SHEPHERD HORIZON
by GOODBUILD INDIA PRIVATE LIMITED · Varsova, Mumbai
Possession date of SHEPHERD HORIZON: 30 November 2027, moved from 31 July 2025 (24 months later). This is the latest completion date the builder has filed on MahaRERA. How to check it yourself
Registered on MahaRERA under P51800046622, and currently active. Its completion date has moved from July 2025 to November 2027: 24 months at the builder's request, plus MahaRERA's automatic 4-month extension for all eligible projects.
Source: GharKundli’s check of MahaRERA records, October 2026.
What do you want to know about SHEPHERD HORIZON?
How the possession date of SHEPHERD HORIZON has moved
31 July 2025
Completion date given when the project was registered
30 July 2026
Extended at the builder's request (MahaRERA application EA26062501736)
Reason the builder gave MahaRERA: “Delay in Obtaining Permissions from MHADA”
30 July 2027
Extended at the builder's request (MahaRERA application EA25072621868)
Reason the builder gave MahaRERA: “Delay in Obtaining Permissions from MHADA”
30 November 2027
MahaRERA's automatic 4-month extension for all eligible projects, not the builder's request
Source: SHEPHERD HORIZON’s extension records on MahaRERA (P51800046622), read by GharKundli in October 2026. The builder’s reasons are quoted as filed. Your own possession date is the one in your agreement for sale.
What builders tell MahaRERA when they’re late: 14,973 applications analysed →GharKundli’s full report on SHEPHERD HORIZON
Read from every filing on MahaRERA when you open it
- Risk & trust score, every point explained
- What the title report says about the land
- Each of the 1 court case, and how it ended
- Construction pace against the November 2027 deadline
- Agreement clauses weaker than the RERA model
- Escrow audit, loans and the builder's record
- Questions to get answered in writing before you pay
- MahaRERA registration
- P51800046622
- Status
- Registered and active
- Builder
- GOODBUILD INDIA PRIVATE LIMITED
- Location
- Varsova, Mumbai · 400058
- Project type
- Residential / Group Housing
- Registered on
- 25 Aug 2022
- Completion date at registration
- July 2025
- Latest completion date
- November 2027
- Delay so far
- 24 months
- MahaRERA's automatic extension
- +4 months (force majeure, all eligible projects)
- Homes
- 78
- Sold or booked
- 44%
- Towers
- 1
- Complaints on MahaRERA
- 0
- Court cases listed
- 1
- Title report on file
- Not found
Construction progress of SHEPHERD HORIZON, as filed by the builder
What the builder has reported to MahaRERA, as GharKundli read it in October 2026. GharKundli’s full report compares it with the deadline.
| Tower / wing | Plinth | Slabs (structure) | Internal work | Lifts, fire & electrical |
|---|---|---|---|---|
| VARSOVA ANDHERI VASUNDHARA CHSL | 100% | 95% | 95% | 85% |
Commencement certificate (CC), as filed on MahaRERA
- VARSOVA ANDHERI VASUNDHARA CHSL: covers 20 Part CC
Want to know when this changes? Kundli Watch sends a free WhatsApp update on SHEPHERD HORIZON every month.
SHEPHERD HORIZON: buildings, flats and land, as filed on MahaRERA
| Type | Carpet area (sq ft) | Units |
|---|---|---|
| 1 BHK | 400 – 504 | 52 |
| 2 BHK | 650 – 7,007 | 26 |
- Buildings: VARSOVA ANDHERI VASUNDHARA CHSL (25 floors, 78 units)
- Land: 1,169 sq m (about 0.3 acres) · sanctioned built-up 6,328 sq m
The builder’s record and reviews
Goodbuild has 2 projects on MahaRERA since 2017, this one included. Of the 2 GharKundli has checked: 1 still being built, 1 past the promised date (typically 11 months late); 1 lapsed. 1 complaint on MahaRERA across 1 project.
Read Google reviews of SHEPHERD HORIZON →Reviews on Google are opinions by Google users; GharKundli doesn’t check them.
Kundli Watch
SHEPHERD HORIZON: buyers & owners
Free: a WhatsApp update every month on this project, and straight away when anything changes on MahaRERA — a later completion date, new complaints, a red flag. Your number stays private: never shown to other members or the builder.
Be the first to watch this project.
How are you connected to this project?
Bought here? No document needed now. From the builder’s team? Join to answer buyers’ questions; you never see members’ details. You’ll sign in with a one-time code, then come straight back here.
Common questions about SHEPHERD HORIZON
What is the possession date of SHEPHERD HORIZON?
According to GharKundli's check of MahaRERA records (updated October 2026), the latest completion date filed on MahaRERA for SHEPHERD HORIZON in Varsova, Mumbai is 30 November 2027 — 24 months later than 31 July 2025, the date given at registration, plus MahaRERA's automatic 4-month extension for all eligible projects.
Is the builder's possession date different from the MahaRERA date for SHEPHERD HORIZON?
Builders and listing sites often quote an earlier "target" date for handover. The completion date SHEPHERD HORIZON's builder has filed on MahaRERA, the official one, is 30 November 2027, already 24 months later than the 31 July 2025 given at registration, per GharKundli's check of MahaRERA records. If possession is late, what counts under RERA (Section 18) is the possession date written in your agreement for sale.
Why was the possession date of SHEPHERD HORIZON extended?
According to GharKundli's check of MahaRERA records (updated October 2026), SHEPHERD HORIZON's builder applied to MahaRERA to extend the completion date 2 times: to 30 July 2026, giving the reason "Delay in Obtaining Permissions from MHADA"; to 30 July 2027, giving the reason "Delay in Obtaining Permissions from MHADA". MahaRERA also added its automatic 4-month extension for all eligible projects.
What is the RERA number of SHEPHERD HORIZON?
According to GharKundli's check of MahaRERA records (updated October 2026), the MahaRERA registration number of SHEPHERD HORIZON in Varsova, Mumbai is P51800046622.
Is SHEPHERD HORIZON registered with MahaRERA?
According to GharKundli's check of MahaRERA records (updated October 2026), SHEPHERD HORIZON is registered as P51800046622 and its status is "Registered and active".
What is the construction status of SHEPHERD HORIZON?
According to GharKundli's check of MahaRERA records (updated October 2026), SHEPHERD HORIZON's status on MahaRERA is "Registered and active". As filed by the builder, slab work on VARSOVA ANDHERI VASUNDHARA CHSL is 95% done and internal work 95%. GharKundli's full report compares construction progress with the deadline.
Does SHEPHERD HORIZON have complaints on MahaRERA?
No complaints were listed on MahaRERA as of October 2026, per GharKundli's weekly check.
Is SHEPHERD HORIZON safe to buy?
According to GharKundli's check of MahaRERA records (updated October 2026), SHEPHERD HORIZON is registered on MahaRERA as P51800046622, its completion date has moved 24 months since registration and no complaints are listed against it. GharKundli doesn't call a project safe or unsafe from these numbers alone: its full report gives a risk & trust score with every point explained.
How can I get updates if SHEPHERD HORIZON's possession date changes?
The latest dates are on SHEPHERD HORIZON's MahaRERA page (P51800046622). GharKundli's Kundli Watch sends a free WhatsApp update on SHEPHERD HORIZON every month, and straight away when anything changes on MahaRERA: a later completion date, new complaints or a red flag. Your number is never shown to the builder.
How many floors does SHEPHERD HORIZON have?
According to GharKundli's check of MahaRERA records (updated October 2026), SHEPHERD HORIZON has one building filed: VARSOVA ANDHERI VASUNDHARA CHSL with 25 floors and 78 units.
What are the flat sizes (carpet area) in SHEPHERD HORIZON?
According to GharKundli's check of MahaRERA records (updated October 2026), the builder has filed these homes for SHEPHERD HORIZON: 1 BHK: 400 to 504 sq ft carpet (52 homes); 2 BHK: 650 to 7007 sq ft carpet (26 homes). Carpet area is the usable floor area inside the walls, as defined under RERA.
How big is the land of SHEPHERD HORIZON?
According to GharKundli's check of MahaRERA records (updated October 2026), SHEPHERD HORIZON stands on 1,169 sq m of land (about 0.3 acres), with 6,328 sq m of sanctioned built-up area.
What is the track record of SHEPHERD HORIZON's builder?
According to GharKundli's check of MahaRERA records (updated October 2026), Goodbuild has 2 projects on MahaRERA since 2017, this one included. Of the 2 GharKundli has checked: 1 still being built, 1 past the promised date (typically 11 months late); 1 lapsed. 1 complaint on MahaRERA across 1 project. GharKundli's full report covers the builder's record in detail.
Where can I read reviews of SHEPHERD HORIZON?
Google Maps has reviews of SHEPHERD HORIZON written by Google users; GharKundli links to them on this page but doesn't check them. For facts rather than opinions: no complaints are listed on MahaRERA, and Kundli Watch shows verified owners of the project.
Where is SHEPHERD HORIZON?
SHEPHERD HORIZON by GOODBUILD INDIA PRIVATE LIMITED is in Varsova, Mumbai (pincode 400058), Maharashtra, and is registered on MahaRERA as P51800046622, per GharKundli's check of MahaRERA records.
How many homes are in SHEPHERD HORIZON?
According to GharKundli's check of MahaRERA records (updated October 2026), SHEPHERD HORIZON has 78 homes in 1 tower registered on MahaRERA, and 44% of them are sold or booked.
When was SHEPHERD HORIZON registered on MahaRERA?
According to GharKundli's check of MahaRERA records (updated October 2026), SHEPHERD HORIZON was registered on MahaRERA on 25 August 2022. GharKundli did not find a title report on the land on file there.
Are there court cases on SHEPHERD HORIZON?
1 court case is listed for SHEPHERD HORIZON on MahaRERA, per GharKundli's check of MahaRERA records (updated October 2026). GharKundli's full report explains each case and how it ended.
Who is the builder of SHEPHERD HORIZON?
According to GharKundli's check of MahaRERA records (updated October 2026), the builder is GOODBUILD INDIA PRIVATE LIMITED.
Check it yourself on MahaRERA
- How to check the possession date of SHEPHERD HORIZON
- How to find and verify a MahaRERA number
- How to check construction status on MahaRERA
- Occupancy certificate (OC): what to check before possession
- Possession delayed? Work out the interest the builder owes
- How to file a MahaRERA complaint against a builder
- Where MahaRERA complaints are: the data
- Why builders ask MahaRERA for more time: the data
All projects with possession due in 2027 in Mumbai Suburban →
Other projects in Andheri
- SHRADDHA WEST RESIDENCY
- Green Bay
- SHIVSAI SRA CHS
- Live Well Chs Ltd
- THERESE
- FIONA GARDEN
- Pruthvi Symphony
- KK 415 WEST
Data compiled by GharKundli (gharkundli.com) from MahaRERA public records, as of October 2026. Check the project’s MahaRERA page for the latest filings. Not legal advice.