by Ami Virag Shivpuri · Tps VI, MumbaiAlso near Vile Parle East, Vile Parle West, Vileparle East

Possession: Purnima is marked completed on MahaRERA. How to check it yourself

Registered on MahaRERA under P51800051454. Status: Completed.

Source: GharKundli’s check of MahaRERA records, October 2026.

What do you want to know about Purnima?

Ask us on WhatsAppNo login needed. A real person replies.

How the possession date of Purnima has moved

  1. 31 December 2024

    Completion date given when the project was registered

  2. 31 December 2025

    Extended at the builder's request (MahaRERA application EXT51800018156)

    Reason the builder gave MahaRERA:
    “In accordance with circular no 28, we hereby apply for extension of our project u/s 6 in Format B. The project was delayed for reasons beyond our control on account of various reasons and more particularly on account of the pandemic of Covi…” Read the full reason“In accordance with circular no 28, we hereby apply for extension of our project u/s 6 in Format B. The project was delayed for reasons beyond our control on account of various reasons and more particularly on account of the pandemic of Covid-19.”
  3. 31 December 2026

    Extended at the builder's request (MahaRERA application EA21022619945)

    Reason the builder gave MahaRERA:
    “We apologize for the delay in the completion of the project and the submission of this request. The extension is being sought solely due to procedural delays in obtaining the Occupation Certificate (OC). Despite the project being substantia…” Read the full reason“We apologize for the delay in the completion of the project and the submission of this request. The extension is being sought solely due to procedural delays in obtaining the Occupation Certificate (OC). Despite the project being substantially completed, the pending procedural approvals have impacted the formal completion timeline. Given these circumstances, we kindly request an extension until 31-12-2026 to complete the project and fulfil all regulatory requirements.”

Source: Purnima’s extension records on MahaRERA (P51800051454), read by GharKundli in October 2026. The builder’s reasons are quoted as filed. Your own possession date is the one in your agreement for sale.

What builders tell MahaRERA when they’re late: 14,973 applications analysed →

GharKundli’s full report on Purnima

Read from every filing on MahaRERA when you open it

  • Risk & trust score, every point explained
  • What the title report says about the land
  • Each complaint and court case, and how it ended
  • Construction pace against the December 2026 deadline
  • Agreement clauses weaker than the RERA model
  • Escrow audit, loans and the builder's record
  • Questions to get answered in writing before you pay
MahaRERA registration
P51800051454
Status
Completed
Builder
Ami Virag Shivpuri
Location
Tps VI, Mumbai · 400056
Project type
Residential / Group Housing
Registered on
23 Jun 2023
Completion date at registration
December 2024
Latest completion date
December 2026
Delay so far
24 months
Homes
9
Sold or booked
33%
Towers
1
Complaints on MahaRERA
0
Court cases listed
0
Title report on file
Not found

Construction progress of Purnima, as filed by the builder

What the builder has reported to MahaRERA, as GharKundli read it in October 2026. GharKundli’s full report compares it with the deadline.

Tower / wingPlinthSlabs (structure)Internal workLifts, fire & electrical
Wing-B100%100%100%100%

Commencement certificate (CC), as filed on MahaRERA

  • Wing-B: covers 10 (G + 9 Upper Floors)

Want to know when this changes? Kundli Watch sends a free WhatsApp update on Purnima every month.

Purnima: buildings, flats and land, as filed on MahaRERA

TypeCarpet area (sq ft)Units
4 BHK2,2977
Duplex2,2972

The builder’s record and reviews

Not enough of this builder’s other MahaRERA projects have reached their promised date to judge yet.

Read Google reviews of Purnima →Reviews on Google are opinions by Google users; GharKundli doesn’t check them.

Kundli Watch

Purnima: buyers & owners

Free: a WhatsApp update every month on this project, and straight away when anything changes on MahaRERA — a later completion date, new complaints, a red flag. Your number stays private: never shown to other members or the builder.

Be the first to watch this project.

How are you connected to this project?

Bought here? No document needed now. From the builder’s team? Join to answer buyers’ questions; you never see members’ details. You’ll sign in with a one-time code, then come straight back here.

Common questions about Purnima

What is the possession date of Purnima?

According to GharKundli's check of MahaRERA records (updated October 2026), the latest completion date filed on MahaRERA for Purnima in Tps VI, Mumbai is 31 December 2026 — 24 months later than 31 December 2024, the date given at registration.

Is the builder's possession date different from the MahaRERA date for Purnima?

Builders and listing sites often quote an earlier "target" date for handover. The completion date Purnima's builder has filed on MahaRERA, the official one, is 31 December 2026, already 24 months later than the 31 December 2024 given at registration, per GharKundli's check of MahaRERA records. If possession is late, what counts under RERA (Section 18) is the possession date written in your agreement for sale.

Why was the possession date of Purnima extended?

According to GharKundli's check of MahaRERA records (updated October 2026), Purnima's builder applied to MahaRERA to extend the completion date 2 times: to 31 December 2025, giving the reason "In accordance with circular no 28, we hereby apply for extension of our project u/s 6 in Format B. The project was delayed for reasons beyond our control on account of various reasons and more particularly on account of the pandemic of Covid-19."; to 31 December 2026, giving the reason "We apologize for the delay in the completion of the project and the submission of this request. The extension is being sought solely due to procedural delays in obtaining the Occupation Certificate (OC). Despite the project being substantially completed, the pending procedural approvals have impacted the formal completion timeline. Given these circumstances, we kindly request an extension until 31-12-2026 to complete the project and fulfil all regulatory requirements.".

What is the RERA number of Purnima?

According to GharKundli's check of MahaRERA records (updated October 2026), the MahaRERA registration number of Purnima in Tps VI, Mumbai is P51800051454.

Is Purnima registered with MahaRERA?

According to GharKundli's check of MahaRERA records (updated October 2026), Purnima is registered as P51800051454 and its status is "Completed".

What is the construction status of Purnima?

According to GharKundli's check of MahaRERA records (updated October 2026), Purnima's status on MahaRERA is "Completed". As filed by the builder, slab work on Wing-B is 100% done and internal work 100%. GharKundli's full report compares construction progress with the deadline.

Does Purnima have complaints on MahaRERA?

No complaints were listed on MahaRERA as of October 2026, per GharKundli's weekly check.

Is Purnima safe to buy?

According to GharKundli's check of MahaRERA records (updated October 2026), Purnima is registered on MahaRERA as P51800051454, its MahaRERA status is "Completed", its completion date has moved 24 months since registration and no complaints are listed against it. GharKundli doesn't call a project safe or unsafe from these numbers alone: its full report gives a risk & trust score with every point explained.

How can I get updates if Purnima's possession date changes?

The latest dates are on Purnima's MahaRERA page (P51800051454). GharKundli's Kundli Watch sends a free WhatsApp update on Purnima every month, and straight away when anything changes on MahaRERA: a later completion date, new complaints or a red flag. Your number is never shown to the builder.

How many floors does Purnima have?

According to GharKundli's check of MahaRERA records (updated October 2026), Purnima has one building filed: Wing-B with 10 floors and 9 units.

What are the flat sizes (carpet area) in Purnima?

According to GharKundli's check of MahaRERA records (updated October 2026), the builder has filed these homes for Purnima: 4 BHK: 2297 sq ft carpet (7 homes); Duplex: 2297 sq ft carpet (2 homes). Carpet area is the usable floor area inside the walls, as defined under RERA.

How big is the land of Purnima?

According to GharKundli's check of MahaRERA records (updated October 2026), Purnima stands on 889 sq m of land (about 0.2 acres), with 1,074 sq m of sanctioned built-up area.

Where can I read reviews of Purnima?

Google Maps has reviews of Purnima written by Google users; GharKundli links to them on this page but doesn't check them. For facts rather than opinions: no complaints are listed on MahaRERA, and Kundli Watch shows verified owners of the project.

Where is Purnima?

Purnima by Ami Virag Shivpuri is in Tps VI, Mumbai (pincode 400056), near Vile Parle East, Vile Parle West, Vileparle East, Maharashtra, and is registered on MahaRERA as P51800051454, per GharKundli's check of MahaRERA records. Its boundaries filed there include 9M Wide Vithal Bhai Road.

How many homes are in Purnima?

According to GharKundli's check of MahaRERA records (updated October 2026), Purnima has 9 homes in 1 tower registered on MahaRERA, and 33% of them are sold or booked.

When was Purnima registered on MahaRERA?

According to GharKundli's check of MahaRERA records (updated October 2026), Purnima was registered on MahaRERA on 23 June 2023. GharKundli did not find a title report on the land on file there.

Are there court cases on Purnima?

No court cases are listed for Purnima on MahaRERA, per GharKundli's check of MahaRERA records (updated October 2026).

Who is the builder of Purnima?

According to GharKundli's check of MahaRERA records (updated October 2026), the builder is Ami Virag Shivpuri.