Redevelopment Of Mangal Karini CHSL

by Anjani Kumar Developers LLP · Laxmi Narayan Mandir Road, Mumbai

Registered on MahaRERA under P51800052365, and currently active. Its completion date has moved from December 2026 to April 2027, 4 months later.

Source: GharKundli’s check of MahaRERA records, October 2026.

MahaRERA registration
P51800052365
Status
Registered and active
Builder
Anjani Kumar Developers LLP
Location
Laxmi Narayan Mandir Road, Mumbai · 400104
Project type
Residential / Group Housing
Registered on
21 Aug 2023
Completion date at registration
December 2026
Latest completion date
April 2027
Delay so far
4 months
Homes
98
Sold or booked
57%
Towers
1
Complaints on MahaRERA
0
Court cases listed
1
Title report on file
Not found

GharKundli’s full report on Redevelopment Of Mangal Karini CHSL

Read from every filing on MahaRERA when you open it

  • Risk & trust score, every point explained
  • What the title report says about the land
  • Each complaint and court case, and how it ended
  • Construction pace against the deadline
  • Agreement clauses weaker than the RERA model
  • Escrow audit, loans and the builder's record
  • Questions to get answered in writing before you pay

Kundli Watch

Redevelopment Of Mangal Karini CHSL: buyers & owners

Free. You talk to our team privately — no one sees your number.

How are you connected to this project?

You’ll sign in with your mobile number first, then come straight back here.

Common questions about Redevelopment Of Mangal Karini CHSL

Is Redevelopment Of Mangal Karini CHSL registered with MahaRERA?

According to GharKundli's check of MahaRERA records (updated October 2026), Redevelopment Of Mangal Karini CHSL is registered as P51800052365 and its status is "Registered and active".

Where is Redevelopment Of Mangal Karini CHSL?

Redevelopment Of Mangal Karini CHSL by Anjani Kumar Developers LLP is in Laxmi Narayan Mandir Road, Mumbai (pincode 400104), Maharashtra, and is registered on MahaRERA as P51800052365, per GharKundli's check of MahaRERA records.

When is possession of Redevelopment Of Mangal Karini CHSL due?

According to GharKundli's check of MahaRERA records (updated October 2026), the latest completion date filed on MahaRERA for Redevelopment Of Mangal Karini CHSL in Laxmi Narayan Mandir Road, Mumbai is 30 April 2027 — 4 months later than 31 December 2026, the date given at registration.

Does Redevelopment Of Mangal Karini CHSL have complaints on MahaRERA?

No complaints were listed on MahaRERA as of October 2026, per GharKundli's weekly check. GharKundli's full report explains each case and how it ended.

Who is the builder of Redevelopment Of Mangal Karini CHSL?

According to GharKundli's check of MahaRERA records (updated October 2026), the builder is Anjani Kumar Developers LLP.

Other projects in pincode 400104

Data compiled by GharKundli (gharkundli.com) from MahaRERA public records, as of October 2026. Check the project’s MahaRERA page for the latest filings. Not legal advice.