AVANT HILLWAY

by RAGHVENDRA CONSTRUCTION COMPANY PVT LTD (Avant) · M, MumbaiAlso near Goregaon East, Goregaon West, Pahadi Goregaon

Possession date of AVANT HILLWAY: 30 April 2027, moved from 30 December 2024 (24 months later). This is the latest completion date the builder has filed on MahaRERA. How to check it yourself

Registered on MahaRERA under P51800011215, and currently active. Its completion date has moved from December 2024 to April 2027: 24 months at the builder's request, plus MahaRERA's automatic 4-month extension for all eligible projects.

Source: GharKundli’s check of MahaRERA records, October 2026.

What do you want to know about AVANT HILLWAY?

Ask us on WhatsAppNo login needed. A real person replies.

How the possession date of AVANT HILLWAY has moved

  1. 30 December 2024

    Completion date given when the project was registered

  2. 31 December 2025

    Extended at the builder's request (MahaRERA application EXT51800027716)

    Reason the builder gave MahaRERA: “The project is delayed due to few approvals from Concerned Authorities as it is larger land construction.”
  3. 31 December 2026

    Extended at the builder's request (MahaRERA application EA13012619426)

    Reason the builder gave MahaRERA: “Ongoing MOEF Issue”
  4. 30 April 2027

    MahaRERA's automatic 4-month extension for all eligible projects, not the builder's request

Source: AVANT HILLWAY’s extension records on MahaRERA (P51800011215), read by GharKundli in October 2026. The builder’s reasons are quoted as filed. Your own possession date is the one in your agreement for sale.

What builders tell MahaRERA when they’re late: 14,973 applications analysed →

GharKundli’s full report on AVANT HILLWAY

Read from every filing on MahaRERA when you open it

  • Risk & trust score, every point explained
  • What the title report says about the land
  • Each complaint and court case, and how it ended
  • Construction pace against the April 2027 deadline
  • Agreement clauses weaker than the RERA model
  • Escrow audit, loans and the builder's record
  • Questions to get answered in writing before you pay

Other wings and phases of this project

Each is registered on MahaRERA separately, with its own possession date. Check the one your flat is in.

MahaRERA registration
P51800011215
Status
Registered and active
Builder
RAGHVENDRA CONSTRUCTION COMPANY PVT LTD
Location
M, Mumbai · 400063
Project type
Residential / Group Housing
Registered on
31 Aug 2017
Completion date at registration
December 2024
Latest completion date
April 2027
Delay so far
24 months
MahaRERA's automatic extension
+4 months (force majeure, all eligible projects)
Homes
40
Sold or booked
88%
Towers
1
Complaints on MahaRERA
0
Court cases listed
0
Title report on file
Not found
Builder's other MahaRERA projects
2

Construction progress of AVANT HILLWAY, as filed by the builder

What the builder has reported to MahaRERA, as GharKundli read it in October 2026. GharKundli’s full report compares it with the deadline.

Tower / wingPlinthSlabs (structure)Internal workLifts, fire & electrical
SUPREME D Sale Wing100%100%100%100%

Commencement certificate (CC), as filed on MahaRERA

  • SUPREME D Sale Wing: covers 23 floors

Want to know when this changes? Kundli Watch sends a free WhatsApp update on AVANT HILLWAY every month.

AVANT HILLWAY: buildings, flats and land, as filed on MahaRERA

TypeCarpet area (sq ft)Units
2 BHK618 – 85337
1 BHK346 – 4002
3 BHK9001

The builder’s record and reviews

Avant Heritage III Realty (a group of 4 linked companies) has 6 projects on MahaRERA since 2017, this one included. Of the 6 GharKundli has checked: 6 still being built, 4 past the promised date (typically 6 months late). 22 complaints on MahaRERA across 3 projects.

Read Google reviews of AVANT HILLWAY →Reviews on Google are opinions by Google users; GharKundli doesn’t check them.

Kundli Watch

AVANT HILLWAY: buyers & owners

Free: a WhatsApp update every month on this project, and straight away when anything changes on MahaRERA — a later completion date, new complaints, a red flag. Your number stays private: never shown to other members or the builder.

Be the first to watch this project.

How are you connected to this project?

Bought here? No document needed now. From the builder’s team? Join to answer buyers’ questions; you never see members’ details. You’ll sign in with a one-time code, then come straight back here.

Common questions about AVANT HILLWAY

What is the possession date of AVANT HILLWAY?

According to GharKundli's check of MahaRERA records (updated October 2026), the latest completion date filed on MahaRERA for AVANT HILLWAY in M, Mumbai is 30 April 2027 — 24 months later than 30 December 2024, the date given at registration, plus MahaRERA's automatic 4-month extension for all eligible projects.

Is the builder's possession date different from the MahaRERA date for AVANT HILLWAY?

Builders and listing sites often quote an earlier "target" date for handover. The completion date AVANT HILLWAY's builder has filed on MahaRERA, the official one, is 30 April 2027, already 24 months later than the 30 December 2024 given at registration, per GharKundli's check of MahaRERA records. If possession is late, what counts under RERA (Section 18) is the possession date written in your agreement for sale.

Why was the possession date of AVANT HILLWAY extended?

According to GharKundli's check of MahaRERA records (updated October 2026), AVANT HILLWAY's builder applied to MahaRERA to extend the completion date 2 times: to 31 December 2025, giving the reason "The project is delayed due to few approvals from Concerned Authorities as it is larger land construction."; to 31 December 2026, giving the reason "Ongoing MOEF Issue". MahaRERA also added its automatic 4-month extension for all eligible projects.

What is the RERA number of AVANT HILLWAY?

According to GharKundli's check of MahaRERA records (updated October 2026), the MahaRERA registration number of AVANT HILLWAY in M, Mumbai is P51800011215.

Is AVANT HILLWAY registered with MahaRERA?

According to GharKundli's check of MahaRERA records (updated October 2026), AVANT HILLWAY is registered as P51800011215 and its status is "Registered and active".

What is the construction status of AVANT HILLWAY?

According to GharKundli's check of MahaRERA records (updated October 2026), AVANT HILLWAY's status on MahaRERA is "Registered and active". As filed by the builder, slab work on SUPREME D Sale Wing is 100% done and internal work 100%. GharKundli's full report compares construction progress with the deadline.

Does AVANT HILLWAY have complaints on MahaRERA?

No complaints were listed on MahaRERA as of October 2026, per GharKundli's weekly check.

Is AVANT HILLWAY safe to buy?

According to GharKundli's check of MahaRERA records (updated October 2026), AVANT HILLWAY is registered on MahaRERA as P51800011215, its completion date has moved 24 months since registration and no complaints are listed against it. GharKundli doesn't call a project safe or unsafe from these numbers alone: its full report gives a risk & trust score with every point explained.

Does AVANT HILLWAY have other wings or phases?

Yes. MahaRERA lists 1 other registration of the same project, each with its own possession date: AVANT HILLWAY (P51800010785, possession 30 Apr 2027). Check that your agreement names the registration of your own wing.

How can I get updates if AVANT HILLWAY's possession date changes?

The latest dates are on AVANT HILLWAY's MahaRERA page (P51800011215). GharKundli's Kundli Watch sends a free WhatsApp update on AVANT HILLWAY every month, and straight away when anything changes on MahaRERA: a later completion date, new complaints or a red flag. Your number is never shown to the builder.

How many floors does AVANT HILLWAY have?

According to GharKundli's check of MahaRERA records (updated October 2026), AVANT HILLWAY has one building filed: SUPREME D Sale Wing with 25 floors and 40 units.

What are the flat sizes (carpet area) in AVANT HILLWAY?

According to GharKundli's check of MahaRERA records (updated October 2026), the builder has filed these homes for AVANT HILLWAY: 2 BHK: 618 to 853 sq ft carpet (37 homes); 1 BHK: 346 to 400 sq ft carpet (2 homes); 3 BHK: 900 sq ft carpet (1 homes). Carpet area is the usable floor area inside the walls, as defined under RERA.

How big is the land of AVANT HILLWAY?

According to GharKundli's check of MahaRERA records (updated October 2026), AVANT HILLWAY stands on 1,375 sq m of land (about 0.3 acres), with 4,368 sq m of sanctioned built-up area.

What is the track record of AVANT HILLWAY's builder?

According to GharKundli's check of MahaRERA records (updated October 2026), Avant Heritage III Realty (a group of 4 linked companies) has 6 projects on MahaRERA since 2017, this one included. Of the 6 GharKundli has checked: 6 still being built, 4 past the promised date (typically 6 months late). 22 complaints on MahaRERA across 3 projects. GharKundli's full report covers the builder's record in detail.

Where can I read reviews of AVANT HILLWAY?

Google Maps has reviews of AVANT HILLWAY written by Google users; GharKundli links to them on this page but doesn't check them. For facts rather than opinions: no complaints are listed on MahaRERA, and Kundli Watch shows verified owners of the project.

Where is AVANT HILLWAY?

AVANT HILLWAY by RAGHVENDRA CONSTRUCTION COMPANY PVT LTD (Avant) is in M, Mumbai (pincode 400063), near Goregaon East, Goregaon West, Pahadi Goregaon, Maharashtra, and is registered on MahaRERA as P51800011215, per GharKundli's check of MahaRERA records.

How many homes are in AVANT HILLWAY?

According to GharKundli's check of MahaRERA records (updated October 2026), AVANT HILLWAY has 40 homes in 1 tower registered on MahaRERA, and 88% of them are sold or booked.

When was AVANT HILLWAY registered on MahaRERA?

According to GharKundli's check of MahaRERA records (updated October 2026), AVANT HILLWAY was registered on MahaRERA on 31 August 2017. GharKundli did not find a title report on the land on file there.

Are there court cases on AVANT HILLWAY?

No court cases are listed for AVANT HILLWAY on MahaRERA, per GharKundli's check of MahaRERA records (updated October 2026).

Who is the builder of AVANT HILLWAY?

According to GharKundli's check of MahaRERA records (updated October 2026), the builder is RAGHVENDRA CONSTRUCTION COMPANY PVT LTD, the company Avant files this project under, which has 2 other projects registered on MahaRERA.

All projects with possession due in 2027 in Mumbai Suburban →

Other projects in Borivali

All 151 projects in Goregaon East (400063) →

Other projects by RAGHVENDRA CONSTRUCTION COMPANY PVT LTD

Data compiled by GharKundli (gharkundli.com) from MahaRERA public records, as of October 2026. Check the project’s MahaRERA page for the latest filings. Not legal advice.