Chopda Aurus
by M/s. B CHOPDA REALTORS · Ghatkopar East, Mumbai 400077Also near Ghatkopar Kirol, Pant Nagar, KurlaRegistered on MahaRERA as “Aurus”
What’s in the report? →Possession date of Chopda Aurus (MahaRERA P51800055507): 31 July 2027. It has 51 homes (1 BHK, 2 BHK and 3 BHK, 461–1059 sq ft carpet), 50% sold or booked. No complaints on MahaRERA. How to check it yourself
Registered on MahaRERA under P51800055507, and currently active. Its completion date is now July 2027, including MahaRERA's automatic 4-month extension for all eligible projects; the builder hasn't asked for more time.
Source: MahaRERA website — records for P51800055507, read and compiled by GharKundli. Facts as filed on MahaRERA, no opinions.
What do you want to know about Chopda Aurus?
Title report MahaRERA par nahi dikh rahi. Kya poochna hai?Tap a question. We’ll answer you on WhatsApp, free.
How the possession date of Chopda Aurus has moved
31 March 2027
Completion date given when the project was registered
31 July 2027
MahaRERA's automatic 4-month extension for all eligible projects, not the builder's request
Source: Chopda Aurus’s extension records on MahaRERA (P51800055507), read by GharKundli in October 2026. The builder’s reasons are quoted as filed. Your own possession date is the one in your agreement for sale.
What builders tell MahaRERA when they’re late: 14,973 applications analysed →GharKundli’s full report on Chopda Aurus
Read from every filing on MahaRERA when you open it
- Risk & trust score, every point explained
- What the title report says about the land
- Each complaint and court case, and how it ended
- Construction pace against the July 2027 deadline
- Agreement clauses weaker than the RERA model
- Escrow audit, loans and the builder's record
- Questions to get answered in writing before you pay
- MahaRERA registration
- P51800055507
- Status
- Registered and active
- Builder
- M/s. B CHOPDA REALTORS
- Location
- Ghatkopar East, Mumbai · 400077
- Project type
- Residential / Group Housing
- Registered on
- 2 Apr 2024
- Completion date at registration
- March 2027
- Latest completion date
- July 2027
- MahaRERA's automatic extension
- +4 months (force majeure, all eligible projects)
- Homes
- 51
- Sold or booked
- 50%
- Towers
- 1
- Complaints on MahaRERA
- 0
- Court cases listed
- 0
- Title report on file
- Not found
Construction progress of Chopda Aurus, as filed by the builder
What the builder has reported to MahaRERA, as GharKundli read it in October 2026. GharKundli’s full report compares it with the deadline.
| Tower / wing | Plinth | Slabs (structure) | Internal work | Lifts, fire & electrical |
|---|---|---|---|---|
| Aurus | 92% | 0% | 0% | 0% |
Want to know when this changes? Kundli Watch sends a free WhatsApp update on Chopda Aurus every 1–2 months.
Chopda Aurus: buildings, flats and land, as filed on MahaRERA
| Type | Carpet area (sq ft) | Units |
|---|---|---|
| 3 BHK | 754 – 1,059 | 25 |
| 2 BHK | 657 – 754 | 23 |
| 1 BHK | 461 – 467 | 3 |
- Buildings: Aurus (17 floors)
- Land: 1,313 sq m (about 0.3 acres) · sanctioned built-up 2,562 sq m
- Land, as filed: 195/178
- Map: the location the builder filed on MahaRERA · Get directions
The builder’s record and reviews
Not enough of this builder’s other MahaRERA projects have reached their promised date to judge yet.
Read Google reviews of Chopda Aurus →Reviews on Google are opinions by Google users; GharKundli doesn’t check them.
Kundli Watch
Chopda Aurus: buyers & owners
Free: a construction progress update on WhatsApp every 1–2 months, and straight away when anything changes on MahaRERA — a later completion date, new complaints, a red flag. Your number stays private: never shown to other members or the builder.
Be the first to watch this project.
How are you connected to this project?
Watching needs only WhatsApp or your number. Bought here? No document needed now. From the builder’s team? Join to answer buyers’ questions; you never see members’ details. Owners and the builder’s team sign in with a one-time code, then come straight back here.
Common questions about Chopda Aurus
What is the possession date of Chopda Aurus?
According to GharKundli's check of MahaRERA records (updated October 2026), the latest completion date filed on MahaRERA for Chopda Aurus in Ghatkopar East, Mumbai is 31 July 2027, including MahaRERA's automatic 4-month extension for all eligible projects.
Is the builder's possession date different from the MahaRERA date for Chopda Aurus?
Builders and listing sites often quote an earlier "target" date for handover. The completion date Chopda Aurus's builder has filed on MahaRERA, the official one, is 31 July 2027, per GharKundli's check of MahaRERA records. If possession is late, what counts under RERA (Section 18) is the possession date written in your agreement for sale.
What is the RERA number of Chopda Aurus?
According to GharKundli's check of MahaRERA records (updated October 2026), the MahaRERA registration number of Chopda Aurus in Ghatkopar East, Mumbai is P51800055507.
Is Chopda Aurus registered with MahaRERA?
According to GharKundli's check of MahaRERA records (updated October 2026), Chopda Aurus is registered as P51800055507 and its status is "Registered and active".
What is the current construction status of Chopda Aurus? How much work is done?
According to GharKundli's check of MahaRERA records (updated October 2026), Chopda Aurus's status on MahaRERA is "Registered and active". As filed by the builder, slab work on Aurus is 0% done and internal work 0%. GharKundli's full report compares construction progress with the deadline.
Does Chopda Aurus have complaints on MahaRERA?
No complaints were listed on MahaRERA as of October 2026, per GharKundli's weekly check.
Is Chopda Aurus safe to buy?
According to GharKundli's check of MahaRERA records (updated October 2026), Chopda Aurus is registered on MahaRERA as P51800055507, its completion date has not been moved by the builder and no complaints are listed against it. GharKundli doesn't call a project safe or unsafe from these numbers alone: its full report gives a risk & trust score with every point explained.
How much GST is payable on a flat in Chopda Aurus?
Chopda Aurus is under construction, so GST applies to a new flat: 5% of the price, with no input tax credit. The lower 1% rate is only for "affordable" homes: carpet area up to 60 sq m (about 646 sq ft) in the Mumbai region, and price up to ₹45 lakh. Some flats in Chopda Aurus are 461 sq ft carpet, small enough for 1% if the price is ₹45 lakh or less. There is no GST on stamp duty or registration, and none once the occupancy certificate is issued.
What is the stamp duty and registration cost for a flat in Chopda Aurus?
For a flat in Chopda Aurus (Mumbai), stamp duty is 6% of the agreement value, or of the ready reckoner value if that's higher, including 1% Metro Cess. A woman buying in her own name pays 5%. Registration is 1% of the value, capped at ₹30,000. On a ₹1 crore flat that's about ₹6 lakh in stamp duty plus ₹30,000 registration. GharKundli's property cost calculator works it out for your price: gharkundli.com/tools/property-cost-calculator
Has Chopda Aurus received its OC? Is it ready to move in?
Not yet. According to GharKundli's check of MahaRERA records (updated October 2026), Chopda Aurus is still under construction, with 31 July 2027 as the latest completion date filed on MahaRERA. A flat is ready to move in only once the occupancy certificate (OC) is issued, after construction is complete.
Is Chopda Aurus a redevelopment or SRA project?
According to GharKundli's check of MahaRERA records (updated October 2026), Chopda Aurus is a redevelopment: 31 of its flats are set aside for existing occupants (rehab), and the rest are for sale. Its planning authority is MCGM, not the Slum Rehabilitation Authority, so it isn't an SRA scheme.
Has Chopda Aurus uploaded its title report on MahaRERA?
According to GharKundli's check of MahaRERA records (updated October 2026), no title report for Chopda Aurus was found on MahaRERA. Builders are expected to upload one; before booking, ask the builder for the advocate's title certificate in writing.
No title report is on MahaRERA for this project. See which documents are missing →
How can I get updates if Chopda Aurus's possession date changes?
The latest dates are on Chopda Aurus's MahaRERA page (P51800055507). GharKundli's Kundli Watch sends a free WhatsApp update on Chopda Aurus every 1–2 months, and straight away when anything changes on MahaRERA: a later completion date, new complaints or a red flag. Your number is never shown to the builder.
How many floors does Chopda Aurus have?
According to GharKundli's check of MahaRERA records (updated October 2026), Chopda Aurus has one building filed: Aurus with 17 floors.
What are the flat sizes (carpet area) in Chopda Aurus?
According to GharKundli's check of MahaRERA records (updated October 2026), the builder has filed these homes for Chopda Aurus: 3 BHK: 754 to 1059 sq ft carpet (25 homes); 2 BHK: 657 to 754 sq ft carpet (23 homes); 1 BHK: 461 to 467 sq ft carpet (3 homes). Carpet area is the usable floor area inside the walls, as defined under RERA.
How big is the land of Chopda Aurus?
According to GharKundli's check of MahaRERA records (updated October 2026), Chopda Aurus stands on 1,313 sq m of land (about 0.3 acres), with 2,562 sq m of sanctioned built-up area.
What are the reviews of Chopda Aurus?
Google Maps has reviews of Chopda Aurus written by Google users; GharKundli links to them on this page but doesn't check them. For facts rather than opinions: no complaints are listed on MahaRERA, and Kundli Watch shows verified owners of the project.
What is the address and pincode of Chopda Aurus?
Chopda Aurus by M/s. B CHOPDA REALTORS is in Ghatkopar East, Mumbai, pincode 400077 (near Ghatkopar Kirol, Pant Nagar, Kurla), Maharashtra, and is registered on MahaRERA as P51800055507, per GharKundli's check of MahaRERA records. Its land is filed as 195/178. GharKundli lists all 228 MahaRERA projects in Ghatkopar East (400077).
How many flats are in Chopda Aurus, and how many are sold?
According to GharKundli's check of MahaRERA records (updated October 2026), Chopda Aurus has 51 homes in 1 tower registered on MahaRERA, and 50% of them are sold or booked.
When was Chopda Aurus registered on MahaRERA?
According to GharKundli's check of MahaRERA records (updated October 2026), Chopda Aurus was registered on MahaRERA on 2 April 2024. GharKundli did not find a title report on the land on file there.
Does Chopda Aurus have any legal issues or court cases?
No court cases are listed for Chopda Aurus on MahaRERA, per GharKundli's check of MahaRERA records (updated October 2026).
Who is the builder / developer of Chopda Aurus?
According to GharKundli's check of MahaRERA records (updated October 2026), the builder is M/s. B CHOPDA REALTORS.
Check it yourself on MahaRERA
- How to check the possession date of Chopda Aurus
- How to find and verify a MahaRERA number
- How to check construction status on MahaRERA
- Occupancy certificate (OC): what to check before possession
- Possession delayed? Work out the interest the builder owes
- How to file a MahaRERA complaint against a builder
- Where MahaRERA complaints are: the data
- Why builders ask MahaRERA for more time: the data
All projects with possession due in 2027 in Mumbai Suburban →
Other projects in Ghatkopar East (400077)
- Aum Laxminarayan
- Subham Bileshwar
- Anand Bhavan - Pristino
- Mannat Tower
- Pant Nagar Shankar Sadan CHS Ltd
- Kailas Nagar
Data compiled by GharKundli (gharkundli.com) from MahaRERA public records, as of October 2026. Check the project’s MahaRERA page for the latest filings. Not legal advice.