Possession date of The Grand Tower No 1 (MahaRERA P51900076793): 1 May 2028. It has 103 homes (4 BHK and 6 BHK, 3013–4344 sq ft carpet), 0% sold or booked. No complaints on MahaRERA. How to check it yourself

Registered on MahaRERA under P51900076793, and currently active. Its completion date is now May 2028, including MahaRERA's automatic 4-month extension for all eligible projects; the builder hasn't asked for more time.

Source: MahaRERA website — records for P51900076793, read and compiled by GharKundli. Facts as filed on MahaRERA, no opinions.

What do you want to know about The Grand Tower No 1?

Title report MahaRERA par nahi dikh rahi. Kya poochna hai?Tap a question. We’ll answer you on WhatsApp, free.

Ask something else on WhatsAppNo login needed. A real person replies.

Or leave your number, we’ll message you:

How the possession date of The Grand Tower No 1 has moved

  1. 1 January 2028

    Completion date given when the project was registered

  2. 1 May 2028

    MahaRERA's automatic 4-month extension for all eligible projects, not the builder's request

Source: The Grand Tower No 1’s extension records on MahaRERA (P51900076793), read by GharKundli in October 2026. The builder’s reasons are quoted as filed. Your own possession date is the one in your agreement for sale.

What builders tell MahaRERA when they’re late: 14,973 applications analysed →

GharKundli’s full report on The Grand Tower No 1

Read from every filing on MahaRERA when you open it

  • Risk & trust score, every point explained
  • What the title report says about the land
  • Each complaint and court case, and how it ended
  • Construction pace against the May 2028 deadline
  • Agreement clauses weaker than the RERA model
  • Escrow audit, loans and the builder's record
  • Questions to get answered in writing before you pay
MahaRERA registration
P51900076793
Status
Registered and active
Builder
SAMIR NARAIN BHOJWANI
Location
Lower Parel, Mumbai · 400013
Project type
Residential / Group Housing
Registered on
28 Jun 2024
Completion date at registration
January 2028
Latest completion date
May 2028
MahaRERA's automatic extension
+4 months (force majeure, all eligible projects)
Homes
103
Sold or booked
0%
Towers
2
Complaints on MahaRERA
0
Court cases listed
0
Title report on file
Not found

Construction progress of The Grand Tower No 1, as filed by the builder

What the builder has reported to MahaRERA, as GharKundli read it in October 2026. GharKundli’s full report compares it with the deadline.

Tower / wingPlinthSlabs (structure)Internal workLifts, fire & electrical
BUILDING NO 1 - A WING100%91%1%1%
BUILDING NO 1- B WING100%91%1%1%

Want to know when this changes? Kundli Watch sends a free WhatsApp update on The Grand Tower No 1 every 1–2 months.

The Grand Tower No 1: buildings, flats and land, as filed on MahaRERA

TypeCarpet area (sq ft)Units
4 BHK3,013 – 3,01887
6 BHK4,334 – 4,34416
  • Buildings: BUILDING NO 1 - A WING (50 floors) · BUILDING NO 1- B WING (50 floors)
  • Land: 2,404 sq m (about 0.6 acres) · sanctioned built-up 50,823 sq m
  • Land, as filed: 1/434
  • Map: Get directions

The builder’s record and reviews

Not enough of this builder’s other MahaRERA projects have reached their promised date to judge yet.

Read Google reviews of The Grand Tower No 1 →Reviews on Google are opinions by Google users; GharKundli doesn’t check them.

Kundli Watch

The Grand Tower No 1: buyers & owners

Free: a construction progress update on WhatsApp every 1–2 months, and straight away when anything changes on MahaRERA — a later completion date, new complaints, a red flag. Your number stays private: never shown to other members or the builder.

Be the first to watch this project.

How are you connected to this project?

Watching needs only WhatsApp or your number. Bought here? No document needed now. From the builder’s team? Join to answer buyers’ questions; you never see members’ details. Owners and the builder’s team sign in with a one-time code, then come straight back here.

Common questions about The Grand Tower No 1

What is the possession date of The Grand Tower No 1?

According to GharKundli's check of MahaRERA records (updated October 2026), the latest completion date filed on MahaRERA for The Grand Tower No 1 in Lower Parel, Mumbai is 1 May 2028, including MahaRERA's automatic 4-month extension for all eligible projects.

Is the builder's possession date different from the MahaRERA date for The Grand Tower No 1?

Builders and listing sites often quote an earlier "target" date for handover. The completion date The Grand Tower No 1's builder has filed on MahaRERA, the official one, is 1 May 2028, per GharKundli's check of MahaRERA records. If possession is late, what counts under RERA (Section 18) is the possession date written in your agreement for sale.

What is the RERA number of The Grand Tower No 1?

According to GharKundli's check of MahaRERA records (updated October 2026), the MahaRERA registration number of The Grand Tower No 1 in Lower Parel, Mumbai is P51900076793.

Is The Grand Tower No 1 registered with MahaRERA?

According to GharKundli's check of MahaRERA records (updated October 2026), The Grand Tower No 1 is registered as P51900076793 and its status is "Registered and active".

What is the current construction status of The Grand Tower No 1? How much work is done?

According to GharKundli's check of MahaRERA records (updated October 2026), The Grand Tower No 1's status on MahaRERA is "Registered and active". As filed by the builder, slab work is 91% done across 2 towers. GharKundli's full report compares construction progress with the deadline.

Does The Grand Tower No 1 have complaints on MahaRERA?

No complaints were listed on MahaRERA as of October 2026, per GharKundli's weekly check.

Is The Grand Tower No 1 safe to buy?

According to GharKundli's check of MahaRERA records (updated October 2026), The Grand Tower No 1 is registered on MahaRERA as P51900076793, its completion date has not been moved by the builder and no complaints are listed against it. GharKundli doesn't call a project safe or unsafe from these numbers alone: its full report gives a risk & trust score with every point explained.

How much GST is payable on a flat in The Grand Tower No 1?

The Grand Tower No 1 is under construction, so GST applies to a new flat: 5% of the price, with no input tax credit. The lower 1% rate is only for "affordable" homes: carpet area up to 60 sq m (about 646 sq ft) in the Mumbai region, and price up to ₹45 lakh. Flats in The Grand Tower No 1 start at 3013 sq ft carpet, above that limit, so expect 5%. There is no GST on stamp duty or registration, and none once the occupancy certificate is issued.

What is the stamp duty and registration cost for a flat in The Grand Tower No 1?

For a flat in The Grand Tower No 1 (Mumbai), stamp duty is 6% of the agreement value, or of the ready reckoner value if that's higher, including 1% Metro Cess. A woman buying in her own name pays 5%. Registration is 1% of the value, capped at ₹30,000. On a ₹1 crore flat that's about ₹6 lakh in stamp duty plus ₹30,000 registration. GharKundli's property cost calculator works it out for your price: gharkundli.com/tools/property-cost-calculator

Has The Grand Tower No 1 received its OC? Is it ready to move in?

Not yet. According to GharKundli's check of MahaRERA records (updated October 2026), The Grand Tower No 1 is still under construction, with 1 May 2028 as the latest completion date filed on MahaRERA. A flat is ready to move in only once the occupancy certificate (OC) is issued, after construction is complete.

Is The Grand Tower No 1 a redevelopment or SRA project?

According to GharKundli's check of MahaRERA records (updated October 2026), The Grand Tower No 1's planning authority on MahaRERA is MCGM, not the Slum Rehabilitation Authority, so it isn't an SRA scheme, and no flats are filed as rehab flats for existing occupants.

Has The Grand Tower No 1 uploaded its title report on MahaRERA?

According to GharKundli's check of MahaRERA records (updated October 2026), no title report for The Grand Tower No 1 was found on MahaRERA. Builders are expected to upload one; before booking, ask the builder for the advocate's title certificate in writing.

No title report is on MahaRERA for this project. See which documents are missing →

How can I get updates if The Grand Tower No 1's possession date changes?

The latest dates are on The Grand Tower No 1's MahaRERA page (P51900076793). GharKundli's Kundli Watch sends a free WhatsApp update on The Grand Tower No 1 every 1–2 months, and straight away when anything changes on MahaRERA: a later completion date, new complaints or a red flag. Your number is never shown to the builder.

How many floors does The Grand Tower No 1 have?

According to GharKundli's check of MahaRERA records (updated October 2026), The Grand Tower No 1 has 2 buildings filed: BUILDING NO 1 - A WING with 50 floors; BUILDING NO 1- B WING with 50 floors.

What are the flat sizes (carpet area) in The Grand Tower No 1?

According to GharKundli's check of MahaRERA records (updated October 2026), the builder has filed these homes for The Grand Tower No 1: 4 BHK: 3013 to 3018 sq ft carpet (87 homes); 6 BHK: 4334 to 4344 sq ft carpet (16 homes). Carpet area is the usable floor area inside the walls, as defined under RERA.

How big is the land of The Grand Tower No 1?

According to GharKundli's check of MahaRERA records (updated October 2026), The Grand Tower No 1 stands on 2,404 sq m of land (about 0.6 acres), with 50,823 sq m of sanctioned built-up area.

What are the reviews of The Grand Tower No 1?

Google Maps has reviews of The Grand Tower No 1 written by Google users; GharKundli links to them on this page but doesn't check them. For facts rather than opinions: no complaints are listed on MahaRERA, and Kundli Watch shows verified owners of the project.

What is the address and pincode of The Grand Tower No 1?

The Grand Tower No 1 by SAMIR NARAIN BHOJWANI is in Lower Parel, Mumbai, pincode 400013, Maharashtra, and is registered on MahaRERA as P51900076793, per GharKundli's check of MahaRERA records. Its land is filed as 1/434. GharKundli lists all 61 MahaRERA projects in Lower Parel (400013).

How many flats are in The Grand Tower No 1, and how many are sold?

According to GharKundli's check of MahaRERA records (updated October 2026), The Grand Tower No 1 has 103 homes in 2 towers registered on MahaRERA, and 0% of them are sold or booked.

When was The Grand Tower No 1 registered on MahaRERA?

According to GharKundli's check of MahaRERA records (updated October 2026), The Grand Tower No 1 was registered on MahaRERA on 28 June 2024. GharKundli did not find a title report on the land on file there.

Does The Grand Tower No 1 have any legal issues or court cases?

No court cases are listed for The Grand Tower No 1 on MahaRERA, per GharKundli's check of MahaRERA records (updated October 2026).

Who is the builder / developer of The Grand Tower No 1?

According to GharKundli's check of MahaRERA records (updated October 2026), the builder is SAMIR NARAIN BHOJWANI.

All projects with possession due in 2028 in Mumbai City →

Other projects in Lower Parel (400013)

All 61 projects in Lower Parel (400013) →

Data compiled by GharKundli (gharkundli.com) from MahaRERA public records, as of October 2026. Check the project’s MahaRERA page for the latest filings. Not legal advice.