Satellite Elegance

by Newone Constructions Private Limited (Satellite) · Goregoan East, MumbaiAlso near Malad East, Aareymilk Colony

Possession date of Satellite Elegance: 30 April 2027, moved from 30 December 2024 (24 months later). This is the latest completion date the builder has filed on MahaRERA. How to check it yourself

Registered on MahaRERA under P51800021913, and currently active. Its completion date has moved from December 2024 to April 2027: 24 months at the builder's request, plus MahaRERA's automatic 4-month extension for all eligible projects. 11 complaints are listed against it on MahaRERA.

Source: GharKundli’s check of MahaRERA records, October 2026.

What do you want to know about Satellite Elegance?

Ask us on WhatsAppNo login needed. A real person replies.

How the possession date of Satellite Elegance has moved

  1. 30 December 2024

    Completion date given when the project was registered

  2. 29 December 2025

    Extended at the builder's request (MahaRERA application EXT51800024728)

    Reason the builder gave MahaRERA:
    “The project's completion date has been delayed mainly due to non-receipt of CC for part of 34th floor of project Satellite Elegance where MOEF/ EC clearance is mandatory. The reasons beyond the control of Developer for delay in MOEF/EC clea…” Read the full reason“The project's completion date has been delayed mainly due to non-receipt of CC for part of 34th floor of project Satellite Elegance where MOEF/ EC clearance is mandatory. The reasons beyond the control of Developer for delay in MOEF/EC clearance are as follows. A) The absence of the State Level Environment Impact Assessment Authority (SEIAA) for Maharashtra from Jan 24 to Jun 24, which led to the need for EC clearance through the PARIVESH portal in Delhi. Delhi waited for the few months on proposal and send back proposal to Maharashtra post Jun-24 when committee was formed. The proposal was…”
  3. 30 June 2026

    Extended at the builder's request (MahaRERA application EA15122518680)

    Reason the builder gave MahaRERA:
    “The reasons for seeking extension which were beyond the control of Newone Constructions Private Limited are briefly set out hereunder: 1. Final Commencement Certificate (CC) delayed (34th floor (Part) for MOEF / EC Approval: The State Level…” Read the full reason“The reasons for seeking extension which were beyond the control of Newone Constructions Private Limited are briefly set out hereunder: 1. Final Commencement Certificate (CC) delayed (34th floor (Part) for MOEF / EC Approval: The State Level Environment Impact Assessment Authority (SEIAA) for the state of Maharashtra Environment was not in existence from Jan 2024 to Jun 2024 due to this we had to put EC clearance through PARIVESH PORTAL at Delhi. 2. Later on when state level Committee SEIAA (Authority) was formed in June 2024 our proposal was referred by Delhi Authority to SEIAA (Maharashtra…”
  4. 31 December 2026

    Extended at the builder's request (MahaRERA application EA01072621650)

    Reason the builder gave MahaRERA:
    “The reasons for seeking extension which were beyond the control of Promoter are briefly set out hereunder: 1. Final Commencement Certificate (CC) delayed (34th floor (Part) for MOEF/EC Approval: The State Level Environment Impact Assessment…” Read the full reason“The reasons for seeking extension which were beyond the control of Promoter are briefly set out hereunder: 1. Final Commencement Certificate (CC) delayed (34th floor (Part) for MOEF/EC Approval: The State Level Environment Impact Assessment Authority (SEIAA) for the state of Maharashtra Environment was not in existence from Jan 2024 to Jun 2024 due to this we had to put EC clearance through PARIVESH PORTAL at Delhi. 2. Later on when state level Committee SEIAA (Authority) was formed in June 2024 our proposal was referred by Delhi Authority to SEIAA on 11/06/2024 with change in file no to SI…”
  5. 30 April 2027

    MahaRERA's automatic 4-month extension for all eligible projects, not the builder's request

Source: Satellite Elegance’s extension records on MahaRERA (P51800021913), read by GharKundli in October 2026. The builder’s reasons are quoted as filed. Your own possession date is the one in your agreement for sale.

What builders tell MahaRERA when they’re late: 14,973 applications analysed →

GharKundli’s full report on Satellite Elegance

Read from every filing on MahaRERA when you open it

  • Risk & trust score, every point explained
  • What the title report says about the land
  • Each of the 11 complaints and 1 court case, and how it ended
  • Construction pace against the April 2027 deadline
  • Agreement clauses weaker than the RERA model
  • Escrow audit, loans and the builder's record
  • Questions to get answered in writing before you pay
MahaRERA registration
P51800021913
Status
Registered and active
Builder
Newone Constructions Private Limited
Location
Goregoan East, Mumbai · 400063
Project type
Residential / Group Housing
Registered on
8 Aug 2019
Completion date at registration
December 2024
Latest completion date
April 2027
Delay so far
24 months
MahaRERA's automatic extension
+4 months (force majeure, all eligible projects)
Homes
287
Sold or booked
93%
Towers
2
Complaints on MahaRERA
11
Court cases listed
1
Appeals at the tribunal
6
Title report on file
Not found

Construction progress of Satellite Elegance, as filed by the builder

What the builder has reported to MahaRERA, as GharKundli read it in October 2026. GharKundli’s full report compares it with the deadline.

Tower / wingPlinthSlabs (structure)Internal workLifts, fire & electrical
Elegance Wing A100%100%81%30%
Elegance Wing B100%100%81%30%

Commencement certificate (CC), as filed on MahaRERA

  • Elegance Wing A: covers upto 34th Floor
  • Elegance Wing B: covers Upto 34th Floor

Latest CC order on MahaRERA: dated 29/10/2025.

Want to know when this changes? Kundli Watch sends a free WhatsApp update on Satellite Elegance every month.

Satellite Elegance: buildings, flats and land, as filed on MahaRERA

TypeCarpet area (sq ft)Units
2 BHK635 – 794226
1 BHK427 – 52057
3 BHK794 – 8904
  • Buildings: Elegance Wing A (36 floors, 144 units) · Elegance Wing B (36 floors, 143 units)
  • Car parking: 293 covered
  • Land: 4,621 sq m (about 1.1 acres) · sanctioned built-up 18,568 sq m · recreational space 369 sq m
  • Map: the location the builder filed on MahaRERA

The builder’s record and reviews

Satellite Developers (a group of 5 linked companies) has 11 projects on MahaRERA since 2017, this one included. Of the 11 GharKundli has checked: 4 finished, 3 within the promised date and 1 needed more time (typically 4 months); 6 still being built, 2 past the promised date (typically 10 months late); 1 lapsed. 29 complaints on MahaRERA across 5 projects.

Read Google reviews of Satellite Elegance →Reviews on Google are opinions by Google users; GharKundli doesn’t check them.

Kundli Watch

Satellite Elegance: buyers & owners

Free: a WhatsApp update every month on this project, and straight away when anything changes on MahaRERA — a later completion date, new complaints, a red flag. Your number stays private: never shown to other members or the builder.

Be the first to watch this project.

How are you connected to this project?

Bought here? No document needed now. From the builder’s team? Join to answer buyers’ questions; you never see members’ details. You’ll sign in with a one-time code, then come straight back here.

Common questions about Satellite Elegance

What is the possession date of Satellite Elegance?

According to GharKundli's check of MahaRERA records (updated October 2026), the latest completion date filed on MahaRERA for Satellite Elegance in Goregoan East, Mumbai is 30 April 2027 — 24 months later than 30 December 2024, the date given at registration, plus MahaRERA's automatic 4-month extension for all eligible projects.

Is the builder's possession date different from the MahaRERA date for Satellite Elegance?

Builders and listing sites often quote an earlier "target" date for handover. The completion date Satellite Elegance's builder has filed on MahaRERA, the official one, is 30 April 2027, already 24 months later than the 30 December 2024 given at registration, per GharKundli's check of MahaRERA records. If possession is late, what counts under RERA (Section 18) is the possession date written in your agreement for sale.

Why was the possession date of Satellite Elegance extended?

According to GharKundli's check of MahaRERA records (updated October 2026), Satellite Elegance's builder applied to MahaRERA to extend the completion date 3 times: to 29 December 2025, giving the reason "The project's completion date has been delayed mainly due to non-receipt of CC for part of 34th floor of project Satellite Elegance where MOEF/ EC clearance is mandatory. The reasons beyond the control of Developer for delay in MOEF/EC clearance are as follows. A) The absence of the State Level Environment Impact Assessment Authority (SEIAA) for Maharashtra from Jan 24 to Jun 24, which led to the need for EC clearance through the PARIVESH portal in Delhi. Delhi waited for the few months on proposal and send back proposal to Maharashtra post Jun-24 when committee was formed. The proposal was…"; to 30 June 2026, giving the reason "The reasons for seeking extension which were beyond the control of Newone Constructions Private Limited are briefly set out hereunder: 1. Final Commencement Certificate (CC) delayed (34th floor (Part) for MOEF / EC Approval: The State Level Environment Impact Assessment Authority (SEIAA) for the state of Maharashtra Environment was not in existence from Jan 2024 to Jun 2024 due to this we had to put EC clearance through PARIVESH PORTAL at Delhi. 2. Later on when state level Committee SEIAA (Authority) was formed in June 2024 our proposal was referred by Delhi Authority to SEIAA (Maharashtra…"; to 31 December 2026, giving the reason "The reasons for seeking extension which were beyond the control of Promoter are briefly set out hereunder: 1. Final Commencement Certificate (CC) delayed (34th floor (Part) for MOEF/EC Approval: The State Level Environment Impact Assessment Authority (SEIAA) for the state of Maharashtra Environment was not in existence from Jan 2024 to Jun 2024 due to this we had to put EC clearance through PARIVESH PORTAL at Delhi. 2. Later on when state level Committee SEIAA (Authority) was formed in June 2024 our proposal was referred by Delhi Authority to SEIAA on 11/06/2024 with change in file no to SI…". MahaRERA also added its automatic 4-month extension for all eligible projects.

What is the RERA number of Satellite Elegance?

According to GharKundli's check of MahaRERA records (updated October 2026), the MahaRERA registration number of Satellite Elegance in Goregoan East, Mumbai is P51800021913.

Is Satellite Elegance registered with MahaRERA?

According to GharKundli's check of MahaRERA records (updated October 2026), Satellite Elegance is registered as P51800021913 and its status is "Registered and active".

What is the construction status of Satellite Elegance?

According to GharKundli's check of MahaRERA records (updated October 2026), Satellite Elegance's status on MahaRERA is "Registered and active". As filed by the builder, slab work is 100% done across 2 towers. GharKundli's full report compares construction progress with the deadline.

Does Satellite Elegance have complaints on MahaRERA?

11 complaints were listed on MahaRERA as of October 2026, per GharKundli's weekly check. GharKundli's full report explains each case and how it ended.

Is Satellite Elegance safe to buy?

According to GharKundli's check of MahaRERA records (updated October 2026), Satellite Elegance is registered on MahaRERA as P51800021913, its completion date has moved 24 months since registration and 11 complaints are listed against it. GharKundli doesn't call a project safe or unsafe from these numbers alone: its full report gives a risk & trust score with every point explained.

How can I get updates if Satellite Elegance's possession date changes?

The latest dates are on Satellite Elegance's MahaRERA page (P51800021913). GharKundli's Kundli Watch sends a free WhatsApp update on Satellite Elegance every month, and straight away when anything changes on MahaRERA: a later completion date, new complaints or a red flag. Your number is never shown to the builder.

How many floors does Satellite Elegance have?

According to GharKundli's check of MahaRERA records (updated October 2026), Satellite Elegance has 2 buildings filed: Elegance Wing A with 36 floors and 144 units; Elegance Wing B with 36 floors and 143 units.

What are the flat sizes (carpet area) in Satellite Elegance?

According to GharKundli's check of MahaRERA records (updated October 2026), the builder has filed these homes for Satellite Elegance: 2 BHK: 635 to 794 sq ft carpet (226 homes); 1 BHK: 427 to 520 sq ft carpet (57 homes); 3 BHK: 794 to 890 sq ft carpet (4 homes). Carpet area is the usable floor area inside the walls, as defined under RERA.

How much parking does Satellite Elegance have?

According to GharKundli's check of MahaRERA records (updated October 2026), the builder has filed 293 covered car parking spaces for Satellite Elegance.

How big is the land of Satellite Elegance?

According to GharKundli's check of MahaRERA records (updated October 2026), Satellite Elegance stands on 4,621 sq m of land (about 1.1 acres), with 18,568 sq m of sanctioned built-up area and 369 sq m of recreational open space.

What is the track record of Satellite Elegance's builder?

According to GharKundli's check of MahaRERA records (updated October 2026), Satellite Developers (a group of 5 linked companies) has 11 projects on MahaRERA since 2017, this one included. Of the 11 GharKundli has checked: 4 finished, 3 within the promised date and 1 needed more time (typically 4 months); 6 still being built, 2 past the promised date (typically 10 months late); 1 lapsed. 29 complaints on MahaRERA across 5 projects. GharKundli's full report covers the builder's record in detail.

Where can I read reviews of Satellite Elegance?

Google Maps has reviews of Satellite Elegance written by Google users; GharKundli links to them on this page but doesn't check them. For facts rather than opinions: 11 complaints are listed on MahaRERA, and Kundli Watch shows verified owners of the project.

Where is Satellite Elegance?

Satellite Elegance by Newone Constructions Private Limited (Satellite) is in Goregoan East, Mumbai (pincode 400063), near Malad East, Aareymilk Colony, Maharashtra, and is registered on MahaRERA as P51800021913, per GharKundli's check of MahaRERA records.

How many homes are in Satellite Elegance?

According to GharKundli's check of MahaRERA records (updated October 2026), Satellite Elegance has 287 homes in 2 towers registered on MahaRERA, and 93% of them are sold or booked.

When was Satellite Elegance registered on MahaRERA?

According to GharKundli's check of MahaRERA records (updated October 2026), Satellite Elegance was registered on MahaRERA on 8 August 2019. GharKundli did not find a title report on the land on file there.

Are there court cases on Satellite Elegance?

1 court case is listed for Satellite Elegance on MahaRERA, and 6 appeals at the tribunal, per GharKundli's check of MahaRERA records (updated October 2026). GharKundli's full report explains each case and how it ended.

Who is the builder of Satellite Elegance?

According to GharKundli's check of MahaRERA records (updated October 2026), the builder is Newone Constructions Private Limited, the company Satellite files this project under.

All projects with possession due in 2027 in Mumbai Suburban →

Other projects in pincode 400063

All 151 projects in Goregaon East (400063) →

Data compiled by GharKundli (gharkundli.com) from MahaRERA public records, as of October 2026. Check the project’s MahaRERA page for the latest filings. Not legal advice.