Possession date of NATHANI RESIDENCY: 30 April 2027, moved from 30 December 2021 (60 months later). This is the latest completion date the builder has filed on MahaRERA. How to check it yourself

Registered on MahaRERA under P51900009339, and currently active. Its completion date has moved from December 2021 to April 2027: 60 months at the builder's request, plus MahaRERA's automatic 4-month extension for all eligible projects.

Source: GharKundli’s check of MahaRERA records, October 2026.

What do you want to know about NATHANI RESIDENCY?

Ask us on WhatsAppNo login needed. A real person replies.

How the possession date of NATHANI RESIDENCY has moved

  1. 30 December 2021

    Completion date given when the project was registered

  2. 31 December 2023

    Extended at the builder's request (MahaRERA application EXT51900011382)

    Reason the builder gave MahaRERA: “To get NOC from Estate department”
  3. 31 December 2024

    Extended at the builder's request (MahaRERA application EXT51900016791)

    Reason the builder gave MahaRERA: “ESTATE DEPARTMENT AND O.C TO BE RECIEVED”
  4. 31 December 2025

    Extended at the builder's request (MahaRERA application EXT51900025849)

    Reason the builder gave MahaRERA: “Increment in Total Permissible FSI. Kindly note total number of apartments in the project for sale are only 28 units rest all are rehab out which only 24 units are sold”
  5. 31 December 2026

    Extended at the builder's request (MahaRERA application EA03012619274)

    Reason the builder gave MahaRERA: “Increment in Total Permissible FSI.”
  6. 30 April 2027

    MahaRERA's automatic 4-month extension for all eligible projects, not the builder's request

Source: NATHANI RESIDENCY’s extension records on MahaRERA (P51900009339), read by GharKundli in October 2026. The builder’s reasons are quoted as filed. Your own possession date is the one in your agreement for sale.

What builders tell MahaRERA when they’re late: 14,973 applications analysed →

GharKundli’s full report on NATHANI RESIDENCY

Read from every filing on MahaRERA when you open it

  • Risk & trust score, every point explained
  • What the title report says about the land
  • Each complaint and court case, and how it ended
  • Construction pace against the April 2027 deadline
  • Agreement clauses weaker than the RERA model
  • Escrow audit, loans and the builder's record
  • Questions to get answered in writing before you pay
MahaRERA registration
P51900009339
Status
Registered and active
Builder
Nathani Parekh Constructions Private Limited
Location
agripada, Mumbai · 400011
Project type
Others
Registered on
22 Aug 2017
Completion date at registration
December 2021
Latest completion date
April 2027
Delay so far
60 months
MahaRERA's automatic extension
+4 months (force majeure, all eligible projects)
Homes
28
Sold or booked
86%
Towers
1
Complaints on MahaRERA
0
Court cases listed
0
Title report on file
Not found
Builder's other MahaRERA projects
2

Construction progress of NATHANI RESIDENCY, as filed by the builder

What the builder has reported to MahaRERA, as GharKundli read it in October 2026. GharKundli’s full report compares it with the deadline.

Tower / wingPlinthSlabs (structure)Internal workLifts, fire & electrical
NATHANI RESIDENCY100%100%100%100%

Commencement certificate (CC), as filed on MahaRERA

  • NATHANI RESIDENCY: covers 21 floors

Want to know when this changes? Kundli Watch sends a free WhatsApp update on NATHANI RESIDENCY every month.

NATHANI RESIDENCY: buildings, flats and land, as filed on MahaRERA

TypeCarpet area (sq ft)Units
2 BHK636 – 1,01820
1 BHK475 – 6368

The builder’s record and reviews

Nathani Parekh Constructions (a group of 4 linked companies) has 6 projects on MahaRERA since 2017, this one included. Of the 6 GharKundli has checked: 2 finished, all within the promised date; 4 still being built, 1 past the promised date (typically 42 months late). 1 complaint on MahaRERA across 1 project.

Read Google reviews of NATHANI RESIDENCY →Reviews on Google are opinions by Google users; GharKundli doesn’t check them.

Kundli Watch

NATHANI RESIDENCY: buyers & owners

Free: a WhatsApp update every month on this project, and straight away when anything changes on MahaRERA — a later completion date, new complaints, a red flag. Your number stays private: never shown to other members or the builder.

Be the first to watch this project.

How are you connected to this project?

Bought here? No document needed now. From the builder’s team? Join to answer buyers’ questions; you never see members’ details. You’ll sign in with a one-time code, then come straight back here.

Common questions about NATHANI RESIDENCY

What is the possession date of NATHANI RESIDENCY?

According to GharKundli's check of MahaRERA records (updated October 2026), the latest completion date filed on MahaRERA for NATHANI RESIDENCY in agripada, Mumbai is 30 April 2027 — 60 months later than 30 December 2021, the date given at registration, plus MahaRERA's automatic 4-month extension for all eligible projects.

Is the builder's possession date different from the MahaRERA date for NATHANI RESIDENCY?

Builders and listing sites often quote an earlier "target" date for handover. The completion date NATHANI RESIDENCY's builder has filed on MahaRERA, the official one, is 30 April 2027, already 60 months later than the 30 December 2021 given at registration, per GharKundli's check of MahaRERA records. If possession is late, what counts under RERA (Section 18) is the possession date written in your agreement for sale.

Why was the possession date of NATHANI RESIDENCY extended?

According to GharKundli's check of MahaRERA records (updated October 2026), NATHANI RESIDENCY's builder applied to MahaRERA to extend the completion date 4 times: to 31 December 2023, giving the reason "To get NOC from Estate department"; to 31 December 2024, giving the reason "ESTATE DEPARTMENT AND O.C TO BE RECIEVED"; to 31 December 2025, giving the reason "Increment in Total Permissible FSI. Kindly note total number of apartments in the project for sale are only 28 units rest all are rehab out which only 24 units are sold"; to 31 December 2026, giving the reason "Increment in Total Permissible FSI.". MahaRERA also added its automatic 4-month extension for all eligible projects.

What is the RERA number of NATHANI RESIDENCY?

According to GharKundli's check of MahaRERA records (updated October 2026), the MahaRERA registration number of NATHANI RESIDENCY in agripada, Mumbai is P51900009339.

Is NATHANI RESIDENCY registered with MahaRERA?

According to GharKundli's check of MahaRERA records (updated October 2026), NATHANI RESIDENCY is registered as P51900009339 and its status is "Registered and active".

What is the construction status of NATHANI RESIDENCY?

According to GharKundli's check of MahaRERA records (updated October 2026), NATHANI RESIDENCY's status on MahaRERA is "Registered and active". As filed by the builder, slab work on NATHANI RESIDENCY is 100% done and internal work 100%. GharKundli's full report compares construction progress with the deadline.

Does NATHANI RESIDENCY have complaints on MahaRERA?

No complaints were listed on MahaRERA as of October 2026, per GharKundli's weekly check.

Is NATHANI RESIDENCY safe to buy?

According to GharKundli's check of MahaRERA records (updated October 2026), NATHANI RESIDENCY is registered on MahaRERA as P51900009339, its completion date has moved 60 months since registration and no complaints are listed against it. GharKundli doesn't call a project safe or unsafe from these numbers alone: its full report gives a risk & trust score with every point explained.

How can I get updates if NATHANI RESIDENCY's possession date changes?

The latest dates are on NATHANI RESIDENCY's MahaRERA page (P51900009339). GharKundli's Kundli Watch sends a free WhatsApp update on NATHANI RESIDENCY every month, and straight away when anything changes on MahaRERA: a later completion date, new complaints or a red flag. Your number is never shown to the builder.

How many floors does NATHANI RESIDENCY have?

According to GharKundli's check of MahaRERA records (updated October 2026), NATHANI RESIDENCY has one building filed: NATHANI RESIDENCY with 25 floors and 28 units.

What are the flat sizes (carpet area) in NATHANI RESIDENCY?

According to GharKundli's check of MahaRERA records (updated October 2026), the builder has filed these homes for NATHANI RESIDENCY: 2 BHK: 636 to 1018 sq ft carpet (20 homes); 1 BHK: 475 to 636 sq ft carpet (8 homes). Carpet area is the usable floor area inside the walls, as defined under RERA.

How big is the land of NATHANI RESIDENCY?

According to GharKundli's check of MahaRERA records (updated October 2026), NATHANI RESIDENCY stands on 842 sq m of land (about 0.2 acres), with 2,673 sq m of sanctioned built-up area and 280 sq m of recreational open space.

What is the track record of NATHANI RESIDENCY's builder?

According to GharKundli's check of MahaRERA records (updated October 2026), Nathani Parekh Constructions (a group of 4 linked companies) has 6 projects on MahaRERA since 2017, this one included. Of the 6 GharKundli has checked: 2 finished, all within the promised date; 4 still being built, 1 past the promised date (typically 42 months late). 1 complaint on MahaRERA across 1 project. GharKundli's full report covers the builder's record in detail.

Where can I read reviews of NATHANI RESIDENCY?

Google Maps has reviews of NATHANI RESIDENCY written by Google users; GharKundli links to them on this page but doesn't check them. For facts rather than opinions: no complaints are listed on MahaRERA, and Kundli Watch shows verified owners of the project.

Where is NATHANI RESIDENCY?

NATHANI RESIDENCY by Nathani Parekh Constructions Private Limited is in agripada, Mumbai (pincode 400011), near Byculla, Tardeo, Mahalaxmi, Maharashtra, and is registered on MahaRERA as P51900009339, per GharKundli's check of MahaRERA records.

How many homes are in NATHANI RESIDENCY?

According to GharKundli's check of MahaRERA records (updated October 2026), NATHANI RESIDENCY has 28 homes in 1 tower registered on MahaRERA, and 86% of them are sold or booked.

When was NATHANI RESIDENCY registered on MahaRERA?

According to GharKundli's check of MahaRERA records (updated October 2026), NATHANI RESIDENCY was registered on MahaRERA on 22 August 2017. GharKundli did not find a title report on the land on file there.

Are there court cases on NATHANI RESIDENCY?

No court cases are listed for NATHANI RESIDENCY on MahaRERA, per GharKundli's check of MahaRERA records (updated October 2026).

Who is the builder of NATHANI RESIDENCY?

According to GharKundli's check of MahaRERA records (updated October 2026), the builder is Nathani Parekh Constructions Private Limited, which has 2 other projects registered on MahaRERA.

All projects with possession due in 2027 in Mumbai City →

Other projects in pincode 400011

All 56 projects in Jacob Circle (400011) →

Other projects by Nathani Parekh Constructions Private Limited

Data compiled by GharKundli (gharkundli.com) from MahaRERA public records, as of October 2026. Check the project’s MahaRERA page for the latest filings. Not legal advice.