Avant Hillway, Composite Building - B1 Sale Wing, SAPPHIRE
by RAGHVENDRA CONSTRUCTION COMPANY PVT LTD (Avant) · Malad East, MumbaiAlso near Aareymilk Colony
Possession date of Avant Hillway, Composite Building - B1 Sale Wing, SAPPHIRE: 30 April 2027, moved from 31 December 2025 (12 months later). This is the latest completion date the builder has filed on MahaRERA. How to check it yourself
Registered on MahaRERA under P51800048113, and currently active. Its completion date has moved from December 2025 to April 2027: 12 months at the builder's request, plus MahaRERA's automatic 4-month extension for all eligible projects. 6 complaints are listed against it on MahaRERA.
Source: GharKundli’s check of MahaRERA records, October 2026.
What do you want to know about Avant Hillway, Composite Building - B1 Sale Wing, SAPPHIRE?
How the possession date of Avant Hillway, Composite Building - B1 Sale Wing, SAPPHIRE has moved
31 December 2025
Completion date given when the project was registered
31 December 2026
Extended at the builder's request (MahaRERA application EA05012619283)
Reason the builder gave MahaRERA: “Ongoing MOEF case”
30 April 2027
MahaRERA's automatic 4-month extension for all eligible projects, not the builder's request
Source: Avant Hillway, Composite Building - B1 Sale Wing, SAPPHIRE’s extension records on MahaRERA (P51800048113), read by GharKundli in October 2026. The builder’s reasons are quoted as filed. Your own possession date is the one in your agreement for sale.
What builders tell MahaRERA when they’re late: 14,973 applications analysed →GharKundli’s full report on Avant Hillway, Composite Building - B1 Sale Wing, SAPPHIRE
Read from every filing on MahaRERA when you open it
- Risk & trust score, every point explained
- What the title report says about the land
- Each of the 6 complaints, and how it ended
- Construction pace against the April 2027 deadline
- Agreement clauses weaker than the RERA model
- Escrow audit, loans and the builder's record
- Questions to get answered in writing before you pay
- MahaRERA registration
- P51800048113
- Status
- Registered and active
- Builder
- RAGHVENDRA CONSTRUCTION COMPANY PVT LTD
- Location
- Malad East, Mumbai · 400063
- Project type
- Residential / Group Housing
- Registered on
- 12 Dec 2022
- Completion date at registration
- December 2025
- Latest completion date
- April 2027
- Delay so far
- 12 months
- MahaRERA's automatic extension
- +4 months (force majeure, all eligible projects)
- Homes
- 96
- Sold or booked
- 95%
- Towers
- 1
- Complaints on MahaRERA
- 6
- Court cases listed
- 0
- Appeals at the tribunal
- 1
- Title report on file
- Not found
- Builder's other MahaRERA projects
- 2
Construction progress of Avant Hillway, Composite Building - B1 Sale Wing, SAPPHIRE, as filed by the builder
What the builder has reported to MahaRERA, as GharKundli read it in October 2026. GharKundli’s full report compares it with the deadline.
| Tower / wing | Plinth | Slabs (structure) | Internal work | Lifts, fire & electrical |
|---|---|---|---|---|
| Composite Building - B1 Sale Wing, SAPPHIRE | 100% | 78% | 20% | 0% |
Commencement certificate (CC), as filed on MahaRERA
- Composite Building - B1 Sale Wing, SAPPHIRE: covers 23 floors
Want to know when this changes? Kundli Watch sends a free WhatsApp update on Avant Hillway, Composite Building - B1 Sale Wing, SAPPHIRE every month.
Avant Hillway, Composite Building - B1 Sale Wing, SAPPHIRE: buildings, flats and land, as filed on MahaRERA
| Type | Carpet area (sq ft) | Units |
|---|---|---|
| 1 BHK | 234 – 618 | 73 |
| 2 BHK | 603 – 621 | 23 |
- Buildings: Composite Building - B1 Sale Wing, SAPPHIRE (25 floors, 96 units)
- Land: 1,375 sq m (about 0.3 acres) · sanctioned built-up 4,373 sq m · recreational space 745 sq m
The builder’s record and reviews
Avant Heritage III Realty (a group of 4 linked companies) has 6 projects on MahaRERA since 2017, this one included. Of the 6 GharKundli has checked: 6 still being built, 4 past the promised date (typically 6 months late). 22 complaints on MahaRERA across 3 projects.
Read Google reviews of Avant Hillway, Composite Building - B1 Sale Wing, SAPPHIRE →Reviews on Google are opinions by Google users; GharKundli doesn’t check them.
Kundli Watch
Avant Hillway, Composite Building - B1 Sale Wing, SAPPHIRE: buyers & owners
Free: a WhatsApp update every month on this project, and straight away when anything changes on MahaRERA — a later completion date, new complaints, a red flag. Your number stays private: never shown to other members or the builder.
Be the first to watch this project.
How are you connected to this project?
Bought here? No document needed now. From the builder’s team? Join to answer buyers’ questions; you never see members’ details. You’ll sign in with a one-time code, then come straight back here.
Common questions about Avant Hillway, Composite Building - B1 Sale Wing, SAPPHIRE
What is the possession date of Avant Hillway, Composite Building - B1 Sale Wing, SAPPHIRE?
According to GharKundli's check of MahaRERA records (updated October 2026), the latest completion date filed on MahaRERA for Avant Hillway, Composite Building - B1 Sale Wing, SAPPHIRE in Malad East, Mumbai is 30 April 2027 — 12 months later than 31 December 2025, the date given at registration, plus MahaRERA's automatic 4-month extension for all eligible projects.
Is the builder's possession date different from the MahaRERA date for Avant Hillway, Composite Building - B1 Sale Wing, SAPPHIRE?
Builders and listing sites often quote an earlier "target" date for handover. The completion date Avant Hillway, Composite Building - B1 Sale Wing, SAPPHIRE's builder has filed on MahaRERA, the official one, is 30 April 2027, already 12 months later than the 31 December 2025 given at registration, per GharKundli's check of MahaRERA records. If possession is late, what counts under RERA (Section 18) is the possession date written in your agreement for sale.
Why was the possession date of Avant Hillway, Composite Building - B1 Sale Wing, SAPPHIRE extended?
According to GharKundli's check of MahaRERA records (updated October 2026), Avant Hillway, Composite Building - B1 Sale Wing, SAPPHIRE's builder applied to MahaRERA to extend the completion date once: to 31 December 2026, giving the reason "Ongoing MOEF case". MahaRERA also added its automatic 4-month extension for all eligible projects.
What is the RERA number of Avant Hillway, Composite Building - B1 Sale Wing, SAPPHIRE?
According to GharKundli's check of MahaRERA records (updated October 2026), the MahaRERA registration number of Avant Hillway, Composite Building - B1 Sale Wing, SAPPHIRE in Malad East, Mumbai is P51800048113.
Is Avant Hillway, Composite Building - B1 Sale Wing, SAPPHIRE registered with MahaRERA?
According to GharKundli's check of MahaRERA records (updated October 2026), Avant Hillway, Composite Building - B1 Sale Wing, SAPPHIRE is registered as P51800048113 and its status is "Registered and active".
What is the construction status of Avant Hillway, Composite Building - B1 Sale Wing, SAPPHIRE?
According to GharKundli's check of MahaRERA records (updated October 2026), Avant Hillway, Composite Building - B1 Sale Wing, SAPPHIRE's status on MahaRERA is "Registered and active". As filed by the builder, slab work on Composite Building - B1 Sale Wing, SAPPHIRE is 78% done and internal work 20%. GharKundli's full report compares construction progress with the deadline.
Does Avant Hillway, Composite Building - B1 Sale Wing, SAPPHIRE have complaints on MahaRERA?
6 complaints were listed on MahaRERA as of October 2026, per GharKundli's weekly check. GharKundli's full report explains each case and how it ended.
Is Avant Hillway, Composite Building - B1 Sale Wing, SAPPHIRE safe to buy?
According to GharKundli's check of MahaRERA records (updated October 2026), Avant Hillway, Composite Building - B1 Sale Wing, SAPPHIRE is registered on MahaRERA as P51800048113, its completion date has moved 12 months since registration and 6 complaints are listed against it. GharKundli doesn't call a project safe or unsafe from these numbers alone: its full report gives a risk & trust score with every point explained.
How can I get updates if Avant Hillway, Composite Building - B1 Sale Wing, SAPPHIRE's possession date changes?
The latest dates are on Avant Hillway, Composite Building - B1 Sale Wing, SAPPHIRE's MahaRERA page (P51800048113). GharKundli's Kundli Watch sends a free WhatsApp update on Avant Hillway, Composite Building - B1 Sale Wing, SAPPHIRE every month, and straight away when anything changes on MahaRERA: a later completion date, new complaints or a red flag. Your number is never shown to the builder.
How many floors does Avant Hillway, Composite Building - B1 Sale Wing, SAPPHIRE have?
According to GharKundli's check of MahaRERA records (updated October 2026), Avant Hillway, Composite Building - B1 Sale Wing, SAPPHIRE has one building filed: Composite Building - B1 Sale Wing, SAPPHIRE with 25 floors and 96 units.
What are the flat sizes (carpet area) in Avant Hillway, Composite Building - B1 Sale Wing, SAPPHIRE?
According to GharKundli's check of MahaRERA records (updated October 2026), the builder has filed these homes for Avant Hillway, Composite Building - B1 Sale Wing, SAPPHIRE: 1 BHK: 234 to 618 sq ft carpet (73 homes); 2 BHK: 603 to 621 sq ft carpet (23 homes). Carpet area is the usable floor area inside the walls, as defined under RERA.
How big is the land of Avant Hillway, Composite Building - B1 Sale Wing, SAPPHIRE?
According to GharKundli's check of MahaRERA records (updated October 2026), Avant Hillway, Composite Building - B1 Sale Wing, SAPPHIRE stands on 1,375 sq m of land (about 0.3 acres), with 4,373 sq m of sanctioned built-up area and 745 sq m of recreational open space.
What is the track record of Avant Hillway, Composite Building - B1 Sale Wing, SAPPHIRE's builder?
According to GharKundli's check of MahaRERA records (updated October 2026), Avant Heritage III Realty (a group of 4 linked companies) has 6 projects on MahaRERA since 2017, this one included. Of the 6 GharKundli has checked: 6 still being built, 4 past the promised date (typically 6 months late). 22 complaints on MahaRERA across 3 projects. GharKundli's full report covers the builder's record in detail.
Where can I read reviews of Avant Hillway, Composite Building - B1 Sale Wing, SAPPHIRE?
Google Maps has reviews of Avant Hillway, Composite Building - B1 Sale Wing, SAPPHIRE written by Google users; GharKundli links to them on this page but doesn't check them. For facts rather than opinions: 6 complaints are listed on MahaRERA, and Kundli Watch shows verified owners of the project.
Where is Avant Hillway, Composite Building - B1 Sale Wing, SAPPHIRE?
Avant Hillway, Composite Building - B1 Sale Wing, SAPPHIRE by RAGHVENDRA CONSTRUCTION COMPANY PVT LTD (Avant) is in Malad East, Mumbai (pincode 400063), near Aareymilk Colony, Maharashtra, and is registered on MahaRERA as P51800048113, per GharKundli's check of MahaRERA records.
How many homes are in Avant Hillway, Composite Building - B1 Sale Wing, SAPPHIRE?
According to GharKundli's check of MahaRERA records (updated October 2026), Avant Hillway, Composite Building - B1 Sale Wing, SAPPHIRE has 96 homes in 1 tower registered on MahaRERA, and 95% of them are sold or booked.
When was Avant Hillway, Composite Building - B1 Sale Wing, SAPPHIRE registered on MahaRERA?
According to GharKundli's check of MahaRERA records (updated October 2026), Avant Hillway, Composite Building - B1 Sale Wing, SAPPHIRE was registered on MahaRERA on 12 December 2022. GharKundli did not find a title report on the land on file there.
Are there court cases on Avant Hillway, Composite Building - B1 Sale Wing, SAPPHIRE?
No court cases are listed for Avant Hillway, Composite Building - B1 Sale Wing, SAPPHIRE on MahaRERA, and 1 appeal at the tribunal, per GharKundli's check of MahaRERA records (updated October 2026). GharKundli's full report explains each case and how it ended.
Who is the builder of Avant Hillway, Composite Building - B1 Sale Wing, SAPPHIRE?
According to GharKundli's check of MahaRERA records (updated October 2026), the builder is RAGHVENDRA CONSTRUCTION COMPANY PVT LTD, the company Avant files this project under, which has 2 other projects registered on MahaRERA.
Check it yourself on MahaRERA
- How to check the possession date of Avant Hillway, Composite Building - B1 Sale Wing, SAPPHIRE
- How to find and verify a MahaRERA number
- How to check construction status on MahaRERA
- Occupancy certificate (OC): what to check before possession
- Possession delayed? Work out the interest the builder owes
- How to file a MahaRERA complaint against a builder
- Where MahaRERA complaints are: the data
- Why builders ask MahaRERA for more time: the data
All projects with possession due in 2027 in Mumbai Suburban →
Other projects in Malad East
- Vardhan Royale
- Florence Residency
- Pearl Solitaire
- Sheetal Sangam
- Aarambh Phase III by group Satellite
- PARMAR PEARL - JAY KOTESHWAR NAGAR CHS LTD
- Elegance Heights
- Inayah Residency
Other projects by RAGHVENDRA CONSTRUCTION COMPANY PVT LTD
Data compiled by GharKundli (gharkundli.com) from MahaRERA public records, as of October 2026. Check the project’s MahaRERA page for the latest filings. Not legal advice.