by M/s. virtue Enterprises (Darshan) · Dadar, MumbaiAlso near Shivaji Park, Matunga, Mahim
Possession date of Promesa West End: 31 December 2026, moved from 30 December 2021 (60 months later). This is the latest completion date the builder has filed on MahaRERA. How to check it yourself
Registered on MahaRERA under P51900004931, and currently active. 3 complaints are listed against it on MahaRERA.
Source: GharKundli’s check of MahaRERA records, October 2026.
What do you want to know about Promesa West End?
How the possession date of Promesa West End has moved
30 December 2021
Completion date given when the project was registered
31 December 2025
Extended at the builder's request (MahaRERA application EXT51900016561)
Reason the builder gave MahaRERA:
“1) Mhada NOC for Composite Redevelopment of plot bearing F.P.No.415 and 416 of TPS-IV Mahim vide letter No. R/NOC/F-1824 & 2156/6900/MBRRB-13 dated 05.09.2013. 2) MCGM IOD - EB/7130/GN/A dated 15.01.2015. 3) Tenants vacating started n compl…” Read the full reason
“1) Mhada NOC for Composite Redevelopment of plot bearing F.P.No.415 and 416 of TPS-IV Mahim vide letter No. R/NOC/F-1824 & 2156/6900/MBRRB-13 dated 05.09.2013. 2) MCGM IOD - EB/7130/GN/A dated 15.01.2015. 3) Tenants vacating started n completed following due Process of Law. 4) MCGM C.C. - CHE/CTY/0719/G/N/337 (NEW) dated 21.07.2017. 5) Construction on Site Started, n Plinth Completed. 6) UD Dept. Modified DCPR 2034 notification dated 21.09.2018 & 12.11.2018. 7) Mhada NOC for Composite Redevelopment of plot bearing F.P.No.415 and 416 of TPS-IV Mahim vide letter No. R/NOC/F-1824 & 2156/2336/M…”31 December 2026
Extended at the builder's request (MahaRERA application EA05032620107)
Reason the builder gave MahaRERA:
“We sincerely apologize for the delay in the completion of the project and the submission of this request. We would like to inform you that the major construction work of the project has already been completed. At present, only minor works s…” Read the full reason
“We sincerely apologize for the delay in the completion of the project and the submission of this request. We would like to inform you that the major construction work of the project has already been completed. At present, only minor works such as finishing, sanitary fittings, electrical fittings, and other related finishing activities are in progress. Due to the ongoing completion of these minor works, there has been a delay in applying for the Occupancy Certificate (OC), which has consequently resulted in a further delay in obtaining the OC. We are monitoring the progress and taking all ne…”
Source: Promesa West End’s extension records on MahaRERA (P51900004931), read by GharKundli in October 2026. The builder’s reasons are quoted as filed. Your own possession date is the one in your agreement for sale.
What builders tell MahaRERA when they’re late: 14,973 applications analysed →GharKundli’s full report on Promesa West End
Read from every filing on MahaRERA when you open it
- Risk & trust score, every point explained
- What the title report says about the land
- Each of the 3 complaints and 2 court cases, and how it ended
- Construction pace against the December 2026 deadline
- Agreement clauses weaker than the RERA model
- Escrow audit, loans and the builder's record
- Questions to get answered in writing before you pay
- MahaRERA registration
- P51900004931
- Status
- Registered and active
- Builder
- M/s. virtue Enterprises
- Location
- Dadar, Mumbai · 400028
- Project type
- Residential / Group Housing
- Registered on
- 9 Aug 2017
- Completion date at registration
- December 2021
- Latest completion date
- December 2026
- Delay so far
- 60 months
- Homes
- 126
- Sold or booked
- 57%
- Towers
- 1
- Complaints on MahaRERA
- 3
- Court cases listed
- 2
- Appeals at the tribunal
- 1
- Title report on file
- Not found
Construction progress of Promesa West End, as filed by the builder
What the builder has reported to MahaRERA, as GharKundli read it in October 2026. GharKundli’s full report compares it with the deadline.
| Tower / wing | Plinth | Slabs (structure) | Internal work | Lifts, fire & electrical |
|---|---|---|---|---|
| Promesa West End | 100% | 100% | 100% | 710% |
Commencement certificate (CC), as filed on MahaRERA
- Promesa West End: covers 25 floors
Want to know when this changes? Kundli Watch sends a free WhatsApp update on Promesa West End every month.
Promesa West End: buildings, flats and land, as filed on MahaRERA
| Type | Carpet area (sq ft) | Units |
|---|---|---|
| 2 BHK | 380 – 1,249 | 126 |
| Shops | 415 – 884 | 4 |
- Buildings: Promesa West End (21 floors, 130 units)
- Land: 873 sq m (about 0.2 acres) · sanctioned built-up 3,889 sq m
- Boundaries filed include: GOKHALE ROAD
- Map: the location the builder filed on MahaRERA
The builder’s record and reviews
Darshan Group (a group of 4 linked companies) has 7 projects on MahaRERA since 2017, this one included. Of the 7 GharKundli has checked: 1 finished, all within the promised date; 5 still being built, 3 past the promised date (typically 10 months late); 1 lapsed. 3 complaints on MahaRERA across 1 project.
Read Google reviews of Promesa West End →Reviews on Google are opinions by Google users; GharKundli doesn’t check them.
Kundli Watch
Promesa West End: buyers & owners
Free: a WhatsApp update every month on this project, and straight away when anything changes on MahaRERA — a later completion date, new complaints, a red flag. Your number stays private: never shown to other members or the builder.
Be the first to watch this project.
How are you connected to this project?
Bought here? No document needed now. From the builder’s team? Join to answer buyers’ questions; you never see members’ details. You’ll sign in with a one-time code, then come straight back here.
Common questions about Promesa West End
What is the possession date of Promesa West End?
According to GharKundli's check of MahaRERA records (updated October 2026), the latest completion date filed on MahaRERA for Promesa West End in Dadar, Mumbai is 31 December 2026 — 60 months later than 30 December 2021, the date given at registration.
Is the builder's possession date different from the MahaRERA date for Promesa West End?
Builders and listing sites often quote an earlier "target" date for handover. The completion date Promesa West End's builder has filed on MahaRERA, the official one, is 31 December 2026, already 60 months later than the 30 December 2021 given at registration, per GharKundli's check of MahaRERA records. If possession is late, what counts under RERA (Section 18) is the possession date written in your agreement for sale.
Why was the possession date of Promesa West End extended?
According to GharKundli's check of MahaRERA records (updated October 2026), Promesa West End's builder applied to MahaRERA to extend the completion date 2 times: to 31 December 2025, giving the reason "1) Mhada NOC for Composite Redevelopment of plot bearing F.P.No.415 and 416 of TPS-IV Mahim vide letter No. R/NOC/F-1824 & 2156/6900/MBRRB-13 dated 05.09.2013. 2) MCGM IOD - EB/7130/GN/A dated 15.01.2015. 3) Tenants vacating started n completed following due Process of Law. 4) MCGM C.C. - CHE/CTY/0719/G/N/337 (NEW) dated 21.07.2017. 5) Construction on Site Started, n Plinth Completed. 6) UD Dept. Modified DCPR 2034 notification dated 21.09.2018 & 12.11.2018. 7) Mhada NOC for Composite Redevelopment of plot bearing F.P.No.415 and 416 of TPS-IV Mahim vide letter No. R/NOC/F-1824 & 2156/2336/M…"; to 31 December 2026, giving the reason "We sincerely apologize for the delay in the completion of the project and the submission of this request. We would like to inform you that the major construction work of the project has already been completed. At present, only minor works such as finishing, sanitary fittings, electrical fittings, and other related finishing activities are in progress. Due to the ongoing completion of these minor works, there has been a delay in applying for the Occupancy Certificate (OC), which has consequently resulted in a further delay in obtaining the OC. We are monitoring the progress and taking all ne…".
What is the RERA number of Promesa West End?
According to GharKundli's check of MahaRERA records (updated October 2026), the MahaRERA registration number of Promesa West End in Dadar, Mumbai is P51900004931.
Is Promesa West End registered with MahaRERA?
According to GharKundli's check of MahaRERA records (updated October 2026), Promesa West End is registered as P51900004931 and its status is "Registered and active".
What is the construction status of Promesa West End?
According to GharKundli's check of MahaRERA records (updated October 2026), Promesa West End's status on MahaRERA is "Registered and active". As filed by the builder, slab work on Promesa West End is 100% done and internal work 100%. GharKundli's full report compares construction progress with the deadline.
Does Promesa West End have complaints on MahaRERA?
3 complaints were listed on MahaRERA as of October 2026, per GharKundli's weekly check. GharKundli's full report explains each case and how it ended.
Is Promesa West End safe to buy?
According to GharKundli's check of MahaRERA records (updated October 2026), Promesa West End is registered on MahaRERA as P51900004931, its completion date has moved 60 months since registration and 3 complaints are listed against it. GharKundli doesn't call a project safe or unsafe from these numbers alone: its full report gives a risk & trust score with every point explained.
How can I get updates if Promesa West End's possession date changes?
The latest dates are on Promesa West End's MahaRERA page (P51900004931). GharKundli's Kundli Watch sends a free WhatsApp update on Promesa West End every month, and straight away when anything changes on MahaRERA: a later completion date, new complaints or a red flag. Your number is never shown to the builder.
How many floors does Promesa West End have?
According to GharKundli's check of MahaRERA records (updated October 2026), Promesa West End has one building filed: Promesa West End with 21 floors and 130 units.
What are the flat sizes (carpet area) in Promesa West End?
According to GharKundli's check of MahaRERA records (updated October 2026), the builder has filed these homes for Promesa West End: 2 BHK: 380 to 1249 sq ft carpet (126 homes). Carpet area is the usable floor area inside the walls, as defined under RERA.
How big is the land of Promesa West End?
According to GharKundli's check of MahaRERA records (updated October 2026), Promesa West End stands on 873 sq m of land (about 0.2 acres), with 3,889 sq m of sanctioned built-up area.
What is the track record of Promesa West End's builder?
According to GharKundli's check of MahaRERA records (updated October 2026), Darshan Group (a group of 4 linked companies) has 7 projects on MahaRERA since 2017, this one included. Of the 7 GharKundli has checked: 1 finished, all within the promised date; 5 still being built, 3 past the promised date (typically 10 months late); 1 lapsed. 3 complaints on MahaRERA across 1 project. GharKundli's full report covers the builder's record in detail.
Where can I read reviews of Promesa West End?
Google Maps has reviews of Promesa West End written by Google users; GharKundli links to them on this page but doesn't check them. For facts rather than opinions: 3 complaints are listed on MahaRERA, and Kundli Watch shows verified owners of the project.
Where is Promesa West End?
Promesa West End by M/s. virtue Enterprises (Darshan) is in Dadar, Mumbai (pincode 400028), near Shivaji Park, Matunga, Mahim, Maharashtra, and is registered on MahaRERA as P51900004931, per GharKundli's check of MahaRERA records. Its boundaries filed there include GOKHALE ROAD.
How many homes are in Promesa West End?
According to GharKundli's check of MahaRERA records (updated October 2026), Promesa West End has 126 homes in 1 tower registered on MahaRERA, and 57% of them are sold or booked.
When was Promesa West End registered on MahaRERA?
According to GharKundli's check of MahaRERA records (updated October 2026), Promesa West End was registered on MahaRERA on 9 August 2017. GharKundli did not find a title report on the land on file there.
Are there court cases on Promesa West End?
2 court cases are listed for Promesa West End on MahaRERA, and 1 appeal at the tribunal, per GharKundli's check of MahaRERA records (updated October 2026). GharKundli's full report explains each case and how it ended.
Who is the builder of Promesa West End?
According to GharKundli's check of MahaRERA records (updated October 2026), the builder is M/s. virtue Enterprises, the company Darshan files this project under.
Check it yourself on MahaRERA
- How to check the possession date of Promesa West End
- How to find and verify a MahaRERA number
- How to check construction status on MahaRERA
- Occupancy certificate (OC): what to check before possession
- Possession delayed? Work out the interest the builder owes
- How to file a MahaRERA complaint against a builder
- Where MahaRERA complaints are: the data
- Why builders ask MahaRERA for more time: the data
All projects with possession due in 2026 in Mumbai City →
Other projects in Dadar
- VISION CREST
- EL MEJOR
- Janai Heritage
- Yashraj Pristine
- Shanti Square
- Shraddha
- Essgee Options One -Phase II
- Essgee Options One - Phase II
Data compiled by GharKundli (gharkundli.com) from MahaRERA public records, as of October 2026. Check the project’s MahaRERA page for the latest filings. Not legal advice.