KABRA TIARA - Redevelopment of Dindoshi Darshan CHSL
by KABRA AND ASSOCIATES · Dindoshi, Malad East, Mumbai
Possession date of KABRA TIARA - Redevelopment of Dindoshi Darshan CHSL: 30 April 2028. This is the latest completion date the builder has filed on MahaRERA. How to check it yourself
Registered on MahaRERA under P51800054840, and currently active. Its completion date is now April 2028, including MahaRERA's automatic 4-month extension for all eligible projects; the builder hasn't asked for more time. 1 complaint is listed against it on MahaRERA.
Source: GharKundli’s check of MahaRERA records, October 2026.
What do you want to know about KABRA TIARA - Redevelopment of Dindoshi Darshan CHSL?
GharKundli’s full report on KABRA TIARA - Redevelopment of Dindoshi Darshan CHSL
Read from every filing on MahaRERA when you open it
- Risk & trust score, every point explained
- What the title report says about the land
- Each of the 1 complaint, and how it ended
- Construction pace against the April 2028 deadline
- Agreement clauses weaker than the RERA model
- Escrow audit, loans and the builder's record
- Questions to get answered in writing before you pay
- MahaRERA registration
- P51800054840
- Status
- Registered and active
- Builder
- KABRA AND ASSOCIATES
- Location
- Dindoshi, Malad East, Mumbai · 400077
- Project type
- Residential / Group Housing
- Registered on
- 15 Feb 2024
- Completion date at registration
- December 2027
- Latest completion date
- April 2028
- MahaRERA's automatic extension
- +4 months (force majeure, all eligible projects)
- Homes
- 127
- Sold or booked
- 91%
- Towers
- 1
- Complaints on MahaRERA
- 1
- Court cases listed
- 0
- Title report on file
- Not found
- Builder's other MahaRERA projects
- 7
Construction progress of KABRA TIARA - Redevelopment of Dindoshi Darshan CHSL, as filed by the builder
What the builder has reported to MahaRERA, as GharKundli read it in October 2026. GharKundli’s full report compares it with the deadline.
| Tower / wing | Plinth | Slabs (structure) | Internal work | Lifts, fire & electrical |
|---|---|---|---|---|
| Dindoshi Darshan Co-operative Housing Society Ltd | 100% | 100% | 87% | 40% |
Commencement certificate (CC), as filed on MahaRERA
- Dindoshi Darshan Co-operative Housing Society Ltd: covers upto top of 22nd floor
Want to know when this changes? Kundli Watch sends a free WhatsApp update on KABRA TIARA - Redevelopment of Dindoshi Darshan CHSL every month.
KABRA TIARA - Redevelopment of Dindoshi Darshan CHSL: buildings, flats and land, as filed on MahaRERA
| Type | Carpet area (sq ft) | Units |
|---|---|---|
| 3 BHK | 900 – 981 | 63 |
| 2 BHK | 646 – 679 | 63 |
| 4 BHK | 1,088 | 1 |
- Buildings: Dindoshi Darshan Co-operative Housing Society Ltd (23 floors, 127 units)
- Car parking: 154 covered
- Land: 1,416 sq m (about 0.3 acres) · sanctioned built-up 10,637 sq m
The builder’s record and reviews
Kabra AND Associates (a group of 6 linked companies) has 18 projects on MahaRERA since 2017, this one included. Of the 18 GharKundli has checked: 11 finished, 10 within the promised date and 1 needed more time (typically 12 months); 5 still being built, none past the promised date yet; 2 lapsed. 15 complaints on MahaRERA across 7 projects.
Read Google reviews of KABRA TIARA - Redevelopment of Dindoshi Darshan CHSL →Reviews on Google are opinions by Google users; GharKundli doesn’t check them.
Kundli Watch
KABRA TIARA - Redevelopment of Dindoshi Darshan CHSL: buyers & owners
Free: a WhatsApp update every month on this project, and straight away when anything changes on MahaRERA — a later completion date, new complaints, a red flag. Your number stays private: never shown to other members or the builder.
Be the first to watch this project.
How are you connected to this project?
Bought here? No document needed now. From the builder’s team? Join to answer buyers’ questions; you never see members’ details. You’ll sign in with a one-time code, then come straight back here.
Common questions about KABRA TIARA - Redevelopment of Dindoshi Darshan CHSL
What is the possession date of KABRA TIARA - Redevelopment of Dindoshi Darshan CHSL?
According to GharKundli's check of MahaRERA records (updated October 2026), the latest completion date filed on MahaRERA for KABRA TIARA - Redevelopment of Dindoshi Darshan CHSL in Dindoshi, Malad East, Mumbai is 30 April 2028, including MahaRERA's automatic 4-month extension for all eligible projects.
Is the builder's possession date different from the MahaRERA date for KABRA TIARA - Redevelopment of Dindoshi Darshan CHSL?
Builders and listing sites often quote an earlier "target" date for handover. The completion date KABRA TIARA - Redevelopment of Dindoshi Darshan CHSL's builder has filed on MahaRERA, the official one, is 30 April 2028, per GharKundli's check of MahaRERA records. If possession is late, what counts under RERA (Section 18) is the possession date written in your agreement for sale.
What is the RERA number of KABRA TIARA - Redevelopment of Dindoshi Darshan CHSL?
According to GharKundli's check of MahaRERA records (updated October 2026), the MahaRERA registration number of KABRA TIARA - Redevelopment of Dindoshi Darshan CHSL in Dindoshi, Malad East, Mumbai is P51800054840.
Is KABRA TIARA - Redevelopment of Dindoshi Darshan CHSL registered with MahaRERA?
According to GharKundli's check of MahaRERA records (updated October 2026), KABRA TIARA - Redevelopment of Dindoshi Darshan CHSL is registered as P51800054840 and its status is "Registered and active".
What is the construction status of KABRA TIARA - Redevelopment of Dindoshi Darshan CHSL?
According to GharKundli's check of MahaRERA records (updated October 2026), KABRA TIARA - Redevelopment of Dindoshi Darshan CHSL's status on MahaRERA is "Registered and active". As filed by the builder, slab work on Dindoshi Darshan Co-operative Housing Society Ltd is 100% done and internal work 87%. GharKundli's full report compares construction progress with the deadline.
Does KABRA TIARA - Redevelopment of Dindoshi Darshan CHSL have complaints on MahaRERA?
1 complaint was listed on MahaRERA as of October 2026, per GharKundli's weekly check. GharKundli's full report explains each case and how it ended.
Is KABRA TIARA - Redevelopment of Dindoshi Darshan CHSL safe to buy?
According to GharKundli's check of MahaRERA records (updated October 2026), KABRA TIARA - Redevelopment of Dindoshi Darshan CHSL is registered on MahaRERA as P51800054840, its completion date has not been moved by the builder and 1 complaint is listed against it. GharKundli doesn't call a project safe or unsafe from these numbers alone: its full report gives a risk & trust score with every point explained.
How can I get updates if KABRA TIARA - Redevelopment of Dindoshi Darshan CHSL's possession date changes?
The latest dates are on KABRA TIARA - Redevelopment of Dindoshi Darshan CHSL's MahaRERA page (P51800054840). GharKundli's Kundli Watch sends a free WhatsApp update on KABRA TIARA - Redevelopment of Dindoshi Darshan CHSL every month, and straight away when anything changes on MahaRERA: a later completion date, new complaints or a red flag. Your number is never shown to the builder.
How many floors does KABRA TIARA - Redevelopment of Dindoshi Darshan CHSL have?
According to GharKundli's check of MahaRERA records (updated October 2026), KABRA TIARA - Redevelopment of Dindoshi Darshan CHSL has one building filed: Dindoshi Darshan Co-operative Housing Society Ltd with 23 floors and 127 units.
What are the flat sizes (carpet area) in KABRA TIARA - Redevelopment of Dindoshi Darshan CHSL?
According to GharKundli's check of MahaRERA records (updated October 2026), the builder has filed these homes for KABRA TIARA - Redevelopment of Dindoshi Darshan CHSL: 3 BHK: 900 to 981 sq ft carpet (63 homes); 2 BHK: 646 to 679 sq ft carpet (63 homes); 4 BHK: 1088 sq ft carpet (1 homes). Carpet area is the usable floor area inside the walls, as defined under RERA.
How much parking does KABRA TIARA - Redevelopment of Dindoshi Darshan CHSL have?
According to GharKundli's check of MahaRERA records (updated October 2026), the builder has filed 154 covered car parking spaces for KABRA TIARA - Redevelopment of Dindoshi Darshan CHSL.
How big is the land of KABRA TIARA - Redevelopment of Dindoshi Darshan CHSL?
According to GharKundli's check of MahaRERA records (updated October 2026), KABRA TIARA - Redevelopment of Dindoshi Darshan CHSL stands on 1,416 sq m of land (about 0.3 acres), with 10,637 sq m of sanctioned built-up area.
What is the track record of KABRA TIARA - Redevelopment of Dindoshi Darshan CHSL's builder?
According to GharKundli's check of MahaRERA records (updated October 2026), Kabra AND Associates (a group of 6 linked companies) has 18 projects on MahaRERA since 2017, this one included. Of the 18 GharKundli has checked: 11 finished, 10 within the promised date and 1 needed more time (typically 12 months); 5 still being built, none past the promised date yet; 2 lapsed. 15 complaints on MahaRERA across 7 projects. GharKundli's full report covers the builder's record in detail.
Where can I read reviews of KABRA TIARA - Redevelopment of Dindoshi Darshan CHSL?
Google Maps has reviews of KABRA TIARA - Redevelopment of Dindoshi Darshan CHSL written by Google users; GharKundli links to them on this page but doesn't check them. For facts rather than opinions: 1 complaint is listed on MahaRERA, and Kundli Watch shows verified owners of the project.
Where is KABRA TIARA - Redevelopment of Dindoshi Darshan CHSL?
KABRA TIARA - Redevelopment of Dindoshi Darshan CHSL by KABRA AND ASSOCIATES is in Dindoshi, Malad East, Mumbai (pincode 400077), Maharashtra, and is registered on MahaRERA as P51800054840, per GharKundli's check of MahaRERA records.
How many homes are in KABRA TIARA - Redevelopment of Dindoshi Darshan CHSL?
According to GharKundli's check of MahaRERA records (updated October 2026), KABRA TIARA - Redevelopment of Dindoshi Darshan CHSL has 127 homes in 1 tower registered on MahaRERA, and 91% of them are sold or booked.
When was KABRA TIARA - Redevelopment of Dindoshi Darshan CHSL registered on MahaRERA?
According to GharKundli's check of MahaRERA records (updated October 2026), KABRA TIARA - Redevelopment of Dindoshi Darshan CHSL was registered on MahaRERA on 15 February 2024. GharKundli did not find a title report on the land on file there.
Are there court cases on KABRA TIARA - Redevelopment of Dindoshi Darshan CHSL?
No court cases are listed for KABRA TIARA - Redevelopment of Dindoshi Darshan CHSL on MahaRERA, per GharKundli's check of MahaRERA records (updated October 2026).
Who is the builder of KABRA TIARA - Redevelopment of Dindoshi Darshan CHSL?
According to GharKundli's check of MahaRERA records (updated October 2026), the builder is KABRA AND ASSOCIATES, which has 7 other projects registered on MahaRERA.
Check it yourself on MahaRERA
- How to check the possession date of KABRA TIARA - Redevelopment of Dindoshi Darshan CHSL
- How to find and verify a MahaRERA number
- How to check construction status on MahaRERA
- Occupancy certificate (OC): what to check before possession
- Possession delayed? Work out the interest the builder owes
- How to file a MahaRERA complaint against a builder
- Where MahaRERA complaints are: the data
- Why builders ask MahaRERA for more time: the data
All projects with possession due in 2028 in Mumbai Suburban →
All projects in Ghatkopar East (400077) →
Data compiled by GharKundli (gharkundli.com) from MahaRERA public records, as of October 2026. Check the project’s MahaRERA page for the latest filings. Not legal advice.