Building No.9 - Phase II
by KALINDI ESTATE DEVELOPERS · Motilal Nagar, Mumbai 400104Also near Goregaon West, Oshiwara, Andheri West
What’s in the report? →Possession date of Building No.9 - Phase II (MahaRERA P51800076741): 30 April 2027. It has 52 homes (2 BHK and 3 BHK, 925–1252 sq ft carpet), 0% sold or booked. No complaints on MahaRERA. How to check it yourself
Registered on MahaRERA under P51800076741, and currently active. Its completion date is now April 2027, including MahaRERA's automatic 4-month extension for all eligible projects; the builder hasn't asked for more time.
Source: MahaRERA website — records for P51800076741, read and compiled by GharKundli. Facts as filed on MahaRERA, no opinions.
What do you want to know about Building No.9 - Phase II?
4 court cases MahaRERA par listed. Kya jaanna hai?Tap a question. We’ll answer you on WhatsApp, free.
How the possession date of Building No.9 - Phase II has moved
31 December 2026
Completion date given when the project was registered
30 April 2027
MahaRERA's automatic 4-month extension for all eligible projects, not the builder's request
Source: Building No.9 - Phase II’s extension records on MahaRERA (P51800076741), read by GharKundli in October 2026. The builder’s reasons are quoted as filed. Your own possession date is the one in your agreement for sale.
What builders tell MahaRERA when they’re late: 14,973 applications analysed →GharKundli’s full report on Building No.9 - Phase II
Read from every filing on MahaRERA when you open it
- Risk & trust score, every point explained
- What the title report says about the land
- Each of the 4 court cases, and how it ended
- Construction pace against the April 2027 deadline
- Agreement clauses weaker than the RERA model
- Escrow audit, loans and the builder's record
- Questions to get answered in writing before you pay
- MahaRERA registration
- P51800076741
- Status
- Registered and active
- Builder
- KALINDI ESTATE DEVELOPERS
- Location
- Motilal Nagar, Mumbai · 400104
- Project type
- Others
- Registered on
- 25 Jun 2024
- Completion date at registration
- December 2026
- Latest completion date
- April 2027
- MahaRERA's automatic extension
- +4 months (force majeure, all eligible projects)
- Homes
- 52
- Sold or booked
- 0%
- Towers
- 1
- Complaints on MahaRERA
- 0
- Court cases listed
- 4
- Title report on file
- Not found
Construction progress of Building No.9 - Phase II, as filed by the builder
What the builder has reported to MahaRERA, as GharKundli read it in October 2026. GharKundli’s full report compares it with the deadline.
| Tower / wing | Plinth | Slabs (structure) | Internal work | Lifts, fire & electrical |
|---|---|---|---|---|
| BUILDING NO 9 WING A Wing B | 100% | 70% | 70% | 0% |
Commencement certificate (CC), as filed on MahaRERA
- BUILDING NO 9 WING A Wing B: covers 21 floors
Want to know when this changes? Kundli Watch sends a free WhatsApp update on Building No.9 - Phase II every 1–2 months.
Building No.9 - Phase II: buildings, flats and land, as filed on MahaRERA
| Type | Carpet area (sq ft) | Units |
|---|---|---|
| 3 BHK | 1,222 – 1,252 | 34 |
| 2 BHK | 925 – 927 | 18 |
- Buildings: BUILDING NO 9 WING A Wing B (22 floors, 52 units)
- Land: 6,692 sq m (about 1.7 acres) · sanctioned built-up 14,169 sq m · recreational space 7,961 sq m
- Boundaries filed include: OSHIWARA INDUSTRIAL ESTATE
- Land, as filed: 1A/2
- Map: the location the builder filed on MahaRERA · Get directions
The builder’s record and reviews
Brijesh Satish Dattani has 9 projects on MahaRERA since 2017, this one included. Of the 9 GharKundli has checked: 4 finished, all within the promised date; 2 still being built, none past the promised date yet; 3 lapsed. 3 complaints on MahaRERA across 3 projects.
Read Google reviews of Building No.9 - Phase II →Reviews on Google are opinions by Google users; GharKundli doesn’t check them.
Kundli Watch
Building No.9 - Phase II: buyers & owners
Free: a construction progress update on WhatsApp every 1–2 months, and straight away when anything changes on MahaRERA — a later completion date, new complaints, a red flag. Your number stays private: never shown to other members or the builder.
Be the first to watch this project.
How are you connected to this project?
Watching needs only WhatsApp or your number. Bought here? No document needed now. From the builder’s team? Join to answer buyers’ questions; you never see members’ details. Owners and the builder’s team sign in with a one-time code, then come straight back here.
Common questions about Building No.9 - Phase II
What is the possession date of Building No.9 - Phase II?
According to GharKundli's check of MahaRERA records (updated October 2026), the latest completion date filed on MahaRERA for Building No.9 - Phase II in Motilal Nagar, Mumbai is 30 April 2027, including MahaRERA's automatic 4-month extension for all eligible projects.
Is the builder's possession date different from the MahaRERA date for Building No.9 - Phase II?
Builders and listing sites often quote an earlier "target" date for handover. The completion date Building No.9 - Phase II's builder has filed on MahaRERA, the official one, is 30 April 2027, per GharKundli's check of MahaRERA records. If possession is late, what counts under RERA (Section 18) is the possession date written in your agreement for sale.
What is the RERA number of Building No.9 - Phase II?
According to GharKundli's check of MahaRERA records (updated October 2026), the MahaRERA registration number of Building No.9 - Phase II in Motilal Nagar, Mumbai is P51800076741.
Is Building No.9 - Phase II registered with MahaRERA?
According to GharKundli's check of MahaRERA records (updated October 2026), Building No.9 - Phase II is registered as P51800076741 and its status is "Registered and active".
What is the current construction status of Building No.9 - Phase II? How much work is done?
According to GharKundli's check of MahaRERA records (updated October 2026), Building No.9 - Phase II's status on MahaRERA is "Registered and active". As filed by the builder, slab work on BUILDING NO 9 WING A Wing B is 70% done and internal work 70%. GharKundli's full report compares construction progress with the deadline.
Does Building No.9 - Phase II have complaints on MahaRERA?
No complaints were listed on MahaRERA as of October 2026, per GharKundli's weekly check.
Is Building No.9 - Phase II safe to buy?
According to GharKundli's check of MahaRERA records (updated October 2026), Building No.9 - Phase II is registered on MahaRERA as P51800076741, its completion date has not been moved by the builder and no complaints are listed against it. GharKundli doesn't call a project safe or unsafe from these numbers alone: its full report gives a risk & trust score with every point explained.
How much GST is payable on a flat in Building No.9 - Phase II?
Building No.9 - Phase II is under construction, so GST applies to a new flat: 5% of the price, with no input tax credit. The lower 1% rate is only for "affordable" homes: carpet area up to 60 sq m (about 646 sq ft) in the Mumbai region, and price up to ₹45 lakh. Flats in Building No.9 - Phase II start at 925 sq ft carpet, above that limit, so expect 5%. There is no GST on stamp duty or registration, and none once the occupancy certificate is issued.
What is the stamp duty and registration cost for a flat in Building No.9 - Phase II?
For a flat in Building No.9 - Phase II (Mumbai), stamp duty is 6% of the agreement value, or of the ready reckoner value if that's higher, including 1% Metro Cess. A woman buying in her own name pays 5%. Registration is 1% of the value, capped at ₹30,000. On a ₹1 crore flat that's about ₹6 lakh in stamp duty plus ₹30,000 registration. GharKundli's property cost calculator works it out for your price: gharkundli.com/tools/property-cost-calculator
Has Building No.9 - Phase II received its OC? Is it ready to move in?
Not yet. According to GharKundli's check of MahaRERA records (updated October 2026), Building No.9 - Phase II is still under construction, with 30 April 2027 as the latest completion date filed on MahaRERA. A flat is ready to move in only once the occupancy certificate (OC) is issued, after construction is complete.
Has Building No.9 - Phase II uploaded its title report on MahaRERA?
According to GharKundli's check of MahaRERA records (updated October 2026), no title report for Building No.9 - Phase II was found on MahaRERA. Builders are expected to upload one; before booking, ask the builder for the advocate's title certificate in writing.
No title report is on MahaRERA for this project. See which documents are missing →
How can I get updates if Building No.9 - Phase II's possession date changes?
The latest dates are on Building No.9 - Phase II's MahaRERA page (P51800076741). GharKundli's Kundli Watch sends a free WhatsApp update on Building No.9 - Phase II every 1–2 months, and straight away when anything changes on MahaRERA: a later completion date, new complaints or a red flag. Your number is never shown to the builder.
How many floors does Building No.9 - Phase II have?
According to GharKundli's check of MahaRERA records (updated October 2026), Building No.9 - Phase II has one building filed: BUILDING NO 9 WING A Wing B with 22 floors and 52 units.
What are the flat sizes (carpet area) in Building No.9 - Phase II?
According to GharKundli's check of MahaRERA records (updated October 2026), the builder has filed these homes for Building No.9 - Phase II: 3 BHK: 1222 to 1252 sq ft carpet (34 homes); 2 BHK: 925 to 927 sq ft carpet (18 homes). Carpet area is the usable floor area inside the walls, as defined under RERA.
How big is the land of Building No.9 - Phase II?
According to GharKundli's check of MahaRERA records (updated October 2026), Building No.9 - Phase II stands on 6,692 sq m of land (about 1.7 acres), with 14,169 sq m of sanctioned built-up area and 7,961 sq m of recreational open space.
What is the track record of Building No.9 - Phase II's builder?
According to GharKundli's check of MahaRERA records (updated October 2026), Brijesh Satish Dattani has 9 projects on MahaRERA since 2017, this one included. Of the 9 GharKundli has checked: 4 finished, all within the promised date; 2 still being built, none past the promised date yet; 3 lapsed. 3 complaints on MahaRERA across 3 projects. GharKundli's full report covers the builder's record in detail.
What are the reviews of Building No.9 - Phase II?
Google Maps has reviews of Building No.9 - Phase II written by Google users; GharKundli links to them on this page but doesn't check them. For facts rather than opinions: no complaints are listed on MahaRERA, and Kundli Watch shows verified owners of the project.
What is the address and pincode of Building No.9 - Phase II?
Building No.9 - Phase II by KALINDI ESTATE DEVELOPERS is in Motilal Nagar, Mumbai, pincode 400104 (near Goregaon West, Oshiwara, Andheri West), Maharashtra, and is registered on MahaRERA as P51800076741, per GharKundli's check of MahaRERA records. Its boundaries filed there include OSHIWARA INDUSTRIAL ESTATE. Its land is filed as 1A/2. GharKundli lists all 183 MahaRERA projects in Goregaon West (400104).
How many flats are in Building No.9 - Phase II, and how many are sold?
According to GharKundli's check of MahaRERA records (updated October 2026), Building No.9 - Phase II has 52 homes in 1 tower registered on MahaRERA, and 0% of them are sold or booked.
When was Building No.9 - Phase II registered on MahaRERA?
According to GharKundli's check of MahaRERA records (updated October 2026), Building No.9 - Phase II was registered on MahaRERA on 25 June 2024. GharKundli did not find a title report on the land on file there.
Does Building No.9 - Phase II have any legal issues or court cases?
4 court cases are listed for Building No.9 - Phase II on MahaRERA, per GharKundli's check of MahaRERA records (updated October 2026). GharKundli's full report explains each case and how it ended.
A court case can stall a project or tie up the land. See what each case is about →
Who is the builder / developer of Building No.9 - Phase II?
According to GharKundli's check of MahaRERA records (updated October 2026), the builder is KALINDI ESTATE DEVELOPERS.
Check it yourself on MahaRERA
- How to check the possession date of Building No.9 - Phase II
- How to find and verify a MahaRERA number
- How to check construction status on MahaRERA
- Occupancy certificate (OC): what to check before possession
- Possession delayed? Work out the interest the builder owes
- How to file a MahaRERA complaint against a builder
- Where MahaRERA complaints are: the data
- Why builders ask MahaRERA for more time: the data
All projects with possession due in 2027 in Mumbai Suburban →
Other projects in Goregaon West (400104)
- DRM Sheetal Landmark
- Sunteck Pinnacle 1
- io Residences by PCPL
- io Tower by PCPL
- Ekta Tripolis Phase II
- Apricus
- Paras Residency
- Bali Ananda
Data compiled by GharKundli (gharkundli.com) from MahaRERA public records, as of October 2026. Check the project’s MahaRERA page for the latest filings. Not legal advice.