SHIVSOLITAIRE
by SO LUCKY BUILDERS · Jogeshwari, MumbaiAlso near Andheri East, Jvlr, Andheri West
Possession: SHIVSOLITAIRE is marked completed on MahaRERA. How to check it yourself
Registered on MahaRERA under P51900006722. Status: Completed. 1 complaint is listed against it on MahaRERA.
Source: GharKundli’s check of MahaRERA records, October 2026.
What do you want to know about SHIVSOLITAIRE?
How the possession date of SHIVSOLITAIRE has moved
31 December 2018
Completion date given when the project was registered
31 December 2022
Extended at the builder's request (MahaRERA application EXT51900006196)
Reason the builder gave MahaRERA:
“The said project was registered on 16/08/2017 for completion upto 31st December 2018. This is an SRA (Slum Rehabilitation Authority) project. During the tenure of the project many unexpected hurdles arose which extended the proceedings a bi…” Read the full reason
“The said project was registered on 16/08/2017 for completion upto 31st December 2018. This is an SRA (Slum Rehabilitation Authority) project. During the tenure of the project many unexpected hurdles arose which extended the proceedings a bit. Some of the hurdles causing the extension are: 1. Delay in approvals and permissions from regulators and competent authorities 2. The Project land was affected by reservations, which were removed pursuant to notification of Development Control and Promotion Regulations for Greater Mumbai, 2034 (“DCPR”). There was inordinate delay in notifying DCPR. 3.…”31 December 2024
Extended at the builder's request (MahaRERA application EXT51900016966)
Reason the builder gave MahaRERA:
“Due to uncertain circumstances , the project could not be completed in the given extended time. kindly allow to extend the project completion date further more. Attached Allotees Consent, Affidavit for the Extension of 100 rs, Stamp Paper,…” Read the full reason
“Due to uncertain circumstances , the project could not be completed in the given extended time. kindly allow to extend the project completion date further more. Attached Allotees Consent, Affidavit for the Extension of 100 rs, Stamp Paper, Quality Assurance Certificate and Engineer.s certificate for reference. kindly consider the same and grant extension upto 31/12/2024”31 December 2026
Extended at the builder's request (MahaRERA application EA31032620486)
Reason the builder gave MahaRERA:
“As far as work progress on site is considered, we have completed 100% of our work and have received the Part OC on 07/11/2022 and balance on 19-03-2025. While OC Verification it was observed that there are certain mismatch that has to be re…” Read the full reason
“As far as work progress on site is considered, we have completed 100% of our work and have received the Part OC on 07/11/2022 and balance on 19-03-2025. While OC Verification it was observed that there are certain mismatch that has to be rectified hence we are filing this application”
Source: SHIVSOLITAIRE’s extension records on MahaRERA (P51900006722), read by GharKundli in October 2026. The builder’s reasons are quoted as filed. Your own possession date is the one in your agreement for sale.
What builders tell MahaRERA when they’re late: 14,973 applications analysed →GharKundli’s full report on SHIVSOLITAIRE
Read from every filing on MahaRERA when you open it
- Risk & trust score, every point explained
- What the title report says about the land
- Each of the 1 complaint, and how it ended
- Construction pace against the December 2026 deadline
- Agreement clauses weaker than the RERA model
- Escrow audit, loans and the builder's record
- Questions to get answered in writing before you pay
- MahaRERA registration
- P51900006722
- Status
- Completed
- Builder
- SO LUCKY BUILDERS
- Location
- Jogeshwari, Mumbai · 400060
- Project type
- Commercial
- Registered on
- 16 Aug 2017
- Completion date at registration
- December 2018
- Latest completion date
- December 2026
- Delay so far
- 96 months
- Homes
- 0
- Sold or booked
- 87%
- Towers
- 1
- Complaints on MahaRERA
- 1
- Court cases listed
- 0
- Title report on file
- Not found
Construction progress of SHIVSOLITAIRE, as filed by the builder
What the builder has reported to MahaRERA, as GharKundli read it in October 2026. GharKundli’s full report compares it with the deadline.
| Tower / wing | Plinth | Slabs (structure) | Internal work | Lifts, fire & electrical |
|---|---|---|---|---|
| Wing C & D | 100% | 100% | 100% | 0% |
Commencement certificate (CC), as filed on MahaRERA
- Wing C & D: covers 12 floors
Want to know when this changes? Kundli Watch sends a free WhatsApp update on SHIVSOLITAIRE every month.
SHIVSOLITAIRE: buildings, flats and land, as filed on MahaRERA
| Type | Carpet area (sq ft) | Units |
|---|---|---|
| 1 BHK | 492 – 640 | 176 |
| Shops | 300 – 4,000 | 36 |
- Buildings: Wing C & D (12 floors, 212 units)
- Car parking: 102 covered
- Land: 2,377 sq m (about 0.6 acres) · sanctioned built-up 12,427 sq m · recreational space 540 sq m
- Boundaries filed include: MUNCIPAL MARKET AND EXISTING SLUM
- Map: the location the builder filed on MahaRERA
The builder’s record and reviews
SO Lucky Builders (a group of 2 linked companies) has 2 projects on MahaRERA since 2017, this one included. Of the 2 GharKundli has checked: 2 finished, 0 within the promised date and 2 needed more time (typically 65 months). 6 complaints on MahaRERA across 2 projects.
Read Google reviews of SHIVSOLITAIRE →Reviews on Google are opinions by Google users; GharKundli doesn’t check them.
Kundli Watch
SHIVSOLITAIRE: buyers & owners
Free: a WhatsApp update every month on this project, and straight away when anything changes on MahaRERA — a later completion date, new complaints, a red flag. Your number stays private: never shown to other members or the builder.
Be the first to watch this project.
How are you connected to this project?
Bought here? No document needed now. From the builder’s team? Join to answer buyers’ questions; you never see members’ details. You’ll sign in with a one-time code, then come straight back here.
Common questions about SHIVSOLITAIRE
What is the possession date of SHIVSOLITAIRE?
According to GharKundli's check of MahaRERA records (updated October 2026), the latest completion date filed on MahaRERA for SHIVSOLITAIRE in Jogeshwari, Mumbai is 31 December 2026 — 96 months later than 31 December 2018, the date given at registration.
Is the builder's possession date different from the MahaRERA date for SHIVSOLITAIRE?
Builders and listing sites often quote an earlier "target" date for handover. The completion date SHIVSOLITAIRE's builder has filed on MahaRERA, the official one, is 31 December 2026, already 96 months later than the 31 December 2018 given at registration, per GharKundli's check of MahaRERA records. If possession is late, what counts under RERA (Section 18) is the possession date written in your agreement for sale.
Why was the possession date of SHIVSOLITAIRE extended?
According to GharKundli's check of MahaRERA records (updated October 2026), SHIVSOLITAIRE's builder applied to MahaRERA to extend the completion date 3 times: to 31 December 2022, giving the reason "The said project was registered on 16/08/2017 for completion upto 31st December 2018. This is an SRA (Slum Rehabilitation Authority) project. During the tenure of the project many unexpected hurdles arose which extended the proceedings a bit. Some of the hurdles causing the extension are: 1. Delay in approvals and permissions from regulators and competent authorities 2. The Project land was affected by reservations, which were removed pursuant to notification of Development Control and Promotion Regulations for Greater Mumbai, 2034 (“DCPR”). There was inordinate delay in notifying DCPR. 3.…"; to 31 December 2024, giving the reason "Due to uncertain circumstances , the project could not be completed in the given extended time. kindly allow to extend the project completion date further more. Attached Allotees Consent, Affidavit for the Extension of 100 rs, Stamp Paper, Quality Assurance Certificate and Engineer.s certificate for reference. kindly consider the same and grant extension upto 31/12/2024"; to 31 December 2026, giving the reason "As far as work progress on site is considered, we have completed 100% of our work and have received the Part OC on 07/11/2022 and balance on 19-03-2025. While OC Verification it was observed that there are certain mismatch that has to be rectified hence we are filing this application".
What is the RERA number of SHIVSOLITAIRE?
According to GharKundli's check of MahaRERA records (updated October 2026), the MahaRERA registration number of SHIVSOLITAIRE in Jogeshwari, Mumbai is P51900006722.
Is SHIVSOLITAIRE registered with MahaRERA?
According to GharKundli's check of MahaRERA records (updated October 2026), SHIVSOLITAIRE is registered as P51900006722 and its status is "Completed".
What is the construction status of SHIVSOLITAIRE?
According to GharKundli's check of MahaRERA records (updated October 2026), SHIVSOLITAIRE's status on MahaRERA is "Completed". As filed by the builder, slab work on Wing C & D is 100% done and internal work 100%. GharKundli's full report compares construction progress with the deadline.
Does SHIVSOLITAIRE have complaints on MahaRERA?
1 complaint was listed on MahaRERA as of October 2026, per GharKundli's weekly check. GharKundli's full report explains each case and how it ended.
Is SHIVSOLITAIRE safe to buy?
According to GharKundli's check of MahaRERA records (updated October 2026), SHIVSOLITAIRE is registered on MahaRERA as P51900006722, its MahaRERA status is "Completed", its completion date has moved 96 months since registration and 1 complaint is listed against it. GharKundli doesn't call a project safe or unsafe from these numbers alone: its full report gives a risk & trust score with every point explained.
How can I get updates if SHIVSOLITAIRE's possession date changes?
The latest dates are on SHIVSOLITAIRE's MahaRERA page (P51900006722). GharKundli's Kundli Watch sends a free WhatsApp update on SHIVSOLITAIRE every month, and straight away when anything changes on MahaRERA: a later completion date, new complaints or a red flag. Your number is never shown to the builder.
How many floors does SHIVSOLITAIRE have?
According to GharKundli's check of MahaRERA records (updated October 2026), SHIVSOLITAIRE has one building filed: Wing C & D with 12 floors and 212 units.
How much parking does SHIVSOLITAIRE have?
According to GharKundli's check of MahaRERA records (updated October 2026), the builder has filed 102 covered car parking spaces for SHIVSOLITAIRE.
How big is the land of SHIVSOLITAIRE?
According to GharKundli's check of MahaRERA records (updated October 2026), SHIVSOLITAIRE stands on 2,377 sq m of land (about 0.6 acres), with 12,427 sq m of sanctioned built-up area and 540 sq m of recreational open space.
What is the track record of SHIVSOLITAIRE's builder?
According to GharKundli's check of MahaRERA records (updated October 2026), SO Lucky Builders (a group of 2 linked companies) has 2 projects on MahaRERA since 2017, this one included. Of the 2 GharKundli has checked: 2 finished, 0 within the promised date and 2 needed more time (typically 65 months). 6 complaints on MahaRERA across 2 projects. GharKundli's full report covers the builder's record in detail.
Where can I read reviews of SHIVSOLITAIRE?
Google Maps has reviews of SHIVSOLITAIRE written by Google users; GharKundli links to them on this page but doesn't check them. For facts rather than opinions: 1 complaint is listed on MahaRERA, and Kundli Watch shows verified owners of the project.
Where is SHIVSOLITAIRE?
SHIVSOLITAIRE by SO LUCKY BUILDERS is in Jogeshwari, Mumbai (pincode 400060), near Andheri East, Jvlr, Andheri West, Maharashtra, and is registered on MahaRERA as P51900006722, per GharKundli's check of MahaRERA records. Its boundaries filed there include MUNCIPAL MARKET AND EXISTING SLUM.
How many homes are in SHIVSOLITAIRE?
According to GharKundli's check of MahaRERA records (updated October 2026), SHIVSOLITAIRE has 0 homes in 1 tower registered on MahaRERA, and 87% of them are sold or booked.
When was SHIVSOLITAIRE registered on MahaRERA?
According to GharKundli's check of MahaRERA records (updated October 2026), SHIVSOLITAIRE was registered on MahaRERA on 16 August 2017. GharKundli did not find a title report on the land on file there.
Are there court cases on SHIVSOLITAIRE?
No court cases are listed for SHIVSOLITAIRE on MahaRERA, per GharKundli's check of MahaRERA records (updated October 2026).
Who is the builder of SHIVSOLITAIRE?
According to GharKundli's check of MahaRERA records (updated October 2026), the builder is SO LUCKY BUILDERS.
Check it yourself on MahaRERA
- How to check the possession date of SHIVSOLITAIRE
- How to find and verify a MahaRERA number
- How to check construction status on MahaRERA
- Occupancy certificate (OC): what to check before possession
- Possession delayed? Work out the interest the builder owes
- How to file a MahaRERA complaint against a builder
- Where MahaRERA complaints are: the data
- Why builders ask MahaRERA for more time: the data
Other projects in pincode 400060
- BHAWANI HEIGHTS
- Vraj Bhumi Heights
- SHIVKUNJ
- AVANT HERITAGE - III
- Om Shivalaya CHS Ltd
- SHRADDHA WEST RESIDENCY
- ROSE BLOSSOM CHSL
- DATTARAM TOWER
Data compiled by GharKundli (gharkundli.com) from MahaRERA public records, as of October 2026. Check the project’s MahaRERA page for the latest filings. Not legal advice.