MINERVA
by Lokhandwala Kataria Construction Private Limited · Lower Parel, MumbaiAlso near Saatraasta, Agripada, Byculla
Possession date of MINERVA: 30 April 2027, moved from 30 December 2023 (36 months later). This is the latest completion date the builder has filed on MahaRERA. How to check it yourself
Registered on MahaRERA under P51900008204, and currently active. Its completion date has moved from December 2023 to April 2027: 36 months at the builder's request, plus MahaRERA's automatic 4-month extension for all eligible projects. MahaRERA has issued a regulatory order on this project. 55 complaints are listed against it on MahaRERA.
Source: GharKundli’s check of MahaRERA records, October 2026.
What do you want to know about MINERVA?
How the possession date of MINERVA has moved
30 December 2023
Completion date given when the project was registered
31 December 2024
Extended at the builder's request (MahaRERA application EXT51900018187)
Reason the builder gave MahaRERA: “As per letter attached.”
31 December 2025
Extended at the builder's request (MahaRERA application EXT51900024786)
Reason the builder gave MahaRERA: “1) Delays due to Government Authorities 2) Other Impediments 3) Covid -19”
31 December 2026
Extended at the builder's request (MahaRERA application EA25122518993)
Reason the builder gave MahaRERA:
“We, hereby apply for extension u/s 7(3) of the registered project bearing no. P51900008204 to 31st December 2026. 1. We have obtained Occupation Certificate in respect of all habitable floors and units in the Project as under :- (a) Part Oc…” Read the full reason
“We, hereby apply for extension u/s 7(3) of the registered project bearing no. P51900008204 to 31st December 2026. 1. We have obtained Occupation Certificate in respect of all habitable floors and units in the Project as under :- (a) Part Occupation Certificate from the Slum Rehabilitation Authority bearing no. SRA/ENG/2375/ GS/ML/AP dated 6th January, 2023 upto 39th Level as per the sanctioned plans. (b) Further we have obtained Part Occupation Certificate from Slum Rehabilitation Authority bearing no. SRA/ENG/2375/GS/ML/AP from 40th Level to 79th Level. 2. Upon receipt of Occupation Certif…”30 April 2027
MahaRERA's automatic 4-month extension for all eligible projects, not the builder's request
Source: MINERVA’s extension records on MahaRERA (P51900008204), read by GharKundli in October 2026. The builder’s reasons are quoted as filed. Your own possession date is the one in your agreement for sale.
What builders tell MahaRERA when they’re late: 14,973 applications analysed →GharKundli’s full report on MINERVA
Read from every filing on MahaRERA when you open it
- Risk & trust score, every point explained
- What the title report says about the land
- Each of the 55 complaints and 3 court cases, and how it ended
- Construction pace against the April 2027 deadline
- Agreement clauses weaker than the RERA model
- Escrow audit, loans and the builder's record
- Questions to get answered in writing before you pay
- MahaRERA registration
- P51900008204
- Status
- Registered and active
- Builder
- Lokhandwala Kataria Construction Private Limited
- Location
- Lower Parel, Mumbai · 400011
- Project type
- Residential / Group Housing
- Registered on
- 18 Aug 2017
- Completion date at registration
- December 2023
- Latest completion date
- April 2027
- Delay so far
- 36 months
- MahaRERA's automatic extension
- +4 months (force majeure, all eligible projects)
- Homes
- 372
- Sold or booked
- 82%
- Towers
- 3
- Complaints on MahaRERA
- 55
- Court cases listed
- 3
- Appeals at the tribunal
- 22
- MahaRERA regulatory orders
- 1
- Title report on file
- Not found
Construction progress of MINERVA, as filed by the builder
What the builder has reported to MahaRERA, as GharKundli read it in October 2026. GharKundli’s full report compares it with the deadline.
| Tower / wing | Plinth | Slabs (structure) | Internal work | Lifts, fire & electrical |
|---|---|---|---|---|
| MINERVA 1A 1-39 | 100% | 100% | 100% | 95% |
| MINERVA 1B 40-65 | 100% | 100% | 85% | 50% |
| MINERVA 1C 66-79 | 100% | 98% | 40% | 40% |
Commencement certificate (CC), as filed on MahaRERA
- MINERVA 1A 1-39: covers Upto 39th Floor
- MINERVA 1B 40-65: covers Upto 65th Floor
- MINERVA 1C 66-79: covers Upto 79 floor
Latest CC order on MahaRERA: dated 09/07/2025.
Want to know when this changes? Kundli Watch sends a free WhatsApp update on MINERVA every month.
MINERVA: buildings, flats and land, as filed on MahaRERA
| Type | Carpet area (sq ft) | Units |
|---|---|---|
| 3 BHK | 1,214 – 1,427 | 200 |
| 4 BHK | 2,019 – 2,750 | 100 |
| Other | 2,058 – 2,067 | 64 |
| Duplex | 3,420 – 3,650 | 8 |
- Buildings: MINERVA 1A 1-39 (42 floors, 200 units) · MINERVA 1B 40-65 (26 floors, 124 units) · MINERVA 1C 66-79 (14 floors, 48 units)
- Car parking: 775 covered
- Land: 7,908 sq m (about 2.0 acres) · sanctioned built-up 62,319 sq m
- Boundaries filed include: J R BORICHA MARG
- Map: the location the builder filed on MahaRERA
The builder’s record and reviews
Lokhandwala Kataria Construction (a group of 2 linked companies) has 2 projects on MahaRERA since 2017, this one included. Of the 2 GharKundli has checked: 1 still being built, 1 past the promised date (typically 18 months late); 1 lapsed. 61 complaints on MahaRERA across 2 projects.
Read Google reviews of MINERVA →Reviews on Google are opinions by Google users; GharKundli doesn’t check them.
Kundli Watch
MINERVA: buyers & owners
Free: a WhatsApp update every month on this project, and straight away when anything changes on MahaRERA — a later completion date, new complaints, a red flag. Your number stays private: never shown to other members or the builder.
Be the first to watch this project.
How are you connected to this project?
Bought here? No document needed now. From the builder’s team? Join to answer buyers’ questions; you never see members’ details. You’ll sign in with a one-time code, then come straight back here.
Common questions about MINERVA
What is the possession date of MINERVA?
According to GharKundli's check of MahaRERA records (updated October 2026), the latest completion date filed on MahaRERA for MINERVA in Lower Parel, Mumbai is 30 April 2027 — 36 months later than 30 December 2023, the date given at registration, plus MahaRERA's automatic 4-month extension for all eligible projects.
Is the builder's possession date different from the MahaRERA date for MINERVA?
Builders and listing sites often quote an earlier "target" date for handover. The completion date MINERVA's builder has filed on MahaRERA, the official one, is 30 April 2027, already 36 months later than the 30 December 2023 given at registration, per GharKundli's check of MahaRERA records. If possession is late, what counts under RERA (Section 18) is the possession date written in your agreement for sale.
Why was the possession date of MINERVA extended?
According to GharKundli's check of MahaRERA records (updated October 2026), MINERVA's builder applied to MahaRERA to extend the completion date 3 times: to 31 December 2024, giving the reason "As per letter attached."; to 31 December 2025, giving the reason "1) Delays due to Government Authorities 2) Other Impediments 3) Covid -19"; to 31 December 2026, giving the reason "We, hereby apply for extension u/s 7(3) of the registered project bearing no. P51900008204 to 31st December 2026. 1. We have obtained Occupation Certificate in respect of all habitable floors and units in the Project as under :- (a) Part Occupation Certificate from the Slum Rehabilitation Authority bearing no. SRA/ENG/2375/ GS/ML/AP dated 6th January, 2023 upto 39th Level as per the sanctioned plans. (b) Further we have obtained Part Occupation Certificate from Slum Rehabilitation Authority bearing no. SRA/ENG/2375/GS/ML/AP from 40th Level to 79th Level. 2. Upon receipt of Occupation Certif…". MahaRERA also added its automatic 4-month extension for all eligible projects.
What is the RERA number of MINERVA?
According to GharKundli's check of MahaRERA records (updated October 2026), the MahaRERA registration number of MINERVA in Lower Parel, Mumbai is P51900008204.
Is MINERVA registered with MahaRERA?
According to GharKundli's check of MahaRERA records (updated October 2026), MINERVA is registered as P51900008204 and its status is "Registered and active".
What is the construction status of MINERVA?
According to GharKundli's check of MahaRERA records (updated October 2026), MINERVA's status on MahaRERA is "Registered and active". As filed by the builder, slab work ranges from 98% to 100% across 3 towers. GharKundli's full report compares construction progress with the deadline.
Does MINERVA have complaints on MahaRERA?
55 complaints were listed on MahaRERA as of October 2026, per GharKundli's weekly check. GharKundli's full report explains each case and how it ended.
Is MINERVA safe to buy?
According to GharKundli's check of MahaRERA records (updated October 2026), MINERVA is registered on MahaRERA as P51900008204, its completion date has moved 36 months since registration and 55 complaints are listed against it. GharKundli doesn't call a project safe or unsafe from these numbers alone: its full report gives a risk & trust score with every point explained.
How can I get updates if MINERVA's possession date changes?
The latest dates are on MINERVA's MahaRERA page (P51900008204). GharKundli's Kundli Watch sends a free WhatsApp update on MINERVA every month, and straight away when anything changes on MahaRERA: a later completion date, new complaints or a red flag. Your number is never shown to the builder.
How many floors does MINERVA have?
According to GharKundli's check of MahaRERA records (updated October 2026), MINERVA has 3 buildings filed: MINERVA 1A 1-39 with 42 floors and 200 units; MINERVA 1B 40-65 with 26 floors and 124 units; MINERVA 1C 66-79 with 14 floors and 48 units.
What are the flat sizes (carpet area) in MINERVA?
According to GharKundli's check of MahaRERA records (updated October 2026), the builder has filed these homes for MINERVA: 3 BHK: 1214 to 1427 sq ft carpet (200 homes); 4 BHK: 2019 to 2750 sq ft carpet (100 homes); Other: 2058 to 2067 sq ft carpet (64 homes); Duplex: 3420 to 3650 sq ft carpet (8 homes). Carpet area is the usable floor area inside the walls, as defined under RERA.
How much parking does MINERVA have?
According to GharKundli's check of MahaRERA records (updated October 2026), the builder has filed 775 covered car parking spaces for MINERVA.
How big is the land of MINERVA?
According to GharKundli's check of MahaRERA records (updated October 2026), MINERVA stands on 7,908 sq m of land (about 2.0 acres), with 62,319 sq m of sanctioned built-up area.
What is the track record of MINERVA's builder?
According to GharKundli's check of MahaRERA records (updated October 2026), Lokhandwala Kataria Construction (a group of 2 linked companies) has 2 projects on MahaRERA since 2017, this one included. Of the 2 GharKundli has checked: 1 still being built, 1 past the promised date (typically 18 months late); 1 lapsed. 61 complaints on MahaRERA across 2 projects. GharKundli's full report covers the builder's record in detail.
Where can I read reviews of MINERVA?
Google Maps has reviews of MINERVA written by Google users; GharKundli links to them on this page but doesn't check them. For facts rather than opinions: 55 complaints are listed on MahaRERA, and Kundli Watch shows verified owners of the project.
Where is MINERVA?
MINERVA by Lokhandwala Kataria Construction Private Limited is in Lower Parel, Mumbai (pincode 400011), near Saatraasta, Agripada, Byculla, Maharashtra, and is registered on MahaRERA as P51900008204, per GharKundli's check of MahaRERA records. Its boundaries filed there include J R BORICHA MARG.
How many homes are in MINERVA?
According to GharKundli's check of MahaRERA records (updated October 2026), MINERVA has 372 homes in 3 towers registered on MahaRERA, and 82% of them are sold or booked.
When was MINERVA registered on MahaRERA?
According to GharKundli's check of MahaRERA records (updated October 2026), MINERVA was registered on MahaRERA on 18 August 2017. GharKundli did not find a title report on the land on file there.
Are there court cases on MINERVA?
3 court cases are listed for MINERVA on MahaRERA, and 22 appeals at the tribunal, per GharKundli's check of MahaRERA records (updated October 2026). GharKundli's full report explains each case and how it ended.
Who is the builder of MINERVA?
According to GharKundli's check of MahaRERA records (updated October 2026), the builder is Lokhandwala Kataria Construction Private Limited.
Check it yourself on MahaRERA
- How to check the possession date of MINERVA
- How to find and verify a MahaRERA number
- How to check construction status on MahaRERA
- Occupancy certificate (OC): what to check before possession
- Possession delayed? Work out the interest the builder owes
- How to file a MahaRERA complaint against a builder
- Where MahaRERA complaints are: the data
- Why builders ask MahaRERA for more time: the data
All projects with possession due in 2027 in Mumbai City →
Other projects in Lower Parel
- MONTESOUTH-6
- ARIHANT TOWERS - BY MJ SHAH
- EMBASSY CITADEL
- RUNWAL RAAYA - TOWER 1
- MONTESOUTH-5
- AETHERIA TOWER
- THE GRAND TOWER NO 1
- Palais Royale
Data compiled by GharKundli (gharkundli.com) from MahaRERA public records, as of October 2026. Check the project’s MahaRERA page for the latest filings. Not legal advice.