Skip to content
GharKundli

Kalpataru Vivant - South Wing C

by Alder Residency Private Limited (Kalpataru) · Jvlr, MumbaiAlso near Jogeshwari East, Jogeshwari West, Seepz

Possession date of Kalpataru Vivant - South Wing C: 30 April 2029. This is the latest completion date the builder has filed on MahaRERA. How to check it yourself

Registered on MahaRERA under P51800053558, and currently active. Its completion date is now April 2029, including MahaRERA's automatic 4-month extension for all eligible projects; the builder hasn't asked for more time. 1 complaint is listed against it on MahaRERA.

Source: GharKundli’s check of MahaRERA records, October 2026.

What do you want to know about Kalpataru Vivant - South Wing C?

Ask us on WhatsAppNo login needed. A real person replies.

How the possession date of Kalpataru Vivant - South Wing C has moved

  1. 31 December 2028

    Completion date given when the project was registered

  2. 30 April 2029

    MahaRERA's automatic 4-month extension for all eligible projects, not the builder's request

Source: Kalpataru Vivant - South Wing C’s extension records on MahaRERA (P51800053558), read by GharKundli in October 2026. The builder’s reasons are quoted as filed. Your own possession date is the one in your agreement for sale.

What builders tell MahaRERA when they’re late: 14,973 applications analysed →

GharKundli’s full report on Kalpataru Vivant - South Wing C

Read from every filing on MahaRERA when you open it

  • Risk & trust score, every point explained
  • What the title report says about the land
  • Each of the 1 complaint, and how it ended
  • Construction pace against the April 2029 deadline
  • Agreement clauses weaker than the RERA model
  • Escrow audit, loans and the builder's record
  • Questions to get answered in writing before you pay

Other wings and phases of this project

Each is registered on MahaRERA separately, with its own possession date. Check the one your flat is in.

MahaRERA registration
P51800053558
Status
Registered and active
Builder
Alder Residency Private Limited
Location
Jvlr, Mumbai · 400060
Project type
Residential / Group Housing
Registered on
10 Nov 2023
Completion date at registration
December 2028
Latest completion date
April 2029
MahaRERA's automatic extension
+4 months (force majeure, all eligible projects)
Homes
82
Sold or booked
91%
Towers
1
Complaints on MahaRERA
1
Court cases listed
0
Title report on file
Not found
Builder's other MahaRERA projects
9

Construction progress of Kalpataru Vivant - South Wing C, as filed by the builder

What the builder has reported to MahaRERA, as GharKundli read it in October 2026. GharKundli’s full report compares it with the deadline.

Tower / wingPlinthSlabs (structure)Internal workLifts, fire & electrical
Building No-2 Wing - C100%100%75%5%

Commencement certificate (CC), as filed on MahaRERA

  • Building No-2 Wing - C: covers 26 floors

Want to know when this changes? Kundli Watch sends a free WhatsApp update on Kalpataru Vivant - South Wing C every month.

Kalpataru Vivant - South Wing C: buildings, flats and land, as filed on MahaRERA

TypeCarpet area (sq ft)Units
1 BHK414 – 43582
  • Buildings: Building No-2 Wing - C (27 floors, 82 units)
  • Car parking: 21 covered
  • Land: 305 sq m (about 0.1 acres) · sanctioned built-up 3,760 sq m

The builder’s record and reviews

Kalpataru (a group of 21 linked companies) has 96 projects on MahaRERA since 2017, this one included. Of the 90 GharKundli has checked: 55 finished, 51 within the promised date and 4 needed more time (typically 5 months); 33 still being built, 2 past the promised date (typically 5 months late); 2 lapsed. 385 complaints on MahaRERA across 56 projects.

Read Google reviews of Kalpataru Vivant - South Wing C →Reviews on Google are opinions by Google users; GharKundli doesn’t check them.

Kundli Watch

Kalpataru Vivant - South Wing C: buyers & owners

Free: a WhatsApp update every month on this project, and straight away when anything changes on MahaRERA — a later completion date, new complaints, a red flag. Your number stays private: never shown to other members or the builder.

Be the first to watch this project.

How are you connected to this project?

Bought here? No document needed now. From the builder’s team? Join to answer buyers’ questions; you never see members’ details. You’ll sign in with a one-time code, then come straight back here.

Common questions about Kalpataru Vivant - South Wing C

What is the possession date of Kalpataru Vivant - South Wing C?

According to GharKundli's check of MahaRERA records (updated October 2026), the latest completion date filed on MahaRERA for Kalpataru Vivant - South Wing C in Jvlr, Mumbai is 30 April 2029, including MahaRERA's automatic 4-month extension for all eligible projects.

Is the builder's possession date different from the MahaRERA date for Kalpataru Vivant - South Wing C?

Builders and listing sites often quote an earlier "target" date for handover. The completion date Kalpataru Vivant - South Wing C's builder has filed on MahaRERA, the official one, is 30 April 2029, per GharKundli's check of MahaRERA records. If possession is late, what counts under RERA (Section 18) is the possession date written in your agreement for sale.

What is the RERA number of Kalpataru Vivant - South Wing C?

According to GharKundli's check of MahaRERA records (updated October 2026), the MahaRERA registration number of Kalpataru Vivant - South Wing C in Jvlr, Mumbai is P51800053558.

Is Kalpataru Vivant - South Wing C registered with MahaRERA?

According to GharKundli's check of MahaRERA records (updated October 2026), Kalpataru Vivant - South Wing C is registered as P51800053558 and its status is "Registered and active".

What is the construction status of Kalpataru Vivant - South Wing C?

According to GharKundli's check of MahaRERA records (updated October 2026), Kalpataru Vivant - South Wing C's status on MahaRERA is "Registered and active". As filed by the builder, slab work on Building No-2 Wing - C is 100% done and internal work 75%. GharKundli's full report compares construction progress with the deadline.

Does Kalpataru Vivant - South Wing C have complaints on MahaRERA?

1 complaint was listed on MahaRERA as of October 2026, per GharKundli's weekly check. GharKundli's full report explains each case and how it ended.

Is Kalpataru Vivant - South Wing C safe to buy?

According to GharKundli's check of MahaRERA records (updated October 2026), Kalpataru Vivant - South Wing C is registered on MahaRERA as P51800053558, its completion date has not been moved by the builder and 1 complaint is listed against it. GharKundli doesn't call a project safe or unsafe from these numbers alone: its full report gives a risk & trust score with every point explained.

Does Kalpataru Vivant - South Wing C have other wings or phases?

Yes. MahaRERA lists 3 other registrations of the same project, each with its own possession date: Kalpataru Vivant - South Wing A (P51800045360, possession 31 Mar 2028); Kalpataru Vivant - South Wing B (P51800034531, possession 31 Mar 2028); Kalpataru Vivant - South Wing E (P51800053828, possession 30 Apr 2029). Check that your agreement names the registration of your own wing.

How can I get updates if Kalpataru Vivant - South Wing C's possession date changes?

The latest dates are on Kalpataru Vivant - South Wing C's MahaRERA page (P51800053558). GharKundli's Kundli Watch sends a free WhatsApp update on Kalpataru Vivant - South Wing C every month, and straight away when anything changes on MahaRERA: a later completion date, new complaints or a red flag. Your number is never shown to the builder.

How many floors does Kalpataru Vivant - South Wing C have?

According to GharKundli's check of MahaRERA records (updated October 2026), Kalpataru Vivant - South Wing C has one building filed: Building No-2 Wing - C with 27 floors and 82 units.

What are the flat sizes (carpet area) in Kalpataru Vivant - South Wing C?

According to GharKundli's check of MahaRERA records (updated October 2026), the builder has filed these homes for Kalpataru Vivant - South Wing C: 1 BHK: 414 to 435 sq ft carpet (82 homes). Carpet area is the usable floor area inside the walls, as defined under RERA.

How much parking does Kalpataru Vivant - South Wing C have?

According to GharKundli's check of MahaRERA records (updated October 2026), the builder has filed 21 covered car parking spaces for Kalpataru Vivant - South Wing C.

How big is the land of Kalpataru Vivant - South Wing C?

According to GharKundli's check of MahaRERA records (updated October 2026), Kalpataru Vivant - South Wing C stands on 305 sq m of land (about 0.1 acres), with 3,760 sq m of sanctioned built-up area.

What is the track record of Kalpataru Vivant - South Wing C's builder?

According to GharKundli's check of MahaRERA records (updated October 2026), Kalpataru (a group of 21 linked companies) has 96 projects on MahaRERA since 2017, this one included. Of the 90 GharKundli has checked: 55 finished, 51 within the promised date and 4 needed more time (typically 5 months); 33 still being built, 2 past the promised date (typically 5 months late); 2 lapsed. 385 complaints on MahaRERA across 56 projects. GharKundli's full report covers the builder's record in detail.

Where can I read reviews of Kalpataru Vivant - South Wing C?

Google Maps has reviews of Kalpataru Vivant - South Wing C written by Google users; GharKundli links to them on this page but doesn't check them. For facts rather than opinions: 1 complaint is listed on MahaRERA, and Kundli Watch shows verified owners of the project.

Where is Kalpataru Vivant - South Wing C?

Kalpataru Vivant - South Wing C by Alder Residency Private Limited (Kalpataru) is in Jvlr, Mumbai (pincode 400060), near Jogeshwari East, Jogeshwari West, Seepz, Maharashtra, and is registered on MahaRERA as P51800053558, per GharKundli's check of MahaRERA records.

How many homes are in Kalpataru Vivant - South Wing C?

According to GharKundli's check of MahaRERA records (updated October 2026), Kalpataru Vivant - South Wing C has 82 homes in 1 tower registered on MahaRERA, and 91% of them are sold or booked.

When was Kalpataru Vivant - South Wing C registered on MahaRERA?

According to GharKundli's check of MahaRERA records (updated October 2026), Kalpataru Vivant - South Wing C was registered on MahaRERA on 10 November 2023. GharKundli did not find a title report on the land on file there.

Are there court cases on Kalpataru Vivant - South Wing C?

No court cases are listed for Kalpataru Vivant - South Wing C on MahaRERA, per GharKundli's check of MahaRERA records (updated October 2026).

Who is the builder of Kalpataru Vivant - South Wing C?

According to GharKundli's check of MahaRERA records (updated October 2026), the builder is Alder Residency Private Limited, the company Kalpataru files this project under, which has 9 other projects registered on MahaRERA.

All projects with possession due in 2029 in Mumbai Suburban →

Other projects in Jvlr

All 97 projects in Jogeshwari East (400060) →

Other projects by Alder Residency Private Limited

Data compiled by GharKundli (gharkundli.com) from MahaRERA public records, as of October 2026. Check the project’s MahaRERA page for the latest filings. Not legal advice.