THE KONARK RISE
by KONARK RAJENDRA SHAH · Borivali West, Mumbai
Possession date of THE KONARK RISE: 30 April 2028, moved from 31 March 2026 (21 months later). This is the latest completion date the builder has filed on MahaRERA. How to check it yourself
Registered on MahaRERA under P51800052330, and currently active. Its completion date has moved from March 2026 to April 2028: 21 months at the builder's request, plus MahaRERA's automatic 4-month extension for all eligible projects.
Source: GharKundli’s check of MahaRERA records, October 2026.
What do you want to know about THE KONARK RISE?
GharKundli’s full report on THE KONARK RISE
Read from every filing on MahaRERA when you open it
- Risk & trust score, every point explained
- What the title report says about the land
- Each complaint and court case, and how it ended
- Construction pace against the April 2028 deadline
- Agreement clauses weaker than the RERA model
- Escrow audit, loans and the builder's record
- Questions to get answered in writing before you pay
- MahaRERA registration
- P51800052330
- Status
- Registered and active
- Builder
- KONARK RAJENDRA SHAH
- Location
- Borivali West, Mumbai · 400096
- Project type
- Commercial
- Registered on
- 10 Aug 2023
- Completion date at registration
- March 2026
- Latest completion date
- April 2028
- Delay so far
- 21 months
- MahaRERA's automatic extension
- +4 months (force majeure, all eligible projects)
- Homes
- 0
- Sold or booked
- 31%
- Towers
- 1
- Complaints on MahaRERA
- 0
- Court cases listed
- 0
- Title report on file
- Not found
- Builder's other MahaRERA projects
- 1
Construction progress of THE KONARK RISE, as filed by the builder
What the builder has reported to MahaRERA, as GharKundli read it in October 2026. GharKundli’s full report compares it with the deadline.
| Tower / wing | Plinth | Slabs (structure) | Internal work | Lifts, fire & electrical |
|---|---|---|---|---|
| THE KONARK RISE | 100% | 100% | 90% | 30% |
Commencement certificate (CC), as filed on MahaRERA
- THE KONARK RISE: covers FULL CC TILL 16TH UPPER FLOOR
Latest CC order on MahaRERA: dated 08/04/2025.
Want to know when this changes? Kundli Watch sends a free WhatsApp update on THE KONARK RISE every month.
THE KONARK RISE: buildings, flats and land, as filed on MahaRERA
| Type | Carpet area (sq ft) | Units |
|---|---|---|
| Office Space | 786 – 1,176 | 16 |
- Buildings: THE KONARK RISE (17 floors, 16 units)
- Car parking: 36 covered
- Land: 337 sq m (about 0.1 acres) · sanctioned built-up 1,807 sq m
The builder’s record and reviews
Konark Rajendra Shah has 2 projects on MahaRERA since 2023, this one included. Of the 2 GharKundli has checked: 2 still being built, 2 past the promised date (typically 9 months late). 1 complaint on MahaRERA across 1 project.
Read Google reviews of THE KONARK RISE →Reviews on Google are opinions by Google users; GharKundli doesn’t check them.
Kundli Watch
THE KONARK RISE: buyers & owners
Free: a WhatsApp update every month on this project, and straight away when anything changes on MahaRERA — a later completion date, new complaints, a red flag. Your number stays private: never shown to other members or the builder.
Be the first to watch this project.
How are you connected to this project?
Bought here? No document needed now. From the builder’s team? Join to answer buyers’ questions; you never see members’ details. You’ll sign in with a one-time code, then come straight back here.
Common questions about THE KONARK RISE
What is the possession date of THE KONARK RISE?
According to GharKundli's check of MahaRERA records (updated October 2026), the latest completion date filed on MahaRERA for THE KONARK RISE in Borivali West, Mumbai is 30 April 2028 — 21 months later than 31 March 2026, the date given at registration, plus MahaRERA's automatic 4-month extension for all eligible projects.
Is the builder's possession date different from the MahaRERA date for THE KONARK RISE?
Builders and listing sites often quote an earlier "target" date for handover. The completion date THE KONARK RISE's builder has filed on MahaRERA, the official one, is 30 April 2028, already 21 months later than the 31 March 2026 given at registration, per GharKundli's check of MahaRERA records. If possession is late, what counts under RERA (Section 18) is the possession date written in your agreement for sale.
What is the RERA number of THE KONARK RISE?
According to GharKundli's check of MahaRERA records (updated October 2026), the MahaRERA registration number of THE KONARK RISE in Borivali West, Mumbai is P51800052330.
Is THE KONARK RISE registered with MahaRERA?
According to GharKundli's check of MahaRERA records (updated October 2026), THE KONARK RISE is registered as P51800052330 and its status is "Registered and active".
What is the construction status of THE KONARK RISE?
According to GharKundli's check of MahaRERA records (updated October 2026), THE KONARK RISE's status on MahaRERA is "Registered and active". As filed by the builder, slab work on THE KONARK RISE is 100% done and internal work 90%. GharKundli's full report compares construction progress with the deadline.
Does THE KONARK RISE have complaints on MahaRERA?
No complaints were listed on MahaRERA as of October 2026, per GharKundli's weekly check.
Is THE KONARK RISE safe to buy?
According to GharKundli's check of MahaRERA records (updated October 2026), THE KONARK RISE is registered on MahaRERA as P51800052330, its completion date has moved 21 months since registration and no complaints are listed against it. GharKundli doesn't call a project safe or unsafe from these numbers alone: its full report gives a risk & trust score with every point explained.
How can I get updates if THE KONARK RISE's possession date changes?
The latest dates are on THE KONARK RISE's MahaRERA page (P51800052330). GharKundli's Kundli Watch sends a free WhatsApp update on THE KONARK RISE every month, and straight away when anything changes on MahaRERA: a later completion date, new complaints or a red flag. Your number is never shown to the builder.
How many floors does THE KONARK RISE have?
According to GharKundli's check of MahaRERA records (updated October 2026), THE KONARK RISE has one building filed: THE KONARK RISE with 17 floors and 16 units.
How much parking does THE KONARK RISE have?
According to GharKundli's check of MahaRERA records (updated October 2026), the builder has filed 36 covered car parking spaces for THE KONARK RISE.
How big is the land of THE KONARK RISE?
According to GharKundli's check of MahaRERA records (updated October 2026), THE KONARK RISE stands on 337 sq m of land (about 0.1 acres), with 1,807 sq m of sanctioned built-up area.
What is the track record of THE KONARK RISE's builder?
According to GharKundli's check of MahaRERA records (updated October 2026), Konark Rajendra Shah has 2 projects on MahaRERA since 2023, this one included. Of the 2 GharKundli has checked: 2 still being built, 2 past the promised date (typically 9 months late). 1 complaint on MahaRERA across 1 project. GharKundli's full report covers the builder's record in detail.
Where can I read reviews of THE KONARK RISE?
Google Maps has reviews of THE KONARK RISE written by Google users; GharKundli links to them on this page but doesn't check them. For facts rather than opinions: no complaints are listed on MahaRERA, and Kundli Watch shows verified owners of the project.
Where is THE KONARK RISE?
THE KONARK RISE by KONARK RAJENDRA SHAH is in Borivali West, Mumbai (pincode 400096), Maharashtra, and is registered on MahaRERA as P51800052330, per GharKundli's check of MahaRERA records.
How many homes are in THE KONARK RISE?
According to GharKundli's check of MahaRERA records (updated October 2026), THE KONARK RISE has 0 homes in 1 tower registered on MahaRERA, and 31% of them are sold or booked.
When was THE KONARK RISE registered on MahaRERA?
According to GharKundli's check of MahaRERA records (updated October 2026), THE KONARK RISE was registered on MahaRERA on 10 August 2023. GharKundli did not find a title report on the land on file there.
Are there court cases on THE KONARK RISE?
No court cases are listed for THE KONARK RISE on MahaRERA, per GharKundli's check of MahaRERA records (updated October 2026).
Who is the builder of THE KONARK RISE?
According to GharKundli's check of MahaRERA records (updated October 2026), the builder is KONARK RAJENDRA SHAH, which has 1 other project registered on MahaRERA.
Check it yourself on MahaRERA
- How to check the possession date of THE KONARK RISE
- How to find and verify a MahaRERA number
- How to check construction status on MahaRERA
- Occupancy certificate (OC): what to check before possession
- Possession delayed? Work out the interest the builder owes
- How to file a MahaRERA complaint against a builder
- Where MahaRERA complaints are: the data
- Why builders ask MahaRERA for more time: the data
All projects with possession due in 2028 in Mumbai Suburban →
All projects in Seepz (400096) →
Data compiled by GharKundli (gharkundli.com) from MahaRERA public records, as of October 2026. Check the project’s MahaRERA page for the latest filings. Not legal advice.