Possession date of RAGHAV ANANTA: 30 April 2028, moved from 31 December 2026 (12 months later). This is the latest completion date the builder has filed on MahaRERA. How to check it yourself

Registered on MahaRERA under P51800054281, and currently active. Its completion date has moved from December 2026 to April 2028: 12 months at the builder's request, plus MahaRERA's automatic 4-month extension for all eligible projects. 1 complaint is listed against it on MahaRERA.

Source: GharKundli’s check of MahaRERA records, October 2026.

What do you want to know about RAGHAV ANANTA?

Ask us on WhatsAppNo login needed. A real person replies.

How the possession date of RAGHAV ANANTA has moved

  1. 31 December 2026

    Completion date given when the project was registered

  2. 30 December 2027

    Extended at the builder's request (MahaRERA application EA27062501830)

    Reason the builder gave MahaRERA: “Non-availability of labor”
  3. 30 April 2028

    MahaRERA's automatic 4-month extension for all eligible projects, not the builder's request

Source: RAGHAV ANANTA’s extension records on MahaRERA (P51800054281), read by GharKundli in October 2026. The builder’s reasons are quoted as filed. Your own possession date is the one in your agreement for sale.

What builders tell MahaRERA when they’re late: 14,973 applications analysed →

GharKundli’s full report on RAGHAV ANANTA

Read from every filing on MahaRERA when you open it

  • Risk & trust score, every point explained
  • What the title report says about the land
  • Each of the 1 complaint, and how it ended
  • Construction pace against the April 2028 deadline
  • Agreement clauses weaker than the RERA model
  • Escrow audit, loans and the builder's record
  • Questions to get answered in writing before you pay
MahaRERA registration
P51800054281
Status
Registered and active
Builder
RAGHAV RAJ BUILDERS & DEVELOPERS LLP
Location
Vikhroli East, Mumbai · 400083
Project type
Residential / Group Housing
Registered on
15 Jan 2024
Completion date at registration
December 2026
Latest completion date
April 2028
Delay so far
12 months
MahaRERA's automatic extension
+4 months (force majeure, all eligible projects)
Towers
1
Complaints on MahaRERA
1
Court cases listed
0
Title report on file
Not found
Builder's other MahaRERA projects
10

Construction progress of RAGHAV ANANTA, as filed by the builder

What the builder has reported to MahaRERA, as GharKundli read it in October 2026. GharKundli’s full report compares it with the deadline.

Tower / wingPlinthSlabs (structure)Internal workLifts, fire & electrical
RAGHAV ANANTA100%90%70%30%

Want to know when this changes? Kundli Watch sends a free WhatsApp update on RAGHAV ANANTA every month.

RAGHAV ANANTA: buildings, flats and land, as filed on MahaRERA

The builder’s record and reviews

Raghav RAJ Builders & Developers (a group of 5 linked companies) has 15 projects on MahaRERA since 2019, this one included. Of the 15 GharKundli has checked: 4 finished, 2 within the promised date and 2 needed more time (typically 12 months); 10 still being built, 1 past the promised date (typically 10 months late); 1 lapsed. 6 complaints on MahaRERA across 4 projects.

Read Google reviews of RAGHAV ANANTA →Reviews on Google are opinions by Google users; GharKundli doesn’t check them.

Kundli Watch

RAGHAV ANANTA: buyers & owners

Free: a WhatsApp update every month on this project, and straight away when anything changes on MahaRERA — a later completion date, new complaints, a red flag. Your number stays private: never shown to other members or the builder.

Be the first to watch this project.

How are you connected to this project?

Bought here? No document needed now. From the builder’s team? Join to answer buyers’ questions; you never see members’ details. You’ll sign in with a one-time code, then come straight back here.

Common questions about RAGHAV ANANTA

What is the possession date of RAGHAV ANANTA?

According to GharKundli's check of MahaRERA records (updated October 2026), the latest completion date filed on MahaRERA for RAGHAV ANANTA in Vikhroli East, Mumbai is 30 April 2028 — 12 months later than 31 December 2026, the date given at registration, plus MahaRERA's automatic 4-month extension for all eligible projects.

Is the builder's possession date different from the MahaRERA date for RAGHAV ANANTA?

Builders and listing sites often quote an earlier "target" date for handover. The completion date RAGHAV ANANTA's builder has filed on MahaRERA, the official one, is 30 April 2028, already 12 months later than the 31 December 2026 given at registration, per GharKundli's check of MahaRERA records. If possession is late, what counts under RERA (Section 18) is the possession date written in your agreement for sale.

Why was the possession date of RAGHAV ANANTA extended?

According to GharKundli's check of MahaRERA records (updated October 2026), RAGHAV ANANTA's builder applied to MahaRERA to extend the completion date once: to 30 December 2027, giving the reason "Non-availability of labor". MahaRERA also added its automatic 4-month extension for all eligible projects.

What is the RERA number of RAGHAV ANANTA?

According to GharKundli's check of MahaRERA records (updated October 2026), the MahaRERA registration number of RAGHAV ANANTA in Vikhroli East, Mumbai is P51800054281.

Is RAGHAV ANANTA registered with MahaRERA?

According to GharKundli's check of MahaRERA records (updated October 2026), RAGHAV ANANTA is registered as P51800054281 and its status is "Registered and active".

What is the construction status of RAGHAV ANANTA?

According to GharKundli's check of MahaRERA records (updated October 2026), RAGHAV ANANTA's status on MahaRERA is "Registered and active". As filed by the builder, slab work on RAGHAV ANANTA is 90% done and internal work 70%. GharKundli's full report compares construction progress with the deadline.

Does RAGHAV ANANTA have complaints on MahaRERA?

1 complaint was listed on MahaRERA as of October 2026, per GharKundli's weekly check. GharKundli's full report explains each case and how it ended.

Is RAGHAV ANANTA safe to buy?

According to GharKundli's check of MahaRERA records (updated October 2026), RAGHAV ANANTA is registered on MahaRERA as P51800054281, its completion date has moved 12 months since registration and 1 complaint is listed against it. GharKundli doesn't call a project safe or unsafe from these numbers alone: its full report gives a risk & trust score with every point explained.

How can I get updates if RAGHAV ANANTA's possession date changes?

The latest dates are on RAGHAV ANANTA's MahaRERA page (P51800054281). GharKundli's Kundli Watch sends a free WhatsApp update on RAGHAV ANANTA every month, and straight away when anything changes on MahaRERA: a later completion date, new complaints or a red flag. Your number is never shown to the builder.

How many floors does RAGHAV ANANTA have?

According to GharKundli's check of MahaRERA records (updated October 2026), RAGHAV ANANTA has one building filed: RAGHAV ANANTA with 1 floors.

How much parking does RAGHAV ANANTA have?

According to GharKundli's check of MahaRERA records (updated October 2026), the builder has filed 87 covered car parking spaces for RAGHAV ANANTA.

How big is the land of RAGHAV ANANTA?

According to GharKundli's check of MahaRERA records (updated October 2026), RAGHAV ANANTA stands on 1,006 sq m of land (about 0.2 acres).

What is the track record of RAGHAV ANANTA's builder?

According to GharKundli's check of MahaRERA records (updated October 2026), Raghav RAJ Builders & Developers (a group of 5 linked companies) has 15 projects on MahaRERA since 2019, this one included. Of the 15 GharKundli has checked: 4 finished, 2 within the promised date and 2 needed more time (typically 12 months); 10 still being built, 1 past the promised date (typically 10 months late); 1 lapsed. 6 complaints on MahaRERA across 4 projects. GharKundli's full report covers the builder's record in detail.

Where can I read reviews of RAGHAV ANANTA?

Google Maps has reviews of RAGHAV ANANTA written by Google users; GharKundli links to them on this page but doesn't check them. For facts rather than opinions: 1 complaint is listed on MahaRERA, and Kundli Watch shows verified owners of the project.

Where is RAGHAV ANANTA?

RAGHAV ANANTA by RAGHAV RAJ BUILDERS & DEVELOPERS LLP is in Vikhroli East, Mumbai (pincode 400083), near kanamwar Nagar, Hariyali, Vikhroli, Tagore Nagar, Maharashtra, and is registered on MahaRERA as P51800054281, per GharKundli's check of MahaRERA records. Its boundaries filed there include 40 INCH WIDE ROAD.

When was RAGHAV ANANTA registered on MahaRERA?

According to GharKundli's check of MahaRERA records (updated October 2026), RAGHAV ANANTA was registered on MahaRERA on 15 January 2024. GharKundli did not find a title report on the land on file there.

Are there court cases on RAGHAV ANANTA?

No court cases are listed for RAGHAV ANANTA on MahaRERA, per GharKundli's check of MahaRERA records (updated October 2026).

Who is the builder of RAGHAV ANANTA?

According to GharKundli's check of MahaRERA records (updated October 2026), the builder is RAGHAV RAJ BUILDERS & DEVELOPERS LLP, which has 10 other projects registered on MahaRERA.

All projects with possession due in 2028 in Mumbai Suburban →

Other projects in Vikhroli East

All 176 projects in Vikhroli East (400083) →

Other projects by RAGHAV RAJ BUILDERS & DEVELOPERS LLP

Data compiled by GharKundli (gharkundli.com) from MahaRERA public records, as of October 2026. Check the project’s MahaRERA page for the latest filings. Not legal advice.