by M/s Orbit Developers · Bandra West, MumbaiAlso near Bandra East, Khar Delivery

Possession date of The Waterfront: 31 August 2026, moved from 31 August 2025 (8 months later). This is the latest completion date the builder has filed on MahaRERA, and it has already passed. How to check it yourself

Registered on MahaRERA under P51800050617. Status: Lapsed (registration period ended). Its completion date has moved from August 2025 to August 2026: 8 months at the builder's request, plus MahaRERA's automatic 4-month extension for all eligible projects. 1 complaint is listed against it on MahaRERA.

Source: GharKundli’s check of MahaRERA records, October 2026.

The latest completion date on MahaRERA (August 2026) has passed.

What do you want to know about The Waterfront?

Ask us on WhatsAppNo login needed. A real person replies.

How the possession date of The Waterfront has moved

  1. 31 August 2025

    Completion date given when the project was registered

  2. 30 April 2026

    Extended at the builder's request (MahaRERA application EXT51800027778)

    Reason the builder gave MahaRERA:
    “With reference to the said subject matter, I/We hereby inform yourselves that the Approvals for the sald project from B.M.C. and further C. C. got delayed. We had to take revised concessions for 20 floors for which the file needed the appro…” Read the full reason“With reference to the said subject matter, I/We hereby inform yourselves that the Approvals for the sald project from B.M.C. and further C. C. got delayed. We had to take revised concessions for 20 floors for which the file needed the approval of Hon. Municipal Commissioner sir, as anticipated the process of 45 days took more than 5 months to get concessions approved and further CC. Post concession approval from Hon. Municipal Commissioner sir, to get amended IOD and FCC also took further time. Hence there was no slab casted from July 2024 to Feb 2025. The RCC construction was delayed and h…”
  3. 31 August 2026

    MahaRERA's automatic 4-month extension for all eligible projects, not the builder's request

Source: The Waterfront’s extension records on MahaRERA (P51800050617), read by GharKundli in October 2026. The builder’s reasons are quoted as filed. Your own possession date is the one in your agreement for sale.

What builders tell MahaRERA when they’re late: 14,973 applications analysed →

GharKundli’s full report on The Waterfront

Read from every filing on MahaRERA when you open it

  • Risk & trust score, every point explained
  • What the title report says about the land
  • Each of the 1 complaint and 1 court case, and how it ended
  • Construction pace against the August 2026 deadline
  • Agreement clauses weaker than the RERA model
  • Escrow audit, loans and the builder's record
  • Questions to get answered in writing before you pay
MahaRERA registration
P51800050617
Status
Lapsed (registration period ended)
Builder
M/s Orbit Developers
Location
Bandra West, Mumbai · 400050
Project type
Commercial
Registered on
21 Apr 2023
Completion date at registration
August 2025
Latest completion date
August 2026
Delay so far
8 months
MahaRERA's automatic extension
+4 months (force majeure, all eligible projects)
Homes
0
Sold or booked
72%
Towers
1
Complaints on MahaRERA
1
Court cases listed
1
Title report on file
Not found

Construction progress of The Waterfront, as filed by the builder

What the builder has reported to MahaRERA, as GharKundli read it in October 2026. GharKundli’s full report compares it with the deadline.

Tower / wingPlinthSlabs (structure)Internal workLifts, fire & electrical
The Waterfront100%100%100%70%

Commencement certificate (CC), as filed on MahaRERA

  • The Waterfront: covers GROUND + 7TH FLOOR

Latest CC order on MahaRERA: dated 24/01/2025.

Want to know when this changes? Kundli Watch sends a free WhatsApp update on The Waterfront every month.

The Waterfront: buildings, flats and land, as filed on MahaRERA

TypeCarpet area (sq ft)Units
Office Space192 – 10,452133
Shops82 – 5,7553
  • Buildings: The Waterfront (7 floors, 136 units)
  • Car parking: 202 covered
  • Land: 1,901 sq m (about 0.5 acres) · sanctioned built-up 5,683 sq m

The builder’s record and reviews

Not enough of this builder’s other MahaRERA projects have reached their promised date to judge yet.

Read Google reviews of The Waterfront →Reviews on Google are opinions by Google users; GharKundli doesn’t check them.

Kundli Watch

The Waterfront: buyers & owners

Free: a WhatsApp update every month on this project, and straight away when anything changes on MahaRERA — a later completion date, new complaints, a red flag. Your number stays private: never shown to other members or the builder.

Be the first to watch this project.

How are you connected to this project?

Bought here? No document needed now. From the builder’s team? Join to answer buyers’ questions; you never see members’ details. You’ll sign in with a one-time code, then come straight back here.

Common questions about The Waterfront

What is the possession date of The Waterfront?

According to GharKundli's check of MahaRERA records (updated October 2026), the latest completion date filed on MahaRERA for The Waterfront in Bandra West, Mumbai is 31 August 2026 — 8 months later than 31 August 2025, the date given at registration, plus MahaRERA's automatic 4-month extension for all eligible projects. That date has already passed.

Is the builder's possession date different from the MahaRERA date for The Waterfront?

Builders and listing sites often quote an earlier "target" date for handover. The completion date The Waterfront's builder has filed on MahaRERA, the official one, is 31 August 2026, already 8 months later than the 31 August 2025 given at registration, per GharKundli's check of MahaRERA records. If possession is late, what counts under RERA (Section 18) is the possession date written in your agreement for sale.

Why was the possession date of The Waterfront extended?

According to GharKundli's check of MahaRERA records (updated October 2026), The Waterfront's builder applied to MahaRERA to extend the completion date once: to 30 April 2026, giving the reason "With reference to the said subject matter, I/We hereby inform yourselves that the Approvals for the sald project from B.M.C. and further C. C. got delayed. We had to take revised concessions for 20 floors for which the file needed the approval of Hon. Municipal Commissioner sir, as anticipated the process of 45 days took more than 5 months to get concessions approved and further CC. Post concession approval from Hon. Municipal Commissioner sir, to get amended IOD and FCC also took further time. Hence there was no slab casted from July 2024 to Feb 2025. The RCC construction was delayed and h…". MahaRERA also added its automatic 4-month extension for all eligible projects.

What is the RERA number of The Waterfront?

According to GharKundli's check of MahaRERA records (updated October 2026), the MahaRERA registration number of The Waterfront in Bandra West, Mumbai is P51800050617.

Is The Waterfront registered with MahaRERA?

According to GharKundli's check of MahaRERA records (updated October 2026), The Waterfront is registered as P51800050617 and its status is "Lapsed (registration period ended)".

What is the construction status of The Waterfront?

According to GharKundli's check of MahaRERA records (updated October 2026), The Waterfront's status on MahaRERA is "Lapsed (registration period ended)". As filed by the builder, slab work on The Waterfront is 100% done and internal work 100%. GharKundli's full report compares construction progress with the deadline.

Does The Waterfront have complaints on MahaRERA?

1 complaint was listed on MahaRERA as of October 2026, per GharKundli's weekly check. GharKundli's full report explains each case and how it ended.

Is The Waterfront safe to buy?

According to GharKundli's check of MahaRERA records (updated October 2026), The Waterfront is registered on MahaRERA as P51800050617, its MahaRERA status is "Lapsed (registration period ended)", its completion date has moved 8 months since registration and 1 complaint is listed against it. GharKundli doesn't call a project safe or unsafe from these numbers alone: its full report gives a risk & trust score with every point explained.

How can I get updates if The Waterfront's possession date changes?

The latest dates are on The Waterfront's MahaRERA page (P51800050617). GharKundli's Kundli Watch sends a free WhatsApp update on The Waterfront every month, and straight away when anything changes on MahaRERA: a later completion date, new complaints or a red flag. Your number is never shown to the builder.

How many floors does The Waterfront have?

According to GharKundli's check of MahaRERA records (updated October 2026), The Waterfront has one building filed: The Waterfront with 7 floors and 136 units.

How much parking does The Waterfront have?

According to GharKundli's check of MahaRERA records (updated October 2026), the builder has filed 202 covered car parking spaces for The Waterfront.

How big is the land of The Waterfront?

According to GharKundli's check of MahaRERA records (updated October 2026), The Waterfront stands on 1,901 sq m of land (about 0.5 acres), with 5,683 sq m of sanctioned built-up area.

Where can I read reviews of The Waterfront?

Google Maps has reviews of The Waterfront written by Google users; GharKundli links to them on this page but doesn't check them. For facts rather than opinions: 1 complaint is listed on MahaRERA, and Kundli Watch shows verified owners of the project.

Where is The Waterfront?

The Waterfront by M/s Orbit Developers is in Bandra West, Mumbai (pincode 400050), near Bandra East, Khar Delivery, Maharashtra, and is registered on MahaRERA as P51800050617, per GharKundli's check of MahaRERA records.

How many homes are in The Waterfront?

According to GharKundli's check of MahaRERA records (updated October 2026), The Waterfront has 0 homes in 1 tower registered on MahaRERA, and 72% of them are sold or booked.

When was The Waterfront registered on MahaRERA?

According to GharKundli's check of MahaRERA records (updated October 2026), The Waterfront was registered on MahaRERA on 21 April 2023. GharKundli did not find a title report on the land on file there.

Are there court cases on The Waterfront?

1 court case is listed for The Waterfront on MahaRERA, per GharKundli's check of MahaRERA records (updated October 2026). GharKundli's full report explains each case and how it ended.

Who is the builder of The Waterfront?

According to GharKundli's check of MahaRERA records (updated October 2026), the builder is M/s Orbit Developers.

All projects with possession due in 2026 in Mumbai Suburban →

Other projects in pincode 400050

All 168 projects in Bandra West (400050) →

Data compiled by GharKundli (gharkundli.com) from MahaRERA public records, as of October 2026. Check the project’s MahaRERA page for the latest filings. Not legal advice.