by QUBA INFRA LLP · Malad East, MumbaiAlso near Mulund West, Santacruz East, Ghatkopar East

Possession date of 104 EAST: 30 June 2027, moved from 31 December 2024 (30 months later). This is the latest completion date the builder has filed on MahaRERA. How to check it yourself

Registered on MahaRERA under P51800035079, and currently active.

Source: GharKundli’s check of MahaRERA records, October 2026.

What do you want to know about 104 EAST?

Ask us on WhatsAppNo login needed. A real person replies.

How the possession date of 104 EAST has moved

  1. 31 December 2024

    Completion date given when the project was registered

  2. 31 December 2025

    Extended at the builder's request (MahaRERA application EXT51800027337)

    Reason the builder gave MahaRERA: “Ammendment in plan”
  3. 30 June 2027

    Extended at the builder's request (MahaRERA application EA22012619548)

    Reason the builder gave MahaRERA: “Delayed in obtaining approval”

Source: 104 EAST’s extension records on MahaRERA (P51800035079), read by GharKundli in October 2026. The builder’s reasons are quoted as filed. Your own possession date is the one in your agreement for sale.

What builders tell MahaRERA when they’re late: 14,973 applications analysed →

GharKundli’s full report on 104 EAST

Read from every filing on MahaRERA when you open it

  • Risk & trust score, every point explained
  • What the title report says about the land
  • Each complaint and court case, and how it ended
  • Construction pace against the June 2027 deadline
  • Agreement clauses weaker than the RERA model
  • Escrow audit, loans and the builder's record
  • Questions to get answered in writing before you pay
MahaRERA registration
P51800035079
Status
Registered and active
Builder
QUBA INFRA LLP
Location
Malad East, Mumbai · 400063
Project type
Commercial
Registered on
4 May 2022
Completion date at registration
December 2024
Latest completion date
June 2027
Delay so far
30 months
Homes
0
Sold or booked
73%
Towers
1
Complaints on MahaRERA
0
Court cases listed
0
Title report on file
Not found

Construction progress of 104 EAST, as filed by the builder

What the builder has reported to MahaRERA, as GharKundli read it in October 2026. GharKundli’s full report compares it with the deadline.

Tower / wingPlinthSlabs (structure)Internal workLifts, fire & electrical
104 EAST95%90%60%25%

Commencement certificate (CC), as filed on MahaRERA

  • 104 EAST: covers 18 floors

Want to know when this changes? Kundli Watch sends a free WhatsApp update on 104 EAST every month.

104 EAST: buildings, flats and land, as filed on MahaRERA

TypeCarpet area (sq ft)Units
Office Space325 – 1,66884
Shops485 – 1,0534

The builder’s record and reviews

Quba Realty (a group of 9 linked companies) has 12 projects on MahaRERA since 2020, this one included. Of the 12 GharKundli has checked: 10 still being built, 4 past the promised date (typically 8 months late); 2 lapsed. No complaints on MahaRERA.

Read Google reviews of 104 EAST →Reviews on Google are opinions by Google users; GharKundli doesn’t check them.

Kundli Watch

104 EAST: buyers & owners

Free: a WhatsApp update every month on this project, and straight away when anything changes on MahaRERA — a later completion date, new complaints, a red flag. Your number stays private: never shown to other members or the builder.

Be the first to watch this project.

How are you connected to this project?

Bought here? No document needed now. From the builder’s team? Join to answer buyers’ questions; you never see members’ details. You’ll sign in with a one-time code, then come straight back here.

Common questions about 104 EAST

What is the possession date of 104 EAST?

According to GharKundli's check of MahaRERA records (updated October 2026), the latest completion date filed on MahaRERA for 104 EAST in Malad East, Mumbai is 30 June 2027 — 30 months later than 31 December 2024, the date given at registration.

Is the builder's possession date different from the MahaRERA date for 104 EAST?

Builders and listing sites often quote an earlier "target" date for handover. The completion date 104 EAST's builder has filed on MahaRERA, the official one, is 30 June 2027, already 30 months later than the 31 December 2024 given at registration, per GharKundli's check of MahaRERA records. If possession is late, what counts under RERA (Section 18) is the possession date written in your agreement for sale.

Why was the possession date of 104 EAST extended?

According to GharKundli's check of MahaRERA records (updated October 2026), 104 EAST's builder applied to MahaRERA to extend the completion date 2 times: to 31 December 2025, giving the reason "Ammendment in plan"; to 30 June 2027, giving the reason "Delayed in obtaining approval".

What is the RERA number of 104 EAST?

According to GharKundli's check of MahaRERA records (updated October 2026), the MahaRERA registration number of 104 EAST in Malad East, Mumbai is P51800035079.

Is 104 EAST registered with MahaRERA?

According to GharKundli's check of MahaRERA records (updated October 2026), 104 EAST is registered as P51800035079 and its status is "Registered and active".

What is the construction status of 104 EAST?

According to GharKundli's check of MahaRERA records (updated October 2026), 104 EAST's status on MahaRERA is "Registered and active". As filed by the builder, slab work on 104 EAST is 90% done and internal work 60%. GharKundli's full report compares construction progress with the deadline.

Does 104 EAST have complaints on MahaRERA?

No complaints were listed on MahaRERA as of October 2026, per GharKundli's weekly check.

Is 104 EAST safe to buy?

According to GharKundli's check of MahaRERA records (updated October 2026), 104 EAST is registered on MahaRERA as P51800035079, its completion date has moved 30 months since registration and no complaints are listed against it. GharKundli doesn't call a project safe or unsafe from these numbers alone: its full report gives a risk & trust score with every point explained.

How can I get updates if 104 EAST's possession date changes?

The latest dates are on 104 EAST's MahaRERA page (P51800035079). GharKundli's Kundli Watch sends a free WhatsApp update on 104 EAST every month, and straight away when anything changes on MahaRERA: a later completion date, new complaints or a red flag. Your number is never shown to the builder.

How many floors does 104 EAST have?

According to GharKundli's check of MahaRERA records (updated October 2026), 104 EAST has one building filed: 104 EAST with 22 floors and 88 units.

How much parking does 104 EAST have?

According to GharKundli's check of MahaRERA records (updated October 2026), the builder has filed 80 open car parking spaces for 104 EAST.

How big is the land of 104 EAST?

According to GharKundli's check of MahaRERA records (updated October 2026), 104 EAST stands on 1,050 sq m of land (about 0.3 acres).

What is the track record of 104 EAST's builder?

According to GharKundli's check of MahaRERA records (updated October 2026), Quba Realty (a group of 9 linked companies) has 12 projects on MahaRERA since 2020, this one included. Of the 12 GharKundli has checked: 10 still being built, 4 past the promised date (typically 8 months late); 2 lapsed. No complaints on MahaRERA. GharKundli's full report covers the builder's record in detail.

Where can I read reviews of 104 EAST?

Google Maps has reviews of 104 EAST written by Google users; GharKundli links to them on this page but doesn't check them. For facts rather than opinions: no complaints are listed on MahaRERA, and Kundli Watch shows verified owners of the project.

Where is 104 EAST?

104 EAST by QUBA INFRA LLP is in Malad East, Mumbai (pincode 400063), near Mulund West, Santacruz East, Ghatkopar East, Maharashtra, and is registered on MahaRERA as P51800035079, per GharKundli's check of MahaRERA records.

How many homes are in 104 EAST?

According to GharKundli's check of MahaRERA records (updated October 2026), 104 EAST has 0 homes in 1 tower registered on MahaRERA, and 73% of them are sold or booked.

When was 104 EAST registered on MahaRERA?

According to GharKundli's check of MahaRERA records (updated October 2026), 104 EAST was registered on MahaRERA on 4 May 2022. GharKundli did not find a title report on the land on file there.

Are there court cases on 104 EAST?

No court cases are listed for 104 EAST on MahaRERA, per GharKundli's check of MahaRERA records (updated October 2026).

Who is the builder of 104 EAST?

According to GharKundli's check of MahaRERA records (updated October 2026), the builder is QUBA INFRA LLP.

All projects with possession due in 2027 in Mumbai Suburban →

Other projects in Borivali

All 151 projects in Goregaon East (400063) →

Data compiled by GharKundli (gharkundli.com) from MahaRERA public records, as of October 2026. Check the project’s MahaRERA page for the latest filings. Not legal advice.