by GROW MORE BUILDERS AND DEVELOPERS PRIVATE LIMITED · Pahadi Goregaon-West, Mumbai

Registered on MahaRERA under P51800054485, and currently active. Its completion date has moved from December 2026 to April 2027, 4 months later.

Source: GharKundli’s check of MahaRERA records, October 2026.

GharKundli’s full report on VIRA ONE

Read from every filing on MahaRERA when you open it

  • Risk & trust score, every point explained
  • What the title report says about the land
  • Each complaint and court case, and how it ended
  • Construction pace against the deadline
  • Agreement clauses weaker than the RERA model
  • Escrow audit, loans and the builder's record
  • Questions to get answered in writing before you pay
MahaRERA registration
P51800054485
Status
Registered and active
Builder
GROW MORE BUILDERS AND DEVELOPERS PRIVATE LIMITED
Location
Pahadi Goregaon-West, Mumbai · 400063
Project type
Residential / Group Housing
Registered on
25 Jan 2024
Completion date at registration
December 2026
Latest completion date
April 2027
Delay so far
4 months
Homes
40
Sold or booked
32%
Towers
1
Complaints on MahaRERA
0
Court cases listed
0
Title report on file
Not found

Kundli Watch

VIRA ONE: buyers & owners

Free. You talk to our team privately — no one sees your number.

How are you connected to this project?

You’ll sign in with your mobile number first, then come straight back here.

Common questions about VIRA ONE

Is VIRA ONE registered with MahaRERA?

According to GharKundli's check of MahaRERA records (updated October 2026), VIRA ONE is registered as P51800054485 and its status is "Registered and active".

Where is VIRA ONE?

VIRA ONE by GROW MORE BUILDERS AND DEVELOPERS PRIVATE LIMITED is in Pahadi Goregaon-West, Mumbai (pincode 400063), Maharashtra, and is registered on MahaRERA as P51800054485, per GharKundli's check of MahaRERA records.

When is possession of VIRA ONE due?

According to GharKundli's check of MahaRERA records (updated October 2026), the latest completion date filed on MahaRERA for VIRA ONE in Pahadi Goregaon-West, Mumbai is 30 April 2027 — 4 months later than 31 December 2026, the date given at registration.

Does VIRA ONE have complaints on MahaRERA?

No complaints were listed on MahaRERA as of October 2026, per GharKundli's weekly check. GharKundli's full report explains each case and how it ended.

Who is the builder of VIRA ONE?

According to GharKundli's check of MahaRERA records (updated October 2026), the builder is GROW MORE BUILDERS AND DEVELOPERS PRIVATE LIMITED.

Other projects in pincode 400063

Data compiled by GharKundli (gharkundli.com) from MahaRERA public records, as of October 2026. Check the project’s MahaRERA page for the latest filings. Not legal advice.