by HILTON INFRASTRUCTURE (Rubberwala) · Agripada, MumbaiAlso near Girgaon, Nagpada, Khetwadi

Possession date of FUEGO: 30 October 2027, moved from 30 December 2022 (54 months later). This is the latest completion date the builder has filed on MahaRERA. How to check it yourself

Registered on MahaRERA under P51900009939, and currently active. Its completion date has moved from December 2022 to October 2027: 54 months at the builder's request, plus MahaRERA's automatic 4-month extension for all eligible projects. 8 complaints are listed against it on MahaRERA.

Source: GharKundli’s check of MahaRERA records, October 2026.

What do you want to know about FUEGO?

Ask us on WhatsAppNo login needed. A real person replies.

How the possession date of FUEGO has moved

  1. 30 December 2022

    Completion date given when the project was registered

  2. 30 December 2023

    Extended at the builder's request (MahaRERA application EXT51900013092)

    Reason the builder gave MahaRERA:
    “In accordance with circular no 28, we hereby apply for extension of our project u/s 6 in Format B. The project was delayed for reasons beyond our control on account of various reasons and more particularly on account of the pandemic of Covi…” Read the full reason“In accordance with circular no 28, we hereby apply for extension of our project u/s 6 in Format B. The project was delayed for reasons beyond our control on account of various reasons and more particularly on account of the pandemic of Covid-19.”
  3. 30 December 2024

    Extended at the builder's request (MahaRERA application EXT51900018646)

    Reason the builder gave MahaRERA:
    “In accordance with circular no 28, we hereby apply for extension of our project u/s 7(3) in Format B. The project was delayed for reasons beyond our control on account of various reasons and more particularly on account of the pandemic of C…” Read the full reason“In accordance with circular no 28, we hereby apply for extension of our project u/s 7(3) in Format B. The project was delayed for reasons beyond our control on account of various reasons and more particularly on account of the pandemic of Covid-19. We have consent of % allottees for purpose of extension of RERA registration period of the said project.”
  4. 30 December 2025

    Extended at the builder's request (MahaRERA application EXT51900026067)

    Reason the builder gave MahaRERA: “We have almost completed the project and we have attached site photos for your reference so we required 1 year extension for our sale and we will apply for the OC. please grant Extension.”
  5. 30 June 2027

    Extended at the builder's request (MahaRERA application EA09012619385)

    Reason the builder gave MahaRERA:
    “The construction of the project is substantially completed. However, due to slow sales and resultant financial constraints, the completion and sale of the remaining units got delayed. Hence, extension of the project registration is required…” Read the full reason“The construction of the project is substantially completed. However, due to slow sales and resultant financial constraints, the completion and sale of the remaining units got delayed. Hence, extension of the project registration is required up to 30.06.2027”
  6. 30 October 2027

    MahaRERA's automatic 4-month extension for all eligible projects, not the builder's request

Source: FUEGO’s extension records on MahaRERA (P51900009939), read by GharKundli in October 2026. The builder’s reasons are quoted as filed. Your own possession date is the one in your agreement for sale.

What builders tell MahaRERA when they’re late: 14,973 applications analysed →

GharKundli’s full report on FUEGO

Read from every filing on MahaRERA when you open it

  • Risk & trust score, every point explained
  • What the title report says about the land
  • Each of the 8 complaints and 3 court cases, and how it ended
  • Construction pace against the October 2027 deadline
  • Agreement clauses weaker than the RERA model
  • Escrow audit, loans and the builder's record
  • Questions to get answered in writing before you pay
MahaRERA registration
P51900009939
Status
Registered and active
Builder
HILTON INFRASTRUCTURE
Location
Agripada, Mumbai · 400008
Project type
Residential / Group Housing
Registered on
22 Aug 2017
Completion date at registration
December 2022
Latest completion date
October 2027
Delay so far
54 months
MahaRERA's automatic extension
+4 months (force majeure, all eligible projects)
Homes
219
Sold or booked
57%
Towers
3
Complaints on MahaRERA
8
Court cases listed
3
Appeals at the tribunal
6
Title report on file
Not found

Construction progress of FUEGO, as filed by the builder

What the builder has reported to MahaRERA, as GharKundli read it in October 2026. GharKundli’s full report compares it with the deadline.

Tower / wingPlinthSlabs (structure)Internal workLifts, fire & electrical
BUILDING A100%100%90%80%
BUILDING B100%100%100%100%
BUILDING C100%100%100%100%

Commencement certificate (CC), as filed on MahaRERA

  • BUILDING A: covers 20 floors
  • BUILDING B: covers 17 floors
  • BUILDING C: covers 0 floors

Want to know when this changes? Kundli Watch sends a free WhatsApp update on FUEGO every month.

FUEGO: buildings, flats and land, as filed on MahaRERA

TypeCarpet area (sq ft)Units
Unspecified—198
2 BHK587 – 831139
1 BHK335 – 42866
Other49914
Office Space2,9371
  • Buildings: BUILDING A (30 floors, 210 units) · BUILDING B (17 floors, 10 units) · BUILDING C (12 floors)
  • Land: 4,246 sq m (about 1.0 acres) · sanctioned built-up 15,936 sq m · recreational space 314 sq m
  • Map: the location the builder filed on MahaRERA

The builder’s record and reviews

Rubberwala Housing & Infrastructure (a group of 10 linked companies) has 10 projects on MahaRERA since 2017, this one included. Of the 10 GharKundli has checked: 2 finished, 1 within the promised date and 1 needed more time (typically 61 months); 7 still being built, 3 past the promised date (typically 30 months late); 1 lapsed. 13 complaints on MahaRERA across 2 projects.

Read Google reviews of FUEGO →Reviews on Google are opinions by Google users; GharKundli doesn’t check them.

Kundli Watch

FUEGO: buyers & owners

Free: a WhatsApp update every month on this project, and straight away when anything changes on MahaRERA — a later completion date, new complaints, a red flag. Your number stays private: never shown to other members or the builder.

Be the first to watch this project.

How are you connected to this project?

Bought here? No document needed now. From the builder’s team? Join to answer buyers’ questions; you never see members’ details. You’ll sign in with a one-time code, then come straight back here.

Common questions about FUEGO

What is the possession date of FUEGO?

According to GharKundli's check of MahaRERA records (updated October 2026), the latest completion date filed on MahaRERA for FUEGO in Agripada, Mumbai is 30 October 2027 — 54 months later than 30 December 2022, the date given at registration, plus MahaRERA's automatic 4-month extension for all eligible projects.

Is the builder's possession date different from the MahaRERA date for FUEGO?

Builders and listing sites often quote an earlier "target" date for handover. The completion date FUEGO's builder has filed on MahaRERA, the official one, is 30 October 2027, already 54 months later than the 30 December 2022 given at registration, per GharKundli's check of MahaRERA records. If possession is late, what counts under RERA (Section 18) is the possession date written in your agreement for sale.

Why was the possession date of FUEGO extended?

According to GharKundli's check of MahaRERA records (updated October 2026), FUEGO's builder applied to MahaRERA to extend the completion date 4 times: to 30 December 2023, giving the reason "In accordance with circular no 28, we hereby apply for extension of our project u/s 6 in Format B. The project was delayed for reasons beyond our control on account of various reasons and more particularly on account of the pandemic of Covid-19."; to 30 December 2024, giving the reason "In accordance with circular no 28, we hereby apply for extension of our project u/s 7(3) in Format B. The project was delayed for reasons beyond our control on account of various reasons and more particularly on account of the pandemic of Covid-19. We have consent of % allottees for purpose of extension of RERA registration period of the said project."; to 30 December 2025, giving the reason "We have almost completed the project and we have attached site photos for your reference so we required 1 year extension for our sale and we will apply for the OC. please grant Extension."; to 30 June 2027, giving the reason "The construction of the project is substantially completed. However, due to slow sales and resultant financial constraints, the completion and sale of the remaining units got delayed. Hence, extension of the project registration is required up to 30.06.2027". MahaRERA also added its automatic 4-month extension for all eligible projects.

What is the RERA number of FUEGO?

According to GharKundli's check of MahaRERA records (updated October 2026), the MahaRERA registration number of FUEGO in Agripada, Mumbai is P51900009939.

Is FUEGO registered with MahaRERA?

According to GharKundli's check of MahaRERA records (updated October 2026), FUEGO is registered as P51900009939 and its status is "Registered and active".

What is the construction status of FUEGO?

According to GharKundli's check of MahaRERA records (updated October 2026), FUEGO's status on MahaRERA is "Registered and active". As filed by the builder, slab work is 100% done across 3 towers. GharKundli's full report compares construction progress with the deadline.

Does FUEGO have complaints on MahaRERA?

8 complaints were listed on MahaRERA as of October 2026, per GharKundli's weekly check. GharKundli's full report explains each case and how it ended.

Is FUEGO safe to buy?

According to GharKundli's check of MahaRERA records (updated October 2026), FUEGO is registered on MahaRERA as P51900009939, its completion date has moved 54 months since registration and 8 complaints are listed against it. GharKundli doesn't call a project safe or unsafe from these numbers alone: its full report gives a risk & trust score with every point explained.

How can I get updates if FUEGO's possession date changes?

The latest dates are on FUEGO's MahaRERA page (P51900009939). GharKundli's Kundli Watch sends a free WhatsApp update on FUEGO every month, and straight away when anything changes on MahaRERA: a later completion date, new complaints or a red flag. Your number is never shown to the builder.

How many floors does FUEGO have?

According to GharKundli's check of MahaRERA records (updated October 2026), FUEGO has 3 buildings filed: BUILDING A with 30 floors and 210 units; BUILDING B with 17 floors and 10 units; BUILDING C with 12 floors.

What are the flat sizes (carpet area) in FUEGO?

According to GharKundli's check of MahaRERA records (updated October 2026), the builder has filed these homes for FUEGO: 2 BHK: 587 to 831 sq ft carpet (139 homes); 1 BHK: 335 to 428 sq ft carpet (66 homes); Other: 499 sq ft carpet (14 homes). Carpet area is the usable floor area inside the walls, as defined under RERA.

How big is the land of FUEGO?

According to GharKundli's check of MahaRERA records (updated October 2026), FUEGO stands on 4,246 sq m of land (about 1.0 acres), with 15,936 sq m of sanctioned built-up area and 314 sq m of recreational open space.

What is the track record of FUEGO's builder?

According to GharKundli's check of MahaRERA records (updated October 2026), Rubberwala Housing & Infrastructure (a group of 10 linked companies) has 10 projects on MahaRERA since 2017, this one included. Of the 10 GharKundli has checked: 2 finished, 1 within the promised date and 1 needed more time (typically 61 months); 7 still being built, 3 past the promised date (typically 30 months late); 1 lapsed. 13 complaints on MahaRERA across 2 projects. GharKundli's full report covers the builder's record in detail.

Where can I read reviews of FUEGO?

Google Maps has reviews of FUEGO written by Google users; GharKundli links to them on this page but doesn't check them. For facts rather than opinions: 8 complaints are listed on MahaRERA, and Kundli Watch shows verified owners of the project.

Where is FUEGO?

FUEGO by HILTON INFRASTRUCTURE (Rubberwala) is in Agripada, Mumbai (pincode 400008), near Girgaon, Nagpada, Khetwadi, Maharashtra, and is registered on MahaRERA as P51900009939, per GharKundli's check of MahaRERA records.

How many homes are in FUEGO?

According to GharKundli's check of MahaRERA records (updated October 2026), FUEGO has 219 homes in 3 towers registered on MahaRERA, and 57% of them are sold or booked.

When was FUEGO registered on MahaRERA?

According to GharKundli's check of MahaRERA records (updated October 2026), FUEGO was registered on MahaRERA on 22 August 2017. GharKundli did not find a title report on the land on file there.

Are there court cases on FUEGO?

3 court cases are listed for FUEGO on MahaRERA, and 6 appeals at the tribunal, per GharKundli's check of MahaRERA records (updated October 2026). GharKundli's full report explains each case and how it ended.

Who is the builder of FUEGO?

According to GharKundli's check of MahaRERA records (updated October 2026), the builder is HILTON INFRASTRUCTURE, the company Rubberwala files this project under.

All projects with possession due in 2027 in Mumbai City →

Other projects in Agripada

All 75 projects in Mumbai Central (400008) →

Data compiled by GharKundli (gharkundli.com) from MahaRERA public records, as of October 2026. Check the project’s MahaRERA page for the latest filings. Not legal advice.