Reserve in Powai, Mumbai is 30 September 2027 — 23 months later than 30 June 2025, the date given at registration, plus MahaRERA's automatic 4-month extension for all eligible projects.
Is the builder's possession date different from the MahaRERA date for ATTHIS at L and T Realty Elixir Reserve?
Builders and listing sites often quote an earlier "target" date for handover. The completion date ATTHIS at L and T Realty Elixir Reserve's builder has filed on MahaRERA, the official one, is 30 September 2027, already 23 months later than the 30 June 2025 given at registration, per GharKundli's check of MahaRERA records. If possession is late, what counts under RERA (Section 18) is the possession date written in your agreement for sale.
Why was the possession date of ATTHIS at L and T Realty Elixir Reserve extended?
According to GharKundli's check of MahaRERA records (updated October 2026), ATTHIS at L and T Realty Elixir Reserve's builder applied to MahaRERA to extend the completion date once: to 31 May 2027, giving the reason "I state that the completion work of the said project had been delayed beyond project completion date due to certain common infrastructure work which are being executed and certain mitigating circumstance". MahaRERA also added its automatic 4-month extension for all eligible projects.
What is the RERA number of ATTHIS at L and T Realty Elixir Reserve?
According to GharKundli's check of MahaRERA records (updated October 2026), the MahaRERA registration number of ATTHIS at L and T Realty Elixir Reserve in Powai, Mumbai is P51800033618.
Is ATTHIS at L and T Realty Elixir Reserve registered with MahaRERA?
According to GharKundli's check of MahaRERA records (updated October 2026), ATTHIS at L and T Realty Elixir Reserve is registered as P51800033618 and its status is "Registered and active".
What is the construction status of ATTHIS at L and T Realty Elixir Reserve?
According to GharKundli's check of MahaRERA records (updated October 2026), ATTHIS at L and T Realty Elixir Reserve's status on MahaRERA is "Registered and active". As filed by the builder, slab work on ATTHIS at L and T Realty Elixir Reserve is 100% done and internal work 50%. GharKundli's full report compares construction progress with the deadline.
Does ATTHIS at L and T Realty Elixir Reserve have complaints on MahaRERA?
1 complaint was listed on MahaRERA as of October 2026, per GharKundli's weekly check. GharKundli's full report explains each case and how it ended.
Is ATTHIS at L and T Realty Elixir Reserve safe to buy?
According to GharKundli's check of MahaRERA records (updated October 2026), ATTHIS at L and T Realty Elixir Reserve is registered on MahaRERA as P51800033618, its completion date has moved 23 months since registration and 1 complaint is listed against it. GharKundli doesn't call a project safe or unsafe from these numbers alone: its full report gives a risk & trust score with every point explained.
How can I get updates if ATTHIS at L and T Realty Elixir Reserve's possession date changes?
The latest dates are on ATTHIS at L and T Realty Elixir Reserve's MahaRERA page (P51800033618). GharKundli's Kundli Watch sends a free WhatsApp update on ATTHIS at L and T Realty Elixir Reserve every month, and straight away when anything changes on MahaRERA: a later completion date, new complaints or a red flag. Your number is never shown to the builder.
How many floors does ATTHIS at L and T Realty Elixir Reserve have?
According to GharKundli's check of MahaRERA records (updated October 2026), ATTHIS at L and T Realty Elixir Reserve has one building filed: ATTHIS at L and T Realty Elixir Reserve with 31 floors and 190 units.
What are the flat sizes (carpet area) in ATTHIS at L and T Realty Elixir Reserve?
According to GharKundli's check of MahaRERA records (updated October 2026), the builder has filed these homes for ATTHIS at L and T Realty Elixir Reserve: 2 BHK: 632 to 1708 sq ft carpet (142 homes); 3 BHK: 996 sq ft carpet (48 homes). Carpet area is the usable floor area inside the walls, as defined under RERA.
How big is the land of ATTHIS at L and T Realty Elixir Reserve?
According to GharKundli's check of MahaRERA records (updated October 2026), ATTHIS at L and T Realty Elixir Reserve stands on 998 sq m of land (about 0.2 acres), with 16,899 sq m of sanctioned built-up area.
What is the track record of ATTHIS at L and T Realty Elixir Reserve's builder?
According to GharKundli's check of MahaRERA records (updated October 2026), Larsen & Toubro Ltd Realty Division (a group of 3 linked companies) has 38 projects on MahaRERA since 2017, this one included. Of the 38 GharKundli has checked: 10 finished, 9 within the promised date and 1 needed more time (typically 5 months); 25 still being built, 5 past the promised date (typically 12 months late); 3 lapsed. 93 complaints on MahaRERA across 18 projects. GharKundli's full report covers the builder's record in detail.
Where can I read reviews of ATTHIS at L and T Realty Elixir Reserve?
Google Maps has reviews of ATTHIS at L and T Realty Elixir Reserve written by Google users; GharKundli links to them on this page but doesn't check them. For facts rather than opinions: 1 complaint is listed on MahaRERA, and Kundli Watch shows verified owners of the project.
Where is ATTHIS at L and T Realty Elixir Reserve?
ATTHIS at L and T Realty Elixir Reserve by Larsen & Toubro Ltd. (Realty Division) is in Powai, Mumbai (pincode 400072), Maharashtra, and is registered on MahaRERA as P51800033618, per GharKundli's check of MahaRERA records.
How many homes are in ATTHIS at L and T Realty Elixir Reserve?
According to GharKundli's check of MahaRERA records (updated October 2026), ATTHIS at L and T Realty Elixir Reserve has 190 homes in 1 tower registered on MahaRERA, and 87% of them are sold or booked.
When was ATTHIS at L and T Realty Elixir Reserve registered on MahaRERA?
According to GharKundli's check of MahaRERA records (updated October 2026), ATTHIS at L and T Realty Elixir Reserve was registered on MahaRERA on 2 March 2022. GharKundli did not find a title report on the land on file there.
Are there court cases on ATTHIS at L and T Realty Elixir Reserve?
2 court cases are listed for ATTHIS at L and T Realty Elixir Reserve on MahaRERA, per GharKundli's check of MahaRERA records (updated October 2026). GharKundli's full report explains each case and how it ended.
Who is the builder of ATTHIS at L and T Realty Elixir Reserve?
According to GharKundli's check of MahaRERA records (updated October 2026), the builder is Larsen & Toubro Ltd. (Realty Division), which has 24 other projects registered on MahaRERA.
Check it yourself on MahaRERA
- How to check the possession date of ATTHIS at L and T Realty Elixir Reserve
- How to find and verify a MahaRERA number
- How to check construction status on MahaRERA
- Occupancy certificate (OC): what to check before possession
- Possession delayed? Work out the interest the builder owes
- How to file a MahaRERA complaint against a builder
- Where MahaRERA complaints are: the data
- Why builders ask MahaRERA for more time: the data
All projects with possession due in 2027 in Mumbai Suburban →
Other projects in Powai
- Heritage Lakeside
- Hiranandani Westgate - Hampstead
- Veridian at Emerald Isle 13A and 13B
- Veridian at Emerald Isle 14A and 14B
- Veridian at Emerald Isle 12C
- IBIS at L and T Realty Elixir Reserve
- Vascon Tranquil Heights
- Lodha Bellagio-Tower D
Other projects by Larsen & Toubro Ltd. (Realty Division)
Data compiled by GharKundli (gharkundli.com) from MahaRERA public records, as of October 2026. Check the project’s MahaRERA page for the latest filings. Not legal advice.