Trocadero Seventy Seven
by TROCADERO ASSOCIATES · Bandra West, Mumbai 400050Also near Khar Delivery, Bandra EastRegistered on MahaRERA as “SEVENTY SEVEN”
What’s in the report? →Possession date of Trocadero Seventy Seven (MahaRERA P51800049193): 31 July 2027, moved from 31 December 2024 (27 months later). It has 16 homes (1 BHK, 1 Room Kitchen and 2 BHK, 386–2908 sq ft carpet), 0% sold or booked. No complaints on MahaRERA. How to check it yourself
Registered on MahaRERA under P51800049193, and currently active. Its completion date has moved from December 2024 to July 2027: 27 months at the builder's request, plus MahaRERA's automatic 4-month extension for all eligible projects.
Source: MahaRERA website — records for P51800049193, read and compiled by GharKundli. Facts as filed on MahaRERA, no opinions.
What do you want to know about Trocadero Seventy Seven?
Title report MahaRERA par nahi dikh rahi. Kya poochna hai?Tap a question. We’ll answer you on WhatsApp, free.
How the possession date of Trocadero Seventy Seven has moved
31 December 2024
Completion date given when the project was registered
31 March 2026
Extended at the builder's request (MahaRERA application EXT51800027306)
Reason the builder gave MahaRERA:
“In reference to the said project, we wish to state that due to change in policy of the government we had the opportunity of enhancing our Plot potential by 354 sq. meters plus fungible FSI thereon. This was due to a new policy being 33(20)(…” Read the full reason
“In reference to the said project, we wish to state that due to change in policy of the government we had the opportunity of enhancing our Plot potential by 354 sq. meters plus fungible FSI thereon. This was due to a new policy being 33(20)(b) which has been pending for long. However, after an unprecedented wait the policy was finally released by the government on 15/10/2024 (copy of the policy attached herewith for your ready reference). Although the policy is released SOP (Standard Operating Procedure) is awaited which will tell us which form of FSI is to be loaded. SOP have been delayed d…”31 March 2027
Extended at the builder's request (MahaRERA application EA16032620237)
Reason the builder gave MahaRERA:
“SUBJECT: EXPLANATION FOR DELAY IN PROJECT AND REQUEST FOR EXTENSION OF THE PROJECT REF:- Project name Seventy Seven located at CTS F/980 of Village F Ward F.P. No. 23m of TPS Bandra No. IV at Bandra (West), Mumbai-400050 Bearing Rera No.P51…” Read the full reason
“SUBJECT: EXPLANATION FOR DELAY IN PROJECT AND REQUEST FOR EXTENSION OF THE PROJECT REF:- Project name Seventy Seven located at CTS F/980 of Village F Ward F.P. No. 23m of TPS Bandra No. IV at Bandra (West), Mumbai-400050 Bearing Rera No.P51800049193. Dear Sir, In reference to the said project, we wish to state that due to change in policy of the government we had the opportunity of enhancing our Plot potential by 354 sq. meters plus fungible FSI thereon. Accordingly, we have already acquired PTC to be handed over to the Corporation and accordingly further CC has been granted. Occupation Cer…”31 July 2027
MahaRERA's automatic 4-month extension for all eligible projects, not the builder's request
Source: Trocadero Seventy Seven’s extension records on MahaRERA (P51800049193), read by GharKundli in October 2026. The builder’s reasons are quoted as filed. Your own possession date is the one in your agreement for sale.
What builders tell MahaRERA when they’re late: 14,973 applications analysed →GharKundli’s full report on Trocadero Seventy Seven
Read from every filing on MahaRERA when you open it
- Risk & trust score, every point explained
- What the title report says about the land
- Each complaint and court case, and how it ended
- Construction pace against the July 2027 deadline
- Agreement clauses weaker than the RERA model
- Escrow audit, loans and the builder's record
- Questions to get answered in writing before you pay
- MahaRERA registration
- P51800049193
- Status
- Registered and active
- Builder
- TROCADERO ASSOCIATES
- Location
- Bandra West, Mumbai · 400050
- Project type
- Others
- Registered on
- 3 Feb 2023
- Completion date at registration
- December 2024
- Latest completion date
- July 2027
- Delay so far
- 27 months
- MahaRERA's automatic extension
- +4 months (force majeure, all eligible projects)
- Homes
- 16
- Sold or booked
- 0%
- Towers
- 1
- Complaints on MahaRERA
- 0
- Court cases listed
- 0
- Title report on file
- Not found
Construction progress of Trocadero Seventy Seven, as filed by the builder
What the builder has reported to MahaRERA, as GharKundli read it in October 2026. GharKundli’s full report compares it with the deadline.
| Tower / wing | Plinth | Slabs (structure) | Internal work | Lifts, fire & electrical |
|---|---|---|---|---|
| SEVENTY SEVEN | 100% | 92% | 55% | 4% |
Commencement certificate (CC), as filed on MahaRERA
- SEVENTY SEVEN: covers C.C. and FCC for up to top of 18th (part) upper floor
Latest CC order on MahaRERA: dated 28/08/2025.
Want to know when this changes? Kundli Watch sends a free WhatsApp update on Trocadero Seventy Seven every 1–2 months.
Trocadero Seventy Seven: buildings, flats and land, as filed on MahaRERA
| Type | Carpet area (sq ft) | Units |
|---|---|---|
| 4 BHK | 1,903 – 2,908 | 8 |
| 1 BHK | 386 – 468 | 4 |
| 3 BHK | 1,555 – 1,903 | 2 |
| Shops | 2,059 | 1 |
| 2 BHK | 632 | 1 |
| 1 Room Kitchen | 756 | 1 |
- Buildings: SEVENTY SEVEN (20 floors, 17 units)
- Car parking: 42 covered
- Land: 681 sq m (about 0.2 acres) · sanctioned built-up 2,602 sq m
- Boundaries filed include: CROSS ROAD
- Land, as filed: F/980
- Map: Get directions
The builder’s record and reviews
Not enough of this builder’s other MahaRERA projects have reached their promised date to judge yet.
Read Google reviews of Trocadero Seventy Seven →Reviews on Google are opinions by Google users; GharKundli doesn’t check them.
Kundli Watch
Trocadero Seventy Seven: buyers & owners
Free: a construction progress update on WhatsApp every 1–2 months, and straight away when anything changes on MahaRERA — a later completion date, new complaints, a red flag. Your number stays private: never shown to other members or the builder.
Be the first to watch this project.
How are you connected to this project?
Watching needs only WhatsApp or your number. Bought here? No document needed now. From the builder’s team? Join to answer buyers’ questions; you never see members’ details. Owners and the builder’s team sign in with a one-time code, then come straight back here.
Common questions about Trocadero Seventy Seven
What is the possession date of Trocadero Seventy Seven?
According to GharKundli's check of MahaRERA records (updated October 2026), the latest completion date filed on MahaRERA for Trocadero Seventy Seven in Bandra West, Mumbai is 31 July 2027 — 27 months later than 31 December 2024, the date given at registration, plus MahaRERA's automatic 4-month extension for all eligible projects.
The date has already moved 27 months. Will it move again? Check the real pace of construction →
Is the builder's possession date different from the MahaRERA date for Trocadero Seventy Seven?
Builders and listing sites often quote an earlier "target" date for handover. The completion date Trocadero Seventy Seven's builder has filed on MahaRERA, the official one, is 31 July 2027, already 27 months later than the 31 December 2024 given at registration, per GharKundli's check of MahaRERA records. If possession is late, what counts under RERA (Section 18) is the possession date written in your agreement for sale.
Why was the possession date of Trocadero Seventy Seven extended?
According to GharKundli's check of MahaRERA records (updated October 2026), Trocadero Seventy Seven's builder applied to MahaRERA to extend the completion date 2 times: to 31 March 2026, giving the reason "In reference to the said project, we wish to state that due to change in policy of the government we had the opportunity of enhancing our Plot potential by 354 sq. meters plus fungible FSI thereon. This was due to a new policy being 33(20)(b) which has been pending for long. However, after an unprecedented wait the policy was finally released by the government on 15/10/2024 (copy of the policy attached herewith for your ready reference). Although the policy is released SOP (Standard Operating Procedure) is awaited which will tell us which form of FSI is to be loaded. SOP have been delayed d…"; to 31 March 2027, giving the reason "SUBJECT: EXPLANATION FOR DELAY IN PROJECT AND REQUEST FOR EXTENSION OF THE PROJECT REF:- Project name Seventy Seven located at CTS F/980 of Village F Ward F.P. No. 23m of TPS Bandra No. IV at Bandra (West), Mumbai-400050 Bearing Rera No.P51800049193. Dear Sir, In reference to the said project, we wish to state that due to change in policy of the government we had the opportunity of enhancing our Plot potential by 354 sq. meters plus fungible FSI thereon. Accordingly, we have already acquired PTC to be handed over to the Corporation and accordingly further CC has been granted. Occupation Cer…". MahaRERA also added its automatic 4-month extension for all eligible projects.
What is the RERA number of Trocadero Seventy Seven?
According to GharKundli's check of MahaRERA records (updated October 2026), the MahaRERA registration number of Trocadero Seventy Seven in Bandra West, Mumbai is P51800049193.
Is Trocadero Seventy Seven registered with MahaRERA?
According to GharKundli's check of MahaRERA records (updated October 2026), Trocadero Seventy Seven is registered as P51800049193 and its status is "Registered and active".
What is the current construction status of Trocadero Seventy Seven? How much work is done?
According to GharKundli's check of MahaRERA records (updated October 2026), Trocadero Seventy Seven's status on MahaRERA is "Registered and active". As filed by the builder, slab work on SEVENTY SEVEN is 92% done and internal work 55%. GharKundli's full report compares construction progress with the deadline.
Does Trocadero Seventy Seven have complaints on MahaRERA?
No complaints were listed on MahaRERA as of October 2026, per GharKundli's weekly check.
Is Trocadero Seventy Seven safe to buy?
According to GharKundli's check of MahaRERA records (updated October 2026), Trocadero Seventy Seven is registered on MahaRERA as P51800049193, its completion date has moved 27 months since registration and no complaints are listed against it. GharKundli doesn't call a project safe or unsafe from these numbers alone: its full report gives a risk & trust score with every point explained.
How much GST is payable on a flat in Trocadero Seventy Seven?
Trocadero Seventy Seven is under construction, so GST applies to a new flat: 5% of the price, with no input tax credit. The lower 1% rate is only for "affordable" homes: carpet area up to 60 sq m (about 646 sq ft) in the Mumbai region, and price up to ₹45 lakh. Some flats in Trocadero Seventy Seven are 386 sq ft carpet, small enough for 1% if the price is ₹45 lakh or less. There is no GST on stamp duty or registration, and none once the occupancy certificate is issued.
What is the stamp duty and registration cost for a flat in Trocadero Seventy Seven?
For a flat in Trocadero Seventy Seven (Mumbai), stamp duty is 6% of the agreement value, or of the ready reckoner value if that's higher, including 1% Metro Cess. A woman buying in her own name pays 5%. Registration is 1% of the value, capped at ₹30,000. On a ₹1 crore flat that's about ₹6 lakh in stamp duty plus ₹30,000 registration. GharKundli's property cost calculator works it out for your price: gharkundli.com/tools/property-cost-calculator
Has Trocadero Seventy Seven received its OC? Is it ready to move in?
Not yet. According to GharKundli's check of MahaRERA records (updated October 2026), Trocadero Seventy Seven is still under construction, with 31 July 2027 as the latest completion date filed on MahaRERA. A flat is ready to move in only once the occupancy certificate (OC) is issued, after construction is complete.
Is Trocadero Seventy Seven a redevelopment or SRA project?
According to GharKundli's check of MahaRERA records (updated October 2026), Trocadero Seventy Seven's planning authority on MahaRERA is MCGM, not the Slum Rehabilitation Authority, so it isn't an SRA scheme, and no flats are filed as rehab flats for existing occupants.
Has Trocadero Seventy Seven uploaded its title report on MahaRERA?
According to GharKundli's check of MahaRERA records (updated October 2026), no title report for Trocadero Seventy Seven was found on MahaRERA. Builders are expected to upload one; before booking, ask the builder for the advocate's title certificate in writing.
No title report is on MahaRERA for this project. See which documents are missing →
How can I get updates if Trocadero Seventy Seven's possession date changes?
The latest dates are on Trocadero Seventy Seven's MahaRERA page (P51800049193). GharKundli's Kundli Watch sends a free WhatsApp update on Trocadero Seventy Seven every 1–2 months, and straight away when anything changes on MahaRERA: a later completion date, new complaints or a red flag. Your number is never shown to the builder.
How many floors does Trocadero Seventy Seven have?
According to GharKundli's check of MahaRERA records (updated October 2026), Trocadero Seventy Seven has one building filed: SEVENTY SEVEN with 20 floors and 17 units.
What are the flat sizes (carpet area) in Trocadero Seventy Seven?
According to GharKundli's check of MahaRERA records (updated October 2026), the builder has filed these homes for Trocadero Seventy Seven: 4 BHK: 1903 to 2908 sq ft carpet (8 homes); 1 BHK: 386 to 468 sq ft carpet (4 homes); 3 BHK: 1555 to 1903 sq ft carpet (2 homes); 2 BHK: 632 sq ft carpet (1 homes); 1 Room Kitchen: 756 sq ft carpet (1 homes). Carpet area is the usable floor area inside the walls, as defined under RERA.
How much parking does Trocadero Seventy Seven have?
According to GharKundli's check of MahaRERA records (updated October 2026), the builder has filed 42 covered car parking spaces for Trocadero Seventy Seven.
How big is the land of Trocadero Seventy Seven?
According to GharKundli's check of MahaRERA records (updated October 2026), Trocadero Seventy Seven stands on 681 sq m of land (about 0.2 acres), with 2,602 sq m of sanctioned built-up area.
What are the reviews of Trocadero Seventy Seven?
Google Maps has reviews of Trocadero Seventy Seven written by Google users; GharKundli links to them on this page but doesn't check them. For facts rather than opinions: no complaints are listed on MahaRERA, and Kundli Watch shows verified owners of the project.
What is the address and pincode of Trocadero Seventy Seven?
Trocadero Seventy Seven by TROCADERO ASSOCIATES is in Bandra West, Mumbai, pincode 400050 (near Khar Delivery, Bandra East), Maharashtra, and is registered on MahaRERA as P51800049193, per GharKundli's check of MahaRERA records. Its boundaries filed there include CROSS ROAD. Its land is filed as F/980. GharKundli lists all 168 MahaRERA projects in Bandra West (400050).
How many flats are in Trocadero Seventy Seven, and how many are sold?
According to GharKundli's check of MahaRERA records (updated October 2026), Trocadero Seventy Seven has 16 homes in 1 tower registered on MahaRERA, and 0% of them are sold or booked.
When was Trocadero Seventy Seven registered on MahaRERA?
According to GharKundli's check of MahaRERA records (updated October 2026), Trocadero Seventy Seven was registered on MahaRERA on 3 February 2023. GharKundli did not find a title report on the land on file there.
Does Trocadero Seventy Seven have any legal issues or court cases?
No court cases are listed for Trocadero Seventy Seven on MahaRERA, per GharKundli's check of MahaRERA records (updated October 2026).
Who is the builder / developer of Trocadero Seventy Seven?
According to GharKundli's check of MahaRERA records (updated October 2026), the builder is TROCADERO ASSOCIATES.
Check it yourself on MahaRERA
- How to check the possession date of Trocadero Seventy Seven
- How to find and verify a MahaRERA number
- How to check construction status on MahaRERA
- Occupancy certificate (OC): what to check before possession
- Possession delayed? Work out the interest the builder owes
- How to file a MahaRERA complaint against a builder
- Where MahaRERA complaints are: the data
- Why builders ask MahaRERA for more time: the data
All projects with possession due in 2027 in Mumbai Suburban →
Other projects in Bandra West (400050)
- Manthan Embassy
- The Marque
- Therese
- Tonino Lamborghini Residences Mumbai
- Godrej Bandra Bay Phase 2
- Godrej Bandra Bay Phase 3
- KK 415 West
- Verdant
Data compiled by GharKundli (gharkundli.com) from MahaRERA public records, as of October 2026. Check the project’s MahaRERA page for the latest filings. Not legal advice.