Meher Villa
by LIVING STONE CONSTRUCTION PRIVATE LIMITED (Livstone) · Agripada, Mumbai 400008Also near Tardeo, Byculla, mumbai central
What’s in the report? →Possession date of Meher Villa (MahaRERA P51900016529): 31 July 2026, moved from 30 December 2023 (27 months later), and it has already passed. It has 20 homes (2 BHK, 3 BHK and 4 BHK, 650–1619 sq ft carpet), 91% sold or booked. No complaints on MahaRERA. How to check it yourself
Registered on MahaRERA under P51900016529. Status: Lapsed (registration period ended). Its completion date has moved from December 2023 to July 2026: 27 months at the builder's request, plus MahaRERA's automatic 4-month extension for all eligible projects.
Source: MahaRERA website — records for P51900016529, read and compiled by GharKundli. Facts as filed on MahaRERA, no opinions.
The latest completion date on MahaRERA (July 2026) has passed.
What do you want to know about Meher Villa?
Completion date nikal chuki hai. Kya poochna hai?Tap a question. We’ll answer you on WhatsApp, free.
How the possession date of Meher Villa has moved
30 December 2023
Completion date given when the project was registered
31 March 2026
Extended at the builder's request (MahaRERA application EXT51900025202)
Reason the builder gave MahaRERA:
“The project was initially delayed due to complications surrounding the installation of a mechanical parking system. The project team had partnered with a specific parking manufacturer, believing their equipment would meet the project's requ…” Read the full reason
“The project was initially delayed due to complications surrounding the installation of a mechanical parking system. The project team had partnered with a specific parking manufacturer, believing their equipment would meet the project's requirements. However, after a significant period of delay-round one year-the manufacturer delivered defective equipment. This created a major setback, as the faulty system failed to meet the standards necessary for proper installation and operation. As a result of receiving subpar equipment, the project team was forced to terminate their relationship with th…”31 July 2026
MahaRERA's automatic 4-month extension for all eligible projects, not the builder's request
Source: Meher Villa’s extension records on MahaRERA (P51900016529), read by GharKundli in October 2026. The builder’s reasons are quoted as filed. Your own possession date is the one in your agreement for sale.
What builders tell MahaRERA when they’re late: 14,973 applications analysed →GharKundli’s full report on Meher Villa
Read from every filing on MahaRERA when you open it
- Risk & trust score, every point explained
- What the title report says about the land
- Each complaint and court case, and how it ended
- Construction pace against the July 2026 deadline
- Agreement clauses weaker than the RERA model
- Escrow audit, loans and the builder's record
- Questions to get answered in writing before you pay
- MahaRERA registration
- P51900016529
- Status
- Lapsed (registration period ended)
- Builder
- LIVING STONE CONSTRUCTION PRIVATE LIMITED
- Location
- Agripada, Mumbai · 400008
- Project type
- Residential / Group Housing
- Registered on
- 21 May 2018
- Completion date at registration
- December 2023
- Latest completion date
- July 2026
- Delay so far
- 27 months
- MahaRERA's automatic extension
- +4 months (force majeure, all eligible projects)
- Homes
- 20
- Sold or booked
- 91%
- Towers
- 1
- Complaints on MahaRERA
- 0
- Court cases listed
- 0
- Title report on file
- Not found
Construction progress of Meher Villa, as filed by the builder
What the builder has reported to MahaRERA, as GharKundli read it in October 2026. GharKundli’s full report compares it with the deadline.
| Tower / wing | Plinth | Slabs (structure) | Internal work | Lifts, fire & electrical |
|---|---|---|---|---|
| MEHER VILLA | 100% | 100% | 100% | 100% |
Commencement certificate (CC), as filed on MahaRERA
- MEHER VILLA: covers This CC is issued upto plinth level for proposed building (for zero F.S.I.)
Want to know when this changes? Kundli Watch sends a free WhatsApp update on Meher Villa every 1–2 months.
Meher Villa: buildings, flats and land, as filed on MahaRERA
| Type | Carpet area (sq ft) | Units |
|---|---|---|
| 4 BHK | 650 – 1,619 | 18 |
| 2 BHK | 882 | 1 |
| 3 BHK | 882 | 1 |
- Buildings: MEHER VILLA (18 floors, 20 units)
- Land: 717 sq m (about 0.2 acres) · sanctioned built-up 2,902 sq m
- Land, as filed: 1600
- Map: the location the builder filed on MahaRERA · Get directions
The builder’s record and reviews
Living Stone Construction (a group of 7 linked companies) has 7 projects on MahaRERA since 2017, this one included. Of the 7 GharKundli has checked: 1 finished, 0 within the promised date and 1 needed more time (typically 67 months); 3 still being built, 2 past the promised date (typically 12 months late); 3 lapsed. 5 complaints on MahaRERA across 2 projects.
Read Google reviews of Meher Villa →Reviews on Google are opinions by Google users; GharKundli doesn’t check them.
Kundli Watch
Meher Villa: buyers & owners
Free: a construction progress update on WhatsApp every 1–2 months, and straight away when anything changes on MahaRERA — a later completion date, new complaints, a red flag. Your number stays private: never shown to other members or the builder.
Be the first to watch this project.
How are you connected to this project?
Watching needs only WhatsApp or your number. Bought here? No document needed now. From the builder’s team? Join to answer buyers’ questions; you never see members’ details. Owners and the builder’s team sign in with a one-time code, then come straight back here.
Common questions about Meher Villa
What is the possession date of Meher Villa?
According to GharKundli's check of MahaRERA records (updated October 2026), the latest completion date filed on MahaRERA for Meher Villa in Agripada, Mumbai is 31 July 2026 — 27 months later than 30 December 2023, the date given at registration, plus MahaRERA's automatic 4-month extension for all eligible projects. That date has already passed.
The date has already moved 27 months. Will it move again? Check the real pace of construction →
Is the builder's possession date different from the MahaRERA date for Meher Villa?
Builders and listing sites often quote an earlier "target" date for handover. The completion date Meher Villa's builder has filed on MahaRERA, the official one, is 31 July 2026, already 27 months later than the 30 December 2023 given at registration, per GharKundli's check of MahaRERA records. If possession is late, what counts under RERA (Section 18) is the possession date written in your agreement for sale.
Why was the possession date of Meher Villa extended?
According to GharKundli's check of MahaRERA records (updated October 2026), Meher Villa's builder applied to MahaRERA to extend the completion date once: to 31 March 2026, giving the reason "The project was initially delayed due to complications surrounding the installation of a mechanical parking system. The project team had partnered with a specific parking manufacturer, believing their equipment would meet the project's requirements. However, after a significant period of delay-round one year-the manufacturer delivered defective equipment. This created a major setback, as the faulty system failed to meet the standards necessary for proper installation and operation. As a result of receiving subpar equipment, the project team was forced to terminate their relationship with th…". MahaRERA also added its automatic 4-month extension for all eligible projects.
What is the RERA number of Meher Villa?
According to GharKundli's check of MahaRERA records (updated October 2026), the MahaRERA registration number of Meher Villa in Agripada, Mumbai is P51900016529.
Is Meher Villa registered with MahaRERA?
According to GharKundli's check of MahaRERA records (updated October 2026), Meher Villa is registered as P51900016529 and its status is "Lapsed (registration period ended)".
What is the current construction status of Meher Villa? How much work is done?
According to GharKundli's check of MahaRERA records (updated October 2026), Meher Villa's status on MahaRERA is "Lapsed (registration period ended)". As filed by the builder, slab work on MEHER VILLA is 100% done and internal work 100%. GharKundli's full report compares construction progress with the deadline.
Does Meher Villa have complaints on MahaRERA?
No complaints were listed on MahaRERA as of October 2026, per GharKundli's weekly check.
Is Meher Villa safe to buy?
According to GharKundli's check of MahaRERA records (updated October 2026), Meher Villa is registered on MahaRERA as P51900016529, its MahaRERA status is "Lapsed (registration period ended)", its completion date has moved 27 months since registration and no complaints are listed against it. GharKundli doesn't call a project safe or unsafe from these numbers alone: its full report gives a risk & trust score with every point explained.
How much GST is payable on a flat in Meher Villa?
Meher Villa isn't marked completed on MahaRERA, so until the occupancy certificate is issued GST applies to a new flat: 5% of the price, with no input tax credit. The lower 1% rate is only for "affordable" homes: carpet area up to 60 sq m (about 646 sq ft) in the Mumbai region, and price up to ₹45 lakh. Flats in Meher Villa start at 650 sq ft carpet, above that limit, so expect 5%. There is no GST on stamp duty or registration, and none once the occupancy certificate is issued.
What is the stamp duty and registration cost for a flat in Meher Villa?
For a flat in Meher Villa (Mumbai), stamp duty is 6% of the agreement value, or of the ready reckoner value if that's higher, including 1% Metro Cess. A woman buying in her own name pays 5%. Registration is 1% of the value, capped at ₹30,000. On a ₹1 crore flat that's about ₹6 lakh in stamp duty plus ₹30,000 registration. GharKundli's property cost calculator works it out for your price: gharkundli.com/tools/property-cost-calculator
Has Meher Villa received its OC? Is it ready to move in?
Not yet. According to GharKundli's check of MahaRERA records (updated October 2026), Meher Villa isn't completed: its MahaRERA status is "Lapsed (registration period ended)", with 31 July 2026 as the latest completion date filed on MahaRERA, and that date has passed. A flat is ready to move in only once the occupancy certificate (OC) is issued, after construction is complete.
What does "lapsed" mean for Meher Villa?
According to GharKundli's check of MahaRERA records (updated October 2026), Meher Villa's registration shows as lapsed on MahaRERA. Lapsed means the completion date on MahaRERA (31 July 2026) passed without the project being marked complete or the registration being extended. Before paying anything, ask the builder in writing whether an extension has been applied for.
Is Meher Villa a redevelopment or SRA project?
According to GharKundli's check of MahaRERA records (updated October 2026), Meher Villa is a redevelopment: 9 of its flats are set aside for existing occupants (rehab), and the rest are for sale.
Has Meher Villa uploaded its title report on MahaRERA?
According to GharKundli's check of MahaRERA records (updated October 2026), no title report for Meher Villa was found on MahaRERA. Builders are expected to upload one; before booking, ask the builder for the advocate's title certificate in writing.
No title report is on MahaRERA for this project. See which documents are missing →
How can I get updates if Meher Villa's possession date changes?
The latest dates are on Meher Villa's MahaRERA page (P51900016529). GharKundli's Kundli Watch sends a free WhatsApp update on Meher Villa every 1–2 months, and straight away when anything changes on MahaRERA: a later completion date, new complaints or a red flag. Your number is never shown to the builder.
How many floors does Meher Villa have?
According to GharKundli's check of MahaRERA records (updated October 2026), Meher Villa has one building filed: MEHER VILLA with 18 floors and 20 units.
What are the flat sizes (carpet area) in Meher Villa?
According to GharKundli's check of MahaRERA records (updated October 2026), the builder has filed these homes for Meher Villa: 4 BHK: 650 to 1619 sq ft carpet (18 homes); 2 BHK: 882 sq ft carpet (1 homes); 3 BHK: 882 sq ft carpet (1 homes). Carpet area is the usable floor area inside the walls, as defined under RERA.
How big is the land of Meher Villa?
According to GharKundli's check of MahaRERA records (updated October 2026), Meher Villa stands on 717 sq m of land (about 0.2 acres), with 2,902 sq m of sanctioned built-up area.
What is the track record of Meher Villa's builder?
According to GharKundli's check of MahaRERA records (updated October 2026), Living Stone Construction (a group of 7 linked companies) has 7 projects on MahaRERA since 2017, this one included. Of the 7 GharKundli has checked: 1 finished, 0 within the promised date and 1 needed more time (typically 67 months); 3 still being built, 2 past the promised date (typically 12 months late); 3 lapsed. 5 complaints on MahaRERA across 2 projects. GharKundli's full report covers the builder's record in detail.
What are the reviews of Meher Villa?
Google Maps has reviews of Meher Villa written by Google users; GharKundli links to them on this page but doesn't check them. For facts rather than opinions: no complaints are listed on MahaRERA, and Kundli Watch shows verified owners of the project.
What is the address and pincode of Meher Villa?
Meher Villa by LIVING STONE CONSTRUCTION PRIVATE LIMITED (Livstone) is in Agripada, Mumbai, pincode 400008 (near Tardeo, Byculla, mumbai central), Maharashtra, and is registered on MahaRERA as P51900016529, per GharKundli's check of MahaRERA records. Its land is filed as 1600. GharKundli lists all 75 MahaRERA projects in Mumbai Central (400008).
How many flats are in Meher Villa, and how many are sold?
According to GharKundli's check of MahaRERA records (updated October 2026), Meher Villa has 20 homes in 1 tower registered on MahaRERA, and 91% of them are sold or booked.
When was Meher Villa registered on MahaRERA?
According to GharKundli's check of MahaRERA records (updated October 2026), Meher Villa was registered on MahaRERA on 21 May 2018. GharKundli did not find a title report on the land on file there.
Does Meher Villa have any legal issues or court cases?
No court cases are listed for Meher Villa on MahaRERA, per GharKundli's check of MahaRERA records (updated October 2026).
Who is the builder / developer of Meher Villa?
According to GharKundli's check of MahaRERA records (updated October 2026), the builder is LIVING STONE CONSTRUCTION PRIVATE LIMITED, the company Livstone files this project under.
Check it yourself on MahaRERA
- How to check the possession date of Meher Villa
- How to find and verify a MahaRERA number
- How to check construction status on MahaRERA
- Occupancy certificate (OC): what to check before possession
- Possession delayed? Work out the interest the builder owes
- How to file a MahaRERA complaint against a builder
- Where MahaRERA complaints are: the data
- Why builders ask MahaRERA for more time: the data
All projects with possession due in 2026 in Mumbai City →
Other projects in Mumbai Central (400008)
All 75 projects in Mumbai Central (400008) →Data compiled by GharKundli (gharkundli.com) from MahaRERA public records, as of October 2026. Check the project’s MahaRERA page for the latest filings. Not legal advice.