SEJAL SQUARE
by ALCHEMI DEVELOPERS PRIVATE LIMITED · Malad (E), Goregaon East, MumbaiAlso near Malad East, Aareymilk Colony
Possession date of SEJAL SQUARE: 30 April 2030. This is the latest completion date the builder has filed on MahaRERA. How to check it yourself
Registered on MahaRERA under P51800056052, and currently active. Its completion date is now April 2030, including MahaRERA's automatic 4-month extension for all eligible projects; the builder hasn't asked for more time.
Source: GharKundli’s check of MahaRERA records, October 2026.
What do you want to know about SEJAL SQUARE?
How the possession date of SEJAL SQUARE has moved
31 December 2029
Completion date given when the project was registered
30 April 2030
MahaRERA's automatic 4-month extension for all eligible projects, not the builder's request
Source: SEJAL SQUARE’s extension records on MahaRERA (P51800056052), read by GharKundli in October 2026. The builder’s reasons are quoted as filed. Your own possession date is the one in your agreement for sale.
What builders tell MahaRERA when they’re late: 14,973 applications analysed →GharKundli’s full report on SEJAL SQUARE
Read from every filing on MahaRERA when you open it
- Risk & trust score, every point explained
- What the title report says about the land
- Each of the 8 court cases, and how it ended
- Construction pace against the April 2030 deadline
- Agreement clauses weaker than the RERA model
- Escrow audit, loans and the builder's record
- Questions to get answered in writing before you pay
- MahaRERA registration
- P51800056052
- Status
- Registered and active
- Builder
- ALCHEMI DEVELOPERS PRIVATE LIMITED
- Location
- Malad (E), Goregaon East, Mumbai · 400063
- Project type
- Commercial
- Registered on
- 10 May 2024
- Completion date at registration
- December 2029
- Latest completion date
- April 2030
- MahaRERA's automatic extension
- +4 months (force majeure, all eligible projects)
- Homes
- 0
- Sold or booked
- 78%
- Towers
- 1
- Complaints on MahaRERA
- 0
- Court cases listed
- 8
- Title report on file
- Not found
- Builder's other MahaRERA projects
- 3
Construction progress of SEJAL SQUARE, as filed by the builder
What the builder has reported to MahaRERA, as GharKundli read it in October 2026. GharKundli’s full report compares it with the deadline.
| Tower / wing | Plinth | Slabs (structure) | Internal work | Lifts, fire & electrical |
|---|---|---|---|---|
| Wing D and Wing E | 0% | 0% | 0% | 0% |
Commencement certificate (CC), as filed on MahaRERA
- Wing D and Wing E: covers 36 (3 Basement + Ground + Upper Ground + 31 Upper Floors)
Want to know when this changes? Kundli Watch sends a free WhatsApp update on SEJAL SQUARE every month.
SEJAL SQUARE: buildings, flats and land, as filed on MahaRERA
| Type | Carpet area (sq ft) | Units |
|---|---|---|
| Office Space | 482 – 11,910 | 264 |
| Shops | 319 – 8,611 | 32 |
- Buildings: Wing D and Wing E (37 floors, 296 units)
- Land: 3,201 sq m (about 0.8 acres) · sanctioned built-up 44,301 sq m
- Map: the location the builder filed on MahaRERA
The builder’s record and reviews
Sejal Shakti Realtors (a group of 4 linked companies) has 11 projects on MahaRERA since 2017, this one included. Of the 11 GharKundli has checked: 1 finished, all within the promised date; 9 still being built, none past the promised date yet; 1 lapsed. 44 complaints on MahaRERA across 6 projects.
Read Google reviews of SEJAL SQUARE →Reviews on Google are opinions by Google users; GharKundli doesn’t check them.
Kundli Watch
SEJAL SQUARE: buyers & owners
Free: a WhatsApp update every month on this project, and straight away when anything changes on MahaRERA — a later completion date, new complaints, a red flag. Your number stays private: never shown to other members or the builder.
Be the first to watch this project.
How are you connected to this project?
Bought here? No document needed now. From the builder’s team? Join to answer buyers’ questions; you never see members’ details. You’ll sign in with a one-time code, then come straight back here.
Common questions about SEJAL SQUARE
What is the possession date of SEJAL SQUARE?
According to GharKundli's check of MahaRERA records (updated October 2026), the latest completion date filed on MahaRERA for SEJAL SQUARE in Malad (E), Goregaon East, Mumbai is 30 April 2030, including MahaRERA's automatic 4-month extension for all eligible projects.
Is the builder's possession date different from the MahaRERA date for SEJAL SQUARE?
Builders and listing sites often quote an earlier "target" date for handover. The completion date SEJAL SQUARE's builder has filed on MahaRERA, the official one, is 30 April 2030, per GharKundli's check of MahaRERA records. If possession is late, what counts under RERA (Section 18) is the possession date written in your agreement for sale.
What is the RERA number of SEJAL SQUARE?
According to GharKundli's check of MahaRERA records (updated October 2026), the MahaRERA registration number of SEJAL SQUARE in Malad (E), Goregaon East, Mumbai is P51800056052.
Is SEJAL SQUARE registered with MahaRERA?
According to GharKundli's check of MahaRERA records (updated October 2026), SEJAL SQUARE is registered as P51800056052 and its status is "Registered and active".
What is the construction status of SEJAL SQUARE?
According to GharKundli's check of MahaRERA records (updated October 2026), SEJAL SQUARE's status on MahaRERA is "Registered and active". As filed by the builder, slab work on Wing D and Wing E is 0% done and internal work 0%. GharKundli's full report compares construction progress with the deadline.
Does SEJAL SQUARE have complaints on MahaRERA?
No complaints were listed on MahaRERA as of October 2026, per GharKundli's weekly check.
Is SEJAL SQUARE safe to buy?
According to GharKundli's check of MahaRERA records (updated October 2026), SEJAL SQUARE is registered on MahaRERA as P51800056052, its completion date has not been moved by the builder and no complaints are listed against it. GharKundli doesn't call a project safe or unsafe from these numbers alone: its full report gives a risk & trust score with every point explained.
How can I get updates if SEJAL SQUARE's possession date changes?
The latest dates are on SEJAL SQUARE's MahaRERA page (P51800056052). GharKundli's Kundli Watch sends a free WhatsApp update on SEJAL SQUARE every month, and straight away when anything changes on MahaRERA: a later completion date, new complaints or a red flag. Your number is never shown to the builder.
How many floors does SEJAL SQUARE have?
According to GharKundli's check of MahaRERA records (updated October 2026), SEJAL SQUARE has one building filed: Wing D and Wing E with 37 floors and 296 units.
How big is the land of SEJAL SQUARE?
According to GharKundli's check of MahaRERA records (updated October 2026), SEJAL SQUARE stands on 3,201 sq m of land (about 0.8 acres), with 44,301 sq m of sanctioned built-up area.
What is the track record of SEJAL SQUARE's builder?
According to GharKundli's check of MahaRERA records (updated October 2026), Sejal Shakti Realtors (a group of 4 linked companies) has 11 projects on MahaRERA since 2017, this one included. Of the 11 GharKundli has checked: 1 finished, all within the promised date; 9 still being built, none past the promised date yet; 1 lapsed. 44 complaints on MahaRERA across 6 projects. GharKundli's full report covers the builder's record in detail.
Where can I read reviews of SEJAL SQUARE?
Google Maps has reviews of SEJAL SQUARE written by Google users; GharKundli links to them on this page but doesn't check them. For facts rather than opinions: no complaints are listed on MahaRERA, and Kundli Watch shows verified owners of the project.
Where is SEJAL SQUARE?
SEJAL SQUARE by ALCHEMI DEVELOPERS PRIVATE LIMITED is in Malad (E), Goregaon East, Mumbai (pincode 400063), near Malad East, Aareymilk Colony, Maharashtra, and is registered on MahaRERA as P51800056052, per GharKundli's check of MahaRERA records.
How many homes are in SEJAL SQUARE?
According to GharKundli's check of MahaRERA records (updated October 2026), SEJAL SQUARE has 0 homes in 1 tower registered on MahaRERA, and 78% of them are sold or booked.
When was SEJAL SQUARE registered on MahaRERA?
According to GharKundli's check of MahaRERA records (updated October 2026), SEJAL SQUARE was registered on MahaRERA on 10 May 2024. GharKundli did not find a title report on the land on file there.
Are there court cases on SEJAL SQUARE?
8 court cases are listed for SEJAL SQUARE on MahaRERA, per GharKundli's check of MahaRERA records (updated October 2026). GharKundli's full report explains each case and how it ended.
Who is the builder of SEJAL SQUARE?
According to GharKundli's check of MahaRERA records (updated October 2026), the builder is ALCHEMI DEVELOPERS PRIVATE LIMITED, which has 3 other projects registered on MahaRERA.
Check it yourself on MahaRERA
- How to check the possession date of SEJAL SQUARE
- How to find and verify a MahaRERA number
- How to check construction status on MahaRERA
- Occupancy certificate (OC): what to check before possession
- Possession delayed? Work out the interest the builder owes
- How to file a MahaRERA complaint against a builder
- Where MahaRERA complaints are: the data
- Why builders ask MahaRERA for more time: the data
All projects with possession due in 2030 in Mumbai Suburban →
Other projects in pincode 400063
- ASTORIA TOWER B
- AVANT HILLWAY
- AVANT HILLWAY
- Satellite Elegance
- 104 EAST
- BLA BUSINESS PARK
- S-CITY-R2
- Sheetal Sangam
Other projects by ALCHEMI DEVELOPERS PRIVATE LIMITED
Data compiled by GharKundli (gharkundli.com) from MahaRERA public records, as of October 2026. Check the project’s MahaRERA page for the latest filings. Not legal advice.