Palais Royale

by HONEST SHELTERS PRIVATE LTD · Lower Parel, MumbaiAlso near Worli, Kalanagar, Bandra East, Delisle Road

Possession date of Palais Royale: 30 December 2024, moved from 30 December 2022 (24 months later). This is the latest completion date the builder has filed on MahaRERA, and it has already passed. How to check it yourself

Registered on MahaRERA under P51900006786. Status: Lapsed (registration period ended). MahaRERA has issued a regulatory order on this project. 56 complaints are listed against it on MahaRERA.

Source: GharKundli’s check of MahaRERA records, October 2026.

The latest completion date on MahaRERA (December 2024) has passed.

What do you want to know about Palais Royale?

Ask us on WhatsAppNo login needed. A real person replies.

How the possession date of Palais Royale has moved

  1. 30 December 2022

    Completion date given when the project was registered

  2. 30 December 2023

    Extended at the builder's request (MahaRERA application EXT51900013609)

    Reason the builder gave MahaRERA:
    “(i) The said Project has been subject to numerous litigations and proceedings filed against us including by the erstwhile promoter, Shree Ram Urban Infrastructure Limited (“SRUIL”). These proceedings have been filed before various forums an…” Read the full reason“(i) The said Project has been subject to numerous litigations and proceedings filed against us including by the erstwhile promoter, Shree Ram Urban Infrastructure Limited (“SRUIL”). These proceedings have been filed before various forums and courts such as Bombay High Court, NCLT, NCLAT, DRT, and Supreme Court of India and we state that Honest Shelters Private Limited (“HSPL”) has already spent an enormous amount of money in acquiring the said Project and is at present dealing with these pending proceedings on a daily basis since 2019 as well as trying to resolve all the matters. (ii) Delay…”
  3. 30 December 2024

    Extended at the builder's request (MahaRERA application EXT51900018013)

    Reason the builder gave MahaRERA: “Pending litigations and other matters as per application attached. Additional declaration attached dated 19.03.2024. Please consider the same.”

Source: Palais Royale’s extension records on MahaRERA (P51900006786), read by GharKundli in October 2026. The builder’s reasons are quoted as filed. Your own possession date is the one in your agreement for sale.

What builders tell MahaRERA when they’re late: 14,973 applications analysed →

GharKundli’s full report on Palais Royale

Read from every filing on MahaRERA when you open it

  • Risk & trust score, every point explained
  • What the title report says about the land
  • Each of the 56 complaints and 13 court cases, and how it ended
  • Construction pace against the December 2024 deadline
  • Agreement clauses weaker than the RERA model
  • Escrow audit, loans and the builder's record
  • Questions to get answered in writing before you pay
MahaRERA registration
P51900006786
Status
Lapsed (registration period ended)
Builder
HONEST SHELTERS PRIVATE LTD
Location
Lower Parel, Mumbai · 400013
Project type
Residential / Group Housing
Registered on
16 Aug 2017
Completion date at registration
December 2022
Latest completion date
December 2024
Delay so far
24 months
Homes
162
Towers
1
Complaints on MahaRERA
56
Court cases listed
13
Appeals at the tribunal
21
MahaRERA regulatory orders
1
Title report on file
Not found

Construction progress of Palais Royale, as filed by the builder

What the builder has reported to MahaRERA, as GharKundli read it in October 2026. GharKundli’s full report compares it with the deadline.

Tower / wingPlinthSlabs (structure)Internal workLifts, fire & electrical
Palais Royale100%100%65%65%

Want to know when this changes? Kundli Watch sends a free WhatsApp update on Palais Royale every month.

Palais Royale: buildings, flats and land, as filed on MahaRERA

  • Buildings: Palais Royale (84 floors)
  • Car parking: 746 covered, 100 open
  • Land: 28,410 sq m (about 7.0 acres) · sanctioned built-up 54,715 sq m · recreational space 7,150 sq m
  • Boundaries filed include: Amritwar Marg, Ganpatrao Kadam Marg
  • Map: the location the builder filed on MahaRERA

The builder’s record and reviews

Not enough of this builder’s other MahaRERA projects have reached their promised date to judge yet.

Read Google reviews of Palais Royale →Reviews on Google are opinions by Google users; GharKundli doesn’t check them.

Kundli Watch

Palais Royale: buyers & owners

Free: a WhatsApp update every month on this project, and straight away when anything changes on MahaRERA — a later completion date, new complaints, a red flag. Your number stays private: never shown to other members or the builder.

Be the first to watch this project.

How are you connected to this project?

Bought here? No document needed now. From the builder’s team? Join to answer buyers’ questions; you never see members’ details. You’ll sign in with a one-time code, then come straight back here.

Common questions about Palais Royale

What is the possession date of Palais Royale?

According to GharKundli's check of MahaRERA records (updated October 2026), the latest completion date filed on MahaRERA for Palais Royale in Lower Parel, Mumbai is 30 December 2024 — 24 months later than 30 December 2022, the date given at registration. That date has already passed.

Is the builder's possession date different from the MahaRERA date for Palais Royale?

Builders and listing sites often quote an earlier "target" date for handover. The completion date Palais Royale's builder has filed on MahaRERA, the official one, is 30 December 2024, already 24 months later than the 30 December 2022 given at registration, per GharKundli's check of MahaRERA records. If possession is late, what counts under RERA (Section 18) is the possession date written in your agreement for sale.

Why was the possession date of Palais Royale extended?

According to GharKundli's check of MahaRERA records (updated October 2026), Palais Royale's builder applied to MahaRERA to extend the completion date 2 times: to 30 December 2023, giving the reason "(i) The said Project has been subject to numerous litigations and proceedings filed against us including by the erstwhile promoter, Shree Ram Urban Infrastructure Limited (“SRUIL”). These proceedings have been filed before various forums and courts such as Bombay High Court, NCLT, NCLAT, DRT, and Supreme Court of India and we state that Honest Shelters Private Limited (“HSPL”) has already spent an enormous amount of money in acquiring the said Project and is at present dealing with these pending proceedings on a daily basis since 2019 as well as trying to resolve all the matters. (ii) Delay…"; to 30 December 2024, giving the reason "Pending litigations and other matters as per application attached. Additional declaration attached dated 19.03.2024. Please consider the same.".

What is the RERA number of Palais Royale?

According to GharKundli's check of MahaRERA records (updated October 2026), the MahaRERA registration number of Palais Royale in Lower Parel, Mumbai is P51900006786.

Is Palais Royale registered with MahaRERA?

According to GharKundli's check of MahaRERA records (updated October 2026), Palais Royale is registered as P51900006786 and its status is "Lapsed (registration period ended)".

What is the construction status of Palais Royale?

According to GharKundli's check of MahaRERA records (updated October 2026), Palais Royale's status on MahaRERA is "Lapsed (registration period ended)". As filed by the builder, slab work on Palais Royale is 100% done and internal work 65%. GharKundli's full report compares construction progress with the deadline.

Does Palais Royale have complaints on MahaRERA?

56 complaints were listed on MahaRERA as of October 2026, per GharKundli's weekly check. GharKundli's full report explains each case and how it ended.

Is Palais Royale safe to buy?

According to GharKundli's check of MahaRERA records (updated October 2026), Palais Royale is registered on MahaRERA as P51900006786, its MahaRERA status is "Lapsed (registration period ended)", its completion date has moved 24 months since registration and 56 complaints are listed against it. GharKundli doesn't call a project safe or unsafe from these numbers alone: its full report gives a risk & trust score with every point explained.

How can I get updates if Palais Royale's possession date changes?

The latest dates are on Palais Royale's MahaRERA page (P51900006786). GharKundli's Kundli Watch sends a free WhatsApp update on Palais Royale every month, and straight away when anything changes on MahaRERA: a later completion date, new complaints or a red flag. Your number is never shown to the builder.

How many floors does Palais Royale have?

According to GharKundli's check of MahaRERA records (updated October 2026), Palais Royale has one building filed: Palais Royale with 84 floors.

How much parking does Palais Royale have?

According to GharKundli's check of MahaRERA records (updated October 2026), the builder has filed 746 covered and 100 open car parking spaces for Palais Royale.

How big is the land of Palais Royale?

According to GharKundli's check of MahaRERA records (updated October 2026), Palais Royale stands on 28,410 sq m of land (about 7.0 acres), with 54,715 sq m of sanctioned built-up area and 7,150 sq m of recreational open space.

Where can I read reviews of Palais Royale?

Google Maps has reviews of Palais Royale written by Google users; GharKundli links to them on this page but doesn't check them. For facts rather than opinions: 56 complaints are listed on MahaRERA, and Kundli Watch shows verified owners of the project.

Where is Palais Royale?

Palais Royale by HONEST SHELTERS PRIVATE LTD is in Lower Parel, Mumbai (pincode 400013), near Worli, Kalanagar, Bandra East, Delisle Road, Maharashtra, and is registered on MahaRERA as P51900006786, per GharKundli's check of MahaRERA records. Its boundaries filed there include Amritwar Marg, Ganpatrao Kadam Marg.

How many homes are in Palais Royale?

According to GharKundli's check of MahaRERA records (updated October 2026), Palais Royale has 162 homes in 1 tower registered on MahaRERA.

When was Palais Royale registered on MahaRERA?

According to GharKundli's check of MahaRERA records (updated October 2026), Palais Royale was registered on MahaRERA on 16 August 2017. GharKundli did not find a title report on the land on file there.

Are there court cases on Palais Royale?

13 court cases are listed for Palais Royale on MahaRERA, and 21 appeals at the tribunal, per GharKundli's check of MahaRERA records (updated October 2026). GharKundli's full report explains each case and how it ended.

Who is the builder of Palais Royale?

According to GharKundli's check of MahaRERA records (updated October 2026), the builder is HONEST SHELTERS PRIVATE LTD.