by Bhuvnesh Enterprises · Bandra, Mumbai 400050Also near Khar West, Santacruz West, Nashik RoadRegistered on MahaRERA as “Westside”

What’s in the report? →

Possession date of Bhuvnesh Westside (MahaRERA P51900010464): 31 March 2028, moved from 30 December 2022 (63 months later). It has 18 homes (2 BHK and Duplex, 556–782 sq ft carpet), 95% sold or booked. No complaints on MahaRERA. How to check it yourself

Registered on MahaRERA under P51900010464, and currently active.

Source: MahaRERA website — records for P51900010464, read and compiled by GharKundli. Facts as filed on MahaRERA, no opinions.

What do you want to know about Bhuvnesh Westside?

1 court case MahaRERA par listed. Kya jaanna hai?Tap a question. We’ll answer you on WhatsApp, free.

Ask something else on WhatsAppNo login needed. A real person replies.

Or leave your number, we’ll message you:

How the possession date of Bhuvnesh Westside has moved

  1. 30 December 2022

    Completion date given when the project was registered

  2. 30 December 2023

    Extended at the builder's request (MahaRERA application EXT51900012579)

    Reason the builder gave MahaRERA:
    “In accordance with circular no 28, we hereby apply for extension of our project u/s 6 in Format B. The project was delayed for reasons beyond our control on account of various reasons and more particularly on account of the pandemic of Covi…” Read the full reason“In accordance with circular no 28, we hereby apply for extension of our project u/s 6 in Format B. The project was delayed for reasons beyond our control on account of various reasons and more particularly on account of the pandemic of Covid-19.”
  3. 30 December 2025

    Extended at the builder's request (MahaRERA application EXT51900025572)

    Reason the builder gave MahaRERA:
    “We apologize for the delay in the completion of the project and the submission of this request. The delay has occurred due to issues with procurement, unforeseen site conditions, and coordination challenges. Despite these setbacks, we are w…” Read the full reason“We apologize for the delay in the completion of the project and the submission of this request. The delay has occurred due to issues with procurement, unforeseen site conditions, and coordination challenges. Despite these setbacks, we are working diligently to address these issues and complete the remaining work. We are closely monitoring progress and taking all necessary steps to ensure timely completion. Given the circumstances, we kindly request an extension until 30-12-2025 to complete the project and fulfill all regulatory requirements.”
  4. 31 March 2028

    Extended at the builder's request (MahaRERA application EA08042620584)

    Reason the builder gave MahaRERA:
    “The construction work of the project has been completed in accordance with the approved plans, and the application for Occupancy Certificate has been duly submitted to the competent authority. However, the Occupancy Certificate has not yet…” Read the full reason“The construction work of the project has been completed in accordance with the approved plans, and the application for Occupancy Certificate has been duly submitted to the competent authority. However, the Occupancy Certificate has not yet been issued due to administrative and procedural timelines at the authority’s end, which are beyond our control. In view of the same, we request an extension of the project registration period until receipt of the Occupancy Certificate. Given the circumstances, we kindly request an extension until 31-03-2028, to complete the project and fulfil all regulat…”

Source: Bhuvnesh Westside’s extension records on MahaRERA (P51900010464), read by GharKundli in October 2026. The builder’s reasons are quoted as filed. Your own possession date is the one in your agreement for sale.

What builders tell MahaRERA when they’re late: 14,973 applications analysed →

GharKundli’s full report on Bhuvnesh Westside

Read from every filing on MahaRERA when you open it

  • Risk & trust score, every point explained
  • What the title report says about the land
  • Each of the 1 court case, and how it ended
  • Construction pace against the March 2028 deadline
  • Agreement clauses weaker than the RERA model
  • Escrow audit, loans and the builder's record
  • Questions to get answered in writing before you pay
MahaRERA registration
P51900010464
Status
Registered and active
Builder
Bhuvnesh Enterprises
Location
Bandra, Mumbai · 400050
Project type
Residential / Group Housing
Registered on
27 Aug 2017
Completion date at registration
December 2022
Latest completion date
March 2028
Delay so far
63 months
Homes
18
Sold or booked
95%
Towers
1
Complaints on MahaRERA
0
Court cases listed
1
Title report on file
Not found

Construction progress of Bhuvnesh Westside, as filed by the builder

What the builder has reported to MahaRERA, as GharKundli read it in October 2026. GharKundli’s full report compares it with the deadline.

Tower / wingPlinthSlabs (structure)Internal workLifts, fire & electrical
Westside100%100%100%95%

Commencement certificate (CC), as filed on MahaRERA

  • Westside: covers 13 floors

Want to know when this changes? Kundli Watch sends a free WhatsApp update on Bhuvnesh Westside every 1–2 months.

Bhuvnesh Westside: buildings, flats and land, as filed on MahaRERA

TypeCarpet area (sq ft)Units
2 BHK556 – 78216
Duplex7822
Shops5821

The builder’s record and reviews

Not enough of this builder’s other MahaRERA projects have reached their promised date to judge yet.

Read Google reviews of Bhuvnesh Westside →Reviews on Google are opinions by Google users; GharKundli doesn’t check them.

Kundli Watch

Bhuvnesh Westside: buyers & owners

Free: a construction progress update on WhatsApp every 1–2 months, and straight away when anything changes on MahaRERA — a later completion date, new complaints, a red flag. Your number stays private: never shown to other members or the builder.

Be the first to watch this project.

How are you connected to this project?

Watching needs only WhatsApp or your number. Bought here? No document needed now. From the builder’s team? Join to answer buyers’ questions; you never see members’ details. Owners and the builder’s team sign in with a one-time code, then come straight back here.

Common questions about Bhuvnesh Westside

What is the possession date of Bhuvnesh Westside?

According to GharKundli's check of MahaRERA records (updated October 2026), the latest completion date filed on MahaRERA for Bhuvnesh Westside in Bandra, Mumbai is 31 March 2028 — 63 months later than 30 December 2022, the date given at registration.

The date has already moved 63 months. Will it move again? Check the real pace of construction →

Is the builder's possession date different from the MahaRERA date for Bhuvnesh Westside?

Builders and listing sites often quote an earlier "target" date for handover. The completion date Bhuvnesh Westside's builder has filed on MahaRERA, the official one, is 31 March 2028, already 63 months later than the 30 December 2022 given at registration, per GharKundli's check of MahaRERA records. If possession is late, what counts under RERA (Section 18) is the possession date written in your agreement for sale.

Why was the possession date of Bhuvnesh Westside extended?

According to GharKundli's check of MahaRERA records (updated October 2026), Bhuvnesh Westside's builder applied to MahaRERA to extend the completion date 3 times: to 30 December 2023, giving the reason "In accordance with circular no 28, we hereby apply for extension of our project u/s 6 in Format B. The project was delayed for reasons beyond our control on account of various reasons and more particularly on account of the pandemic of Covid-19."; to 30 December 2025, giving the reason "We apologize for the delay in the completion of the project and the submission of this request. The delay has occurred due to issues with procurement, unforeseen site conditions, and coordination challenges. Despite these setbacks, we are working diligently to address these issues and complete the remaining work. We are closely monitoring progress and taking all necessary steps to ensure timely completion. Given the circumstances, we kindly request an extension until 30-12-2025 to complete the project and fulfill all regulatory requirements."; to 31 March 2028, giving the reason "The construction work of the project has been completed in accordance with the approved plans, and the application for Occupancy Certificate has been duly submitted to the competent authority. However, the Occupancy Certificate has not yet been issued due to administrative and procedural timelines at the authority’s end, which are beyond our control. In view of the same, we request an extension of the project registration period until receipt of the Occupancy Certificate. Given the circumstances, we kindly request an extension until 31-03-2028, to complete the project and fulfil all regulat…".

What is the RERA number of Bhuvnesh Westside?

According to GharKundli's check of MahaRERA records (updated October 2026), the MahaRERA registration number of Bhuvnesh Westside in Bandra, Mumbai is P51900010464.

Is Bhuvnesh Westside registered with MahaRERA?

According to GharKundli's check of MahaRERA records (updated October 2026), Bhuvnesh Westside is registered as P51900010464 and its status is "Registered and active".

What is the current construction status of Bhuvnesh Westside? How much work is done?

According to GharKundli's check of MahaRERA records (updated October 2026), Bhuvnesh Westside's status on MahaRERA is "Registered and active". As filed by the builder, slab work on Westside is 100% done and internal work 100%. GharKundli's full report compares construction progress with the deadline.

Does Bhuvnesh Westside have complaints on MahaRERA?

No complaints were listed on MahaRERA as of October 2026, per GharKundli's weekly check.

Is Bhuvnesh Westside safe to buy?

According to GharKundli's check of MahaRERA records (updated October 2026), Bhuvnesh Westside is registered on MahaRERA as P51900010464, its completion date has moved 63 months since registration and no complaints are listed against it. GharKundli doesn't call a project safe or unsafe from these numbers alone: its full report gives a risk & trust score with every point explained.

How much GST is payable on a flat in Bhuvnesh Westside?

Bhuvnesh Westside is under construction, so GST applies to a new flat: 5% of the price, with no input tax credit. The lower 1% rate is only for "affordable" homes: carpet area up to 60 sq m (about 646 sq ft) in the Mumbai region, and price up to ₹45 lakh. Some flats in Bhuvnesh Westside are 556 sq ft carpet, small enough for 1% if the price is ₹45 lakh or less. There is no GST on stamp duty or registration, and none once the occupancy certificate is issued.

What is the stamp duty and registration cost for a flat in Bhuvnesh Westside?

For a flat in Bhuvnesh Westside (Mumbai), stamp duty is 6% of the agreement value, or of the ready reckoner value if that's higher, including 1% Metro Cess. A woman buying in her own name pays 5%. Registration is 1% of the value, capped at ₹30,000. On a ₹1 crore flat that's about ₹6 lakh in stamp duty plus ₹30,000 registration. GharKundli's property cost calculator works it out for your price: gharkundli.com/tools/property-cost-calculator

Has Bhuvnesh Westside received its OC? Is it ready to move in?

Not yet. According to GharKundli's check of MahaRERA records (updated October 2026), Bhuvnesh Westside is still under construction, with 31 March 2028 as the latest completion date filed on MahaRERA. A flat is ready to move in only once the occupancy certificate (OC) is issued, after construction is complete.

Has Bhuvnesh Westside uploaded its title report on MahaRERA?

According to GharKundli's check of MahaRERA records (updated October 2026), no title report for Bhuvnesh Westside was found on MahaRERA. Builders are expected to upload one; before booking, ask the builder for the advocate's title certificate in writing.

No title report is on MahaRERA for this project. See which documents are missing →

How can I get updates if Bhuvnesh Westside's possession date changes?

The latest dates are on Bhuvnesh Westside's MahaRERA page (P51900010464). GharKundli's Kundli Watch sends a free WhatsApp update on Bhuvnesh Westside every 1–2 months, and straight away when anything changes on MahaRERA: a later completion date, new complaints or a red flag. Your number is never shown to the builder.

How many floors does Bhuvnesh Westside have?

According to GharKundli's check of MahaRERA records (updated October 2026), Bhuvnesh Westside has one building filed: Westside with 18 floors and 19 units.

What are the flat sizes (carpet area) in Bhuvnesh Westside?

According to GharKundli's check of MahaRERA records (updated October 2026), the builder has filed these homes for Bhuvnesh Westside: 2 BHK: 556 to 782 sq ft carpet (16 homes); Duplex: 782 sq ft carpet (2 homes). Carpet area is the usable floor area inside the walls, as defined under RERA.

How big is the land of Bhuvnesh Westside?

According to GharKundli's check of MahaRERA records (updated October 2026), Bhuvnesh Westside stands on 523 sq m of land (about 0.1 acres), with 1,397 sq m of sanctioned built-up area.

What are the reviews of Bhuvnesh Westside?

Google Maps has reviews of Bhuvnesh Westside written by Google users; GharKundli links to them on this page but doesn't check them. For facts rather than opinions: no complaints are listed on MahaRERA, and Kundli Watch shows verified owners of the project.

What is the address and pincode of Bhuvnesh Westside?

Bhuvnesh Westside by Bhuvnesh Enterprises is in Bandra, Mumbai, pincode 400050 (near Khar West, Santacruz West, Nashik Road), Maharashtra, and is registered on MahaRERA as P51900010464, per GharKundli's check of MahaRERA records. Its boundaries filed there include Chappel Road. Its land is filed as B 645. GharKundli lists all 168 MahaRERA projects in Bandra West (400050).

How many flats are in Bhuvnesh Westside, and how many are sold?

According to GharKundli's check of MahaRERA records (updated October 2026), Bhuvnesh Westside has 18 homes in 1 tower registered on MahaRERA, and 95% of them are sold or booked.

When was Bhuvnesh Westside registered on MahaRERA?

According to GharKundli's check of MahaRERA records (updated October 2026), Bhuvnesh Westside was registered on MahaRERA on 27 August 2017. GharKundli did not find a title report on the land on file there.

Does Bhuvnesh Westside have any legal issues or court cases?

1 court case is listed for Bhuvnesh Westside on MahaRERA, per GharKundli's check of MahaRERA records (updated October 2026). GharKundli's full report explains each case and how it ended.

A court case can stall a project or tie up the land. See what the case is about →

Who is the builder / developer of Bhuvnesh Westside?

According to GharKundli's check of MahaRERA records (updated October 2026), the builder is Bhuvnesh Enterprises.

All projects with possession due in 2028 in Mumbai Suburban →

Other projects in Bandra West (400050)

All 168 projects in Bandra West (400050) →

Data compiled by GharKundli (gharkundli.com) from MahaRERA public records, as of October 2026. Check the project’s MahaRERA page for the latest filings. Not legal advice.