What’s in the report? →Possession date of Kashi Bhuvan (MahaRERA P51800049342): 30 September 2025, moved from 31 December 2024 (9 months later), and it has already passed. It has 21 homes. No complaints on MahaRERA. How to check it yourself
Registered on MahaRERA under P51800049342. Status: Lapsed (registration period ended).
Source: MahaRERA website — records for P51800049342, read and compiled by GharKundli. Facts as filed on MahaRERA, no opinions.
The latest completion date on MahaRERA (September 2025) has passed.
What do you want to know about Kashi Bhuvan?
Completion date nikal chuki hai. Kya poochna hai?Tap a question. We’ll answer you on WhatsApp, free.
How the possession date of Kashi Bhuvan has moved
31 December 2024
Completion date given when the project was registered
30 September 2025
Extended at the builder's request (MahaRERA application EXT51800027790)
Reason the builder gave MahaRERA: “Reasons are specified in detailed explanation letter attached.”
Source: Kashi Bhuvan’s extension records on MahaRERA (P51800049342), read by GharKundli in October 2026. The builder’s reasons are quoted as filed. Your own possession date is the one in your agreement for sale.
What builders tell MahaRERA when they’re late: 14,973 applications analysed →GharKundli’s full report on Kashi Bhuvan
Read from every filing on MahaRERA when you open it
- Risk & trust score, every point explained
- What the title report says about the land
- Each complaint and court case, and how it ended
- Construction pace against the September 2025 deadline
- Agreement clauses weaker than the RERA model
- Escrow audit, loans and the builder's record
- Questions to get answered in writing before you pay
- MahaRERA registration
- P51800049342
- Status
- Lapsed (registration period ended)
- Builder
- BHARAT V KENNY
- Location
- Dahanukar Wadi, Mumbai · 400067
- Project type
- Residential / Group Housing
- Registered on
- 7 Feb 2023
- Completion date at registration
- December 2024
- Latest completion date
- September 2025
- Delay so far
- 9 months
- Homes
- 21
- Towers
- 1
- Complaints on MahaRERA
- 0
- Court cases listed
- 0
- Title report on file
- Not found
Construction progress of Kashi Bhuvan, as filed by the builder
What the builder has reported to MahaRERA, as GharKundli read it in October 2026. GharKundli’s full report compares it with the deadline.
| Tower / wing | Plinth | Slabs (structure) | Internal work | Lifts, fire & electrical |
|---|---|---|---|---|
| KASHI BHUVAN | 100% | 10% | 40% | 0% |
Want to know when this changes? Kundli Watch sends a free WhatsApp update on Kashi Bhuvan every 1–2 months.
Kashi Bhuvan: buildings, flats and land, as filed on MahaRERA
- Buildings: KASHI BHUVAN (9 floors)
- Land: 487 sq m (about 0.1 acres) · sanctioned built-up 713 sq m
- Boundaries filed include: ROAD DAMU ANNA DATE MARG, SAMEER CHANDAVARKAR ROAD
- Land, as filed: 1011/A
- Map: the location the builder filed on MahaRERA · Get directions
The builder’s record and reviews
Not enough of this builder’s other MahaRERA projects have reached their promised date to judge yet.
Read Google reviews of Kashi Bhuvan →Reviews on Google are opinions by Google users; GharKundli doesn’t check them.
Kundli Watch
Kashi Bhuvan: buyers & owners
Free: a construction progress update on WhatsApp every 1–2 months, and straight away when anything changes on MahaRERA — a later completion date, new complaints, a red flag. Your number stays private: never shown to other members or the builder.
Be the first to watch this project.
How are you connected to this project?
Watching needs only WhatsApp or your number. Bought here? No document needed now. From the builder’s team? Join to answer buyers’ questions; you never see members’ details. Owners and the builder’s team sign in with a one-time code, then come straight back here.
Common questions about Kashi Bhuvan
What is the possession date of Kashi Bhuvan?
According to GharKundli's check of MahaRERA records (updated October 2026), the latest completion date filed on MahaRERA for Kashi Bhuvan in Dahanukar Wadi, Mumbai is 30 September 2025 — 9 months later than 31 December 2024, the date given at registration. That date has already passed.
The date has already moved 9 months. Will it move again? Check the real pace of construction →
Is the builder's possession date different from the MahaRERA date for Kashi Bhuvan?
Builders and listing sites often quote an earlier "target" date for handover. The completion date Kashi Bhuvan's builder has filed on MahaRERA, the official one, is 30 September 2025, already 9 months later than the 31 December 2024 given at registration, per GharKundli's check of MahaRERA records. If possession is late, what counts under RERA (Section 18) is the possession date written in your agreement for sale.
Why was the possession date of Kashi Bhuvan extended?
According to GharKundli's check of MahaRERA records (updated October 2026), Kashi Bhuvan's builder applied to MahaRERA to extend the completion date once: to 30 September 2025, giving the reason "Reasons are specified in detailed explanation letter attached.".
What is the RERA number of Kashi Bhuvan?
According to GharKundli's check of MahaRERA records (updated October 2026), the MahaRERA registration number of Kashi Bhuvan in Dahanukar Wadi, Mumbai is P51800049342.
Is Kashi Bhuvan registered with MahaRERA?
According to GharKundli's check of MahaRERA records (updated October 2026), Kashi Bhuvan is registered as P51800049342 and its status is "Lapsed (registration period ended)".
What is the current construction status of Kashi Bhuvan? How much work is done?
According to GharKundli's check of MahaRERA records (updated October 2026), Kashi Bhuvan's status on MahaRERA is "Lapsed (registration period ended)". As filed by the builder, slab work on KASHI BHUVAN is 10% done and internal work 40%. GharKundli's full report compares construction progress with the deadline.
Does Kashi Bhuvan have complaints on MahaRERA?
No complaints were listed on MahaRERA as of October 2026, per GharKundli's weekly check.
Is Kashi Bhuvan safe to buy?
According to GharKundli's check of MahaRERA records (updated October 2026), Kashi Bhuvan is registered on MahaRERA as P51800049342, its MahaRERA status is "Lapsed (registration period ended)", its completion date has moved 9 months since registration and no complaints are listed against it. GharKundli doesn't call a project safe or unsafe from these numbers alone: its full report gives a risk & trust score with every point explained.
How much GST is payable on a flat in Kashi Bhuvan?
Kashi Bhuvan isn't marked completed on MahaRERA, so until the occupancy certificate is issued GST applies to a new flat: 5% of the price, with no input tax credit. The lower 1% rate is only for "affordable" homes: carpet area up to 60 sq m (about 646 sq ft) in the Mumbai region, and price up to ₹45 lakh. There is no GST on stamp duty or registration, and none once the occupancy certificate is issued.
What is the stamp duty and registration cost for a flat in Kashi Bhuvan?
For a flat in Kashi Bhuvan (Mumbai), stamp duty is 6% of the agreement value, or of the ready reckoner value if that's higher, including 1% Metro Cess. A woman buying in her own name pays 5%. Registration is 1% of the value, capped at ₹30,000. On a ₹1 crore flat that's about ₹6 lakh in stamp duty plus ₹30,000 registration. GharKundli's property cost calculator works it out for your price: gharkundli.com/tools/property-cost-calculator
Has Kashi Bhuvan received its OC? Is it ready to move in?
Not yet. According to GharKundli's check of MahaRERA records (updated October 2026), Kashi Bhuvan isn't completed: its MahaRERA status is "Lapsed (registration period ended)", with 30 September 2025 as the latest completion date filed on MahaRERA, and that date has passed. A flat is ready to move in only once the occupancy certificate (OC) is issued, after construction is complete.
What does "lapsed" mean for Kashi Bhuvan?
According to GharKundli's check of MahaRERA records (updated October 2026), Kashi Bhuvan's registration shows as lapsed on MahaRERA. Lapsed means the completion date on MahaRERA (30 September 2025) passed without the project being marked complete or the registration being extended. Before paying anything, ask the builder in writing whether an extension has been applied for.
Is Kashi Bhuvan a redevelopment or SRA project?
According to GharKundli's check of MahaRERA records (updated October 2026), Kashi Bhuvan's planning authority on MahaRERA is MCGM, not the Slum Rehabilitation Authority, so it isn't an SRA scheme.
Has Kashi Bhuvan uploaded its title report on MahaRERA?
According to GharKundli's check of MahaRERA records (updated October 2026), no title report for Kashi Bhuvan was found on MahaRERA. Builders are expected to upload one; before booking, ask the builder for the advocate's title certificate in writing.
No title report is on MahaRERA for this project. See which documents are missing →
How can I get updates if Kashi Bhuvan's possession date changes?
The latest dates are on Kashi Bhuvan's MahaRERA page (P51800049342). GharKundli's Kundli Watch sends a free WhatsApp update on Kashi Bhuvan every 1–2 months, and straight away when anything changes on MahaRERA: a later completion date, new complaints or a red flag. Your number is never shown to the builder.
How many floors does Kashi Bhuvan have?
According to GharKundli's check of MahaRERA records (updated October 2026), Kashi Bhuvan has one building filed: KASHI BHUVAN with 9 floors.
How big is the land of Kashi Bhuvan?
According to GharKundli's check of MahaRERA records (updated October 2026), Kashi Bhuvan stands on 487 sq m of land (about 0.1 acres), with 713 sq m of sanctioned built-up area.
What are the reviews of Kashi Bhuvan?
Google Maps has reviews of Kashi Bhuvan written by Google users; GharKundli links to them on this page but doesn't check them. For facts rather than opinions: no complaints are listed on MahaRERA, and Kundli Watch shows verified owners of the project.
What is the address and pincode of Kashi Bhuvan?
Kashi Bhuvan by BHARAT V KENNY is in Dahanukar Wadi, Mumbai, pincode 400067 (near Borivali West, Borivali East, Daulat Nagar), Maharashtra, and is registered on MahaRERA as P51800049342, per GharKundli's check of MahaRERA records. Its boundaries filed there include ROAD DAMU ANNA DATE MARG, SAMEER CHANDAVARKAR ROAD. Its land is filed as 1011/A. GharKundli lists all 318 MahaRERA projects in Kandivali West (400067).
How many flats are in Kashi Bhuvan?
According to GharKundli's check of MahaRERA records (updated October 2026), Kashi Bhuvan has 21 homes in 1 tower registered on MahaRERA.
When was Kashi Bhuvan registered on MahaRERA?
According to GharKundli's check of MahaRERA records (updated October 2026), Kashi Bhuvan was registered on MahaRERA on 7 February 2023. GharKundli did not find a title report on the land on file there.
Does Kashi Bhuvan have any legal issues or court cases?
No court cases are listed for Kashi Bhuvan on MahaRERA, per GharKundli's check of MahaRERA records (updated October 2026).
Who is the builder / developer of Kashi Bhuvan?
According to GharKundli's check of MahaRERA records (updated October 2026), the builder is BHARAT V KENNY.
Check it yourself on MahaRERA
- How to check the possession date of Kashi Bhuvan
- How to find and verify a MahaRERA number
- How to check construction status on MahaRERA
- Occupancy certificate (OC): what to check before possession
- Possession delayed? Work out the interest the builder owes
- How to file a MahaRERA complaint against a builder
- Where MahaRERA complaints are: the data
- Why builders ask MahaRERA for more time: the data
Other projects in Borivali
- Kandivali Satyam Apartment CHS LTD
- Shiv Sham Niketan
- Saffronwoods CHSL
- Parshuram Heights
- L&T Realty Ahana Tower A
- L&T Realty Ahana Tower B
- Avirahi Elegance
- Rashmi Icon
Data compiled by GharKundli (gharkundli.com) from MahaRERA public records, as of October 2026. Check the project’s MahaRERA page for the latest filings. Not legal advice.