by DPS BUILDCON CONSTRUCTIONS LLP · Kandivali East, Mumbai 400101
What’s in the report? →Possession date of DPS Greens (MahaRERA P51800034638): 1 October 2024, moved from 1 April 2024 (6 months later), and it has already passed. It has 44 homes (1 BHK, 2 BHK and 3 BHK, 416–840 sq ft carpet), 88% sold or booked. No complaints on MahaRERA. How to check it yourself
Registered on MahaRERA under P51800034638. Status: Lapsed (registration period ended).
Source: MahaRERA website — records for P51800034638, read and compiled by GharKundli. Facts as filed on MahaRERA, no opinions.
The latest completion date on MahaRERA (October 2024) has passed.
What do you want to know about DPS Greens?
Completion date nikal chuki hai. Kya poochna hai?Tap a question. We’ll answer you on WhatsApp, free.
How the possession date of DPS Greens has moved
1 April 2024
Completion date given when the project was registered
1 October 2024
Extended at the builder's request (MahaRERA application EXT51800019516)
Reason the builder gave MahaRERA: “Contractor unable to complete the projects on the given date .”
Source: DPS Greens’s extension records on MahaRERA (P51800034638), read by GharKundli in October 2026. The builder’s reasons are quoted as filed. Your own possession date is the one in your agreement for sale.
What builders tell MahaRERA when they’re late: 14,973 applications analysed →GharKundli’s full report on DPS Greens
Read from every filing on MahaRERA when you open it
- Risk & trust score, every point explained
- What the title report says about the land
- Each complaint and court case, and how it ended
- Construction pace against the October 2024 deadline
- Agreement clauses weaker than the RERA model
- Escrow audit, loans and the builder's record
- Questions to get answered in writing before you pay
- MahaRERA registration
- P51800034638
- Status
- Lapsed (registration period ended)
- Builder
- DPS BUILDCON CONSTRUCTIONS LLP
- Location
- Kandivali East, Mumbai · 400101
- Project type
- Residential / Group Housing
- Registered on
- 20 Apr 2022
- Completion date at registration
- April 2024
- Latest completion date
- October 2024
- Delay so far
- 6 months
- Homes
- 44
- Sold or booked
- 88%
- Towers
- 1
- Complaints on MahaRERA
- 0
- Court cases listed
- 0
- Title report on file
- Not found
Construction progress of DPS Greens, as filed by the builder
What the builder has reported to MahaRERA, as GharKundli read it in October 2026. GharKundli’s full report compares it with the deadline.
| Tower / wing | Plinth | Slabs (structure) | Internal work | Lifts, fire & electrical |
|---|---|---|---|---|
| DPS GREENS | 100% | 100% | 100% | 100% |
Commencement certificate (CC), as filed on MahaRERA
- DPS GREENS: covers 15 floors
Want to know when this changes? Kundli Watch sends a free WhatsApp update on DPS Greens every 1–2 months.
DPS Greens: buildings, flats and land, as filed on MahaRERA
| Type | Carpet area (sq ft) | Units |
|---|---|---|
| 2 BHK | 652 | 21 |
| 3 BHK | 840 | 12 |
| 1 BHK | 416 | 11 |
| Shops | 837 – 968 | 2 |
| Office Space | 894 – 1,184 | 2 |
- Buildings: DPS GREENS (18 floors, 48 units)
- Car parking: 46 covered
- Land: 1,020 sq m (about 0.3 acres) · sanctioned built-up 3,254 sq m
- Land, as filed: 116 & 54
- Map: the location the builder filed on MahaRERA · Get directions
The builder’s record and reviews
Dpspro DEV (a group of 2 linked companies) has 2 projects on MahaRERA since 2022, this one included. Of the 2 GharKundli has checked: 1 finished, 0 within the promised date and 1 needed more time (typically 9 months); 1 lapsed. No complaints on MahaRERA.
Read Google reviews of DPS Greens →Reviews on Google are opinions by Google users; GharKundli doesn’t check them.
Kundli Watch
DPS Greens: buyers & owners
Free: a construction progress update on WhatsApp every 1–2 months, and straight away when anything changes on MahaRERA — a later completion date, new complaints, a red flag. Your number stays private: never shown to other members or the builder.
Be the first to watch this project.
How are you connected to this project?
Watching needs only WhatsApp or your number. Bought here? No document needed now. From the builder’s team? Join to answer buyers’ questions; you never see members’ details. Owners and the builder’s team sign in with a one-time code, then come straight back here.
Common questions about DPS Greens
What is the possession date of DPS Greens?
According to GharKundli's check of MahaRERA records (updated October 2026), the latest completion date filed on MahaRERA for DPS Greens in Kandivali East, Mumbai is 1 October 2024 — 6 months later than 1 April 2024, the date given at registration. That date has already passed.
The date has already moved 6 months. Will it move again? Check the real pace of construction →
Is the builder's possession date different from the MahaRERA date for DPS Greens?
Builders and listing sites often quote an earlier "target" date for handover. The completion date DPS Greens's builder has filed on MahaRERA, the official one, is 1 October 2024, already 6 months later than the 1 April 2024 given at registration, per GharKundli's check of MahaRERA records. If possession is late, what counts under RERA (Section 18) is the possession date written in your agreement for sale.
Why was the possession date of DPS Greens extended?
According to GharKundli's check of MahaRERA records (updated October 2026), DPS Greens's builder applied to MahaRERA to extend the completion date once: to 1 October 2024, giving the reason "Contractor unable to complete the projects on the given date .".
What is the RERA number of DPS Greens?
According to GharKundli's check of MahaRERA records (updated October 2026), the MahaRERA registration number of DPS Greens in Kandivali East, Mumbai is P51800034638.
Is DPS Greens registered with MahaRERA?
According to GharKundli's check of MahaRERA records (updated October 2026), DPS Greens is registered as P51800034638 and its status is "Lapsed (registration period ended)".
What is the current construction status of DPS Greens? How much work is done?
According to GharKundli's check of MahaRERA records (updated October 2026), DPS Greens's status on MahaRERA is "Lapsed (registration period ended)". As filed by the builder, slab work on DPS GREENS is 100% done and internal work 100%. GharKundli's full report compares construction progress with the deadline.
Does DPS Greens have complaints on MahaRERA?
No complaints were listed on MahaRERA as of October 2026, per GharKundli's weekly check.
Is DPS Greens safe to buy?
According to GharKundli's check of MahaRERA records (updated October 2026), DPS Greens is registered on MahaRERA as P51800034638, its MahaRERA status is "Lapsed (registration period ended)", its completion date has moved 6 months since registration and no complaints are listed against it. GharKundli doesn't call a project safe or unsafe from these numbers alone: its full report gives a risk & trust score with every point explained.
How much GST is payable on a flat in DPS Greens?
DPS Greens isn't marked completed on MahaRERA, so until the occupancy certificate is issued GST applies to a new flat: 5% of the price, with no input tax credit. The lower 1% rate is only for "affordable" homes: carpet area up to 60 sq m (about 646 sq ft) in the Mumbai region, and price up to ₹45 lakh. Some flats in DPS Greens are 416 sq ft carpet, small enough for 1% if the price is ₹45 lakh or less. There is no GST on stamp duty or registration, and none once the occupancy certificate is issued.
What is the stamp duty and registration cost for a flat in DPS Greens?
For a flat in DPS Greens (Mumbai), stamp duty is 6% of the agreement value, or of the ready reckoner value if that's higher, including 1% Metro Cess. A woman buying in her own name pays 5%. Registration is 1% of the value, capped at ₹30,000. On a ₹1 crore flat that's about ₹6 lakh in stamp duty plus ₹30,000 registration. GharKundli's property cost calculator works it out for your price: gharkundli.com/tools/property-cost-calculator
Has DPS Greens received its OC? Is it ready to move in?
Not yet. According to GharKundli's check of MahaRERA records (updated October 2026), DPS Greens isn't completed: its MahaRERA status is "Lapsed (registration period ended)", with 1 October 2024 as the latest completion date filed on MahaRERA, and that date has passed. A flat is ready to move in only once the occupancy certificate (OC) is issued, after construction is complete.
What does "lapsed" mean for DPS Greens?
According to GharKundli's check of MahaRERA records (updated October 2026), DPS Greens's registration shows as lapsed on MahaRERA. Lapsed means the completion date on MahaRERA (1 October 2024) passed without the project being marked complete or the registration being extended. Before paying anything, ask the builder in writing whether an extension has been applied for.
Is DPS Greens a redevelopment or SRA project?
According to GharKundli's check of MahaRERA records (updated October 2026), DPS Greens is a redevelopment: 22 of its flats are set aside for existing occupants (rehab), and the rest are for sale.
Has DPS Greens uploaded its title report on MahaRERA?
According to GharKundli's check of MahaRERA records (updated October 2026), no title report for DPS Greens was found on MahaRERA. Builders are expected to upload one; before booking, ask the builder for the advocate's title certificate in writing.
No title report is on MahaRERA for this project. See which documents are missing →
How can I get updates if DPS Greens's possession date changes?
The latest dates are on DPS Greens's MahaRERA page (P51800034638). GharKundli's Kundli Watch sends a free WhatsApp update on DPS Greens every 1–2 months, and straight away when anything changes on MahaRERA: a later completion date, new complaints or a red flag. Your number is never shown to the builder.
How many floors does DPS Greens have?
According to GharKundli's check of MahaRERA records (updated October 2026), DPS Greens has one building filed: DPS GREENS with 18 floors and 48 units.
What are the flat sizes (carpet area) in DPS Greens?
According to GharKundli's check of MahaRERA records (updated October 2026), the builder has filed these homes for DPS Greens: 2 BHK: 652 sq ft carpet (21 homes); 3 BHK: 840 sq ft carpet (12 homes); 1 BHK: 416 sq ft carpet (11 homes). Carpet area is the usable floor area inside the walls, as defined under RERA.
How much parking does DPS Greens have?
According to GharKundli's check of MahaRERA records (updated October 2026), the builder has filed 46 covered car parking spaces for DPS Greens.
How big is the land of DPS Greens?
According to GharKundli's check of MahaRERA records (updated October 2026), DPS Greens stands on 1,020 sq m of land (about 0.3 acres), with 3,254 sq m of sanctioned built-up area.
What is the track record of DPS Greens's builder?
According to GharKundli's check of MahaRERA records (updated October 2026), Dpspro DEV (a group of 2 linked companies) has 2 projects on MahaRERA since 2022, this one included. Of the 2 GharKundli has checked: 1 finished, 0 within the promised date and 1 needed more time (typically 9 months); 1 lapsed. No complaints on MahaRERA. GharKundli's full report covers the builder's record in detail.
What are the reviews of DPS Greens?
Google Maps has reviews of DPS Greens written by Google users; GharKundli links to them on this page but doesn't check them. For facts rather than opinions: no complaints are listed on MahaRERA, and Kundli Watch shows verified owners of the project.
What is the address and pincode of DPS Greens?
DPS Greens by DPS BUILDCON CONSTRUCTIONS LLP is in Kandivali East, Mumbai, pincode 400101, Maharashtra, and is registered on MahaRERA as P51800034638, per GharKundli's check of MahaRERA records. Its land is filed as 116 & 54. GharKundli lists all 113 MahaRERA projects in Kandivali East (400101).
How many flats are in DPS Greens, and how many are sold?
According to GharKundli's check of MahaRERA records (updated October 2026), DPS Greens has 44 homes in 1 tower registered on MahaRERA, and 88% of them are sold or booked.
When was DPS Greens registered on MahaRERA?
According to GharKundli's check of MahaRERA records (updated October 2026), DPS Greens was registered on MahaRERA on 20 April 2022. GharKundli did not find a title report on the land on file there.
Does DPS Greens have any legal issues or court cases?
No court cases are listed for DPS Greens on MahaRERA, per GharKundli's check of MahaRERA records (updated October 2026).
Who is the builder / developer of DPS Greens?
According to GharKundli's check of MahaRERA records (updated October 2026), the builder is DPS BUILDCON CONSTRUCTIONS LLP.
Check it yourself on MahaRERA
- How to check the possession date of DPS Greens
- How to find and verify a MahaRERA number
- How to check construction status on MahaRERA
- Occupancy certificate (OC): what to check before possession
- Possession delayed? Work out the interest the builder owes
- How to file a MahaRERA complaint against a builder
- Where MahaRERA complaints are: the data
- Why builders ask MahaRERA for more time: the data
Other projects in Kandivali East (400101)
- Uk Luxecity - E - F
- Siennaa Wing F
- Avasa
- Aurigae Residency D Wing
- Ajmera Iconic
- 101 Boulevard
- Veda
- Swayambhu Co-op. HSG. Soc. LTD.
Data compiled by GharKundli (gharkundli.com) from MahaRERA public records, as of October 2026. Check the project’s MahaRERA page for the latest filings. Not legal advice.