Horizon Tower
by I.R.Developers LLP · Sher -E-Punjab CHS , Andheri East, Mumbai 400093Also near Jogeshwari East, Andheri West, Mogra
What’s in the report? →Possession date of Horizon Tower (MahaRERA P51800056381): 31 July 2027, moved from 31 March 2026 (12 months later). It has 25 homes (3 BHK, 880–934 sq ft carpet), 15% sold or booked. No complaints on MahaRERA. How to check it yourself
Registered on MahaRERA under P51800056381, and currently active. Its completion date has moved from March 2026 to July 2027: 12 months at the builder's request, plus MahaRERA's automatic 4-month extension for all eligible projects.
Source: MahaRERA website — records for P51800056381, read and compiled by GharKundli. Facts as filed on MahaRERA, no opinions.
What do you want to know about Horizon Tower?
Title report MahaRERA par nahi dikh rahi. Kya poochna hai?Tap a question. We’ll answer you on WhatsApp, free.
How the possession date of Horizon Tower has moved
31 March 2026
Completion date given when the project was registered
31 March 2027
Extended at the builder's request (MahaRERA application EA19072502110)
Reason the builder gave MahaRERA:
“We apologize for the delay in the completion of the project and the submission of this request. The delay has occurred due to unforeseen circumstances, including procurement issues, financial constraints, and site challenges. Despite these…” Read the full reason
“We apologize for the delay in the completion of the project and the submission of this request. The delay has occurred due to unforeseen circumstances, including procurement issues, financial constraints, and site challenges. Despite these setbacks, we are working diligently to address these issues and complete the remaining work. Given the circumstances, we kindly request an extension until 31-03-2027, to complete the project and fulfil all regulatory requirements.”31 July 2027
MahaRERA's automatic 4-month extension for all eligible projects, not the builder's request
Source: Horizon Tower’s extension records on MahaRERA (P51800056381), read by GharKundli in October 2026. The builder’s reasons are quoted as filed. Your own possession date is the one in your agreement for sale.
What builders tell MahaRERA when they’re late: 14,973 applications analysed →GharKundli’s full report on Horizon Tower
Read from every filing on MahaRERA when you open it
- Risk & trust score, every point explained
- What the title report says about the land
- Each complaint and court case, and how it ended
- Construction pace against the July 2027 deadline
- Agreement clauses weaker than the RERA model
- Escrow audit, loans and the builder's record
- Questions to get answered in writing before you pay
- MahaRERA registration
- P51800056381
- Status
- Registered and active
- Builder
- I.R.Developers LLP
- Location
- Sher -E-Punjab CHS , Andheri East, Mumbai · 400093
- Project type
- Residential / Group Housing
- Registered on
- 31 May 2024
- Completion date at registration
- March 2026
- Latest completion date
- July 2027
- Delay so far
- 12 months
- MahaRERA's automatic extension
- +4 months (force majeure, all eligible projects)
- Homes
- 25
- Sold or booked
- 15%
- Towers
- 1
- Complaints on MahaRERA
- 0
- Court cases listed
- 0
- Title report on file
- Not found
- Builder's other MahaRERA projects
- 4
Construction progress of Horizon Tower, as filed by the builder
What the builder has reported to MahaRERA, as GharKundli read it in October 2026. GharKundli’s full report compares it with the deadline.
| Tower / wing | Plinth | Slabs (structure) | Internal work | Lifts, fire & electrical |
|---|---|---|---|---|
| Horizon Tower | 100% | 100% | 90% | 0% |
Commencement certificate (CC), as filed on MahaRERA
- Horizon Tower: covers 15 floors
Latest CC order on MahaRERA: dated 03/07/2025.
Want to know when this changes? Kundli Watch sends a free WhatsApp update on Horizon Tower every 1–2 months.
Horizon Tower: buildings, flats and land, as filed on MahaRERA
| Type | Carpet area (sq ft) | Units |
|---|---|---|
| 3 BHK | 880 – 934 | 25 |
- Buildings: Horizon Tower (16 floors, 25 units)
- Car parking: 35 covered
- Land: 836 sq m (about 0.2 acres) · sanctioned built-up 1,672 sq m
- Land, as filed: 368/301 ,368/302
- Map: the location the builder filed on MahaRERA · Get directions
The builder’s record and reviews
I R Developers has 5 projects on MahaRERA since 2022, this one included. Of the 5 GharKundli has checked: 3 finished, all within the promised date; 2 still being built, 1 past the promised date (typically 3 months late). 1 complaint on MahaRERA across 1 project.
Read Google reviews of Horizon Tower →Reviews on Google are opinions by Google users; GharKundli doesn’t check them.
Kundli Watch
Horizon Tower: buyers & owners
Free: a construction progress update on WhatsApp every 1–2 months, and straight away when anything changes on MahaRERA — a later completion date, new complaints, a red flag. Your number stays private: never shown to other members or the builder.
Be the first to watch this project.
How are you connected to this project?
Watching needs only WhatsApp or your number. Bought here? No document needed now. From the builder’s team? Join to answer buyers’ questions; you never see members’ details. Owners and the builder’s team sign in with a one-time code, then come straight back here.
Common questions about Horizon Tower
What is the possession date of Horizon Tower?
According to GharKundli's check of MahaRERA records (updated October 2026), the latest completion date filed on MahaRERA for Horizon Tower in Sher -E-Punjab CHS , Andheri East, Mumbai is 31 July 2027 — 12 months later than 31 March 2026, the date given at registration, plus MahaRERA's automatic 4-month extension for all eligible projects.
The date has already moved 12 months. Will it move again? Check the real pace of construction →
Is the builder's possession date different from the MahaRERA date for Horizon Tower?
Builders and listing sites often quote an earlier "target" date for handover. The completion date Horizon Tower's builder has filed on MahaRERA, the official one, is 31 July 2027, already 12 months later than the 31 March 2026 given at registration, per GharKundli's check of MahaRERA records. If possession is late, what counts under RERA (Section 18) is the possession date written in your agreement for sale.
Why was the possession date of Horizon Tower extended?
According to GharKundli's check of MahaRERA records (updated October 2026), Horizon Tower's builder applied to MahaRERA to extend the completion date once: to 31 March 2027, giving the reason "We apologize for the delay in the completion of the project and the submission of this request. The delay has occurred due to unforeseen circumstances, including procurement issues, financial constraints, and site challenges. Despite these setbacks, we are working diligently to address these issues and complete the remaining work. Given the circumstances, we kindly request an extension until 31-03-2027, to complete the project and fulfil all regulatory requirements.". MahaRERA also added its automatic 4-month extension for all eligible projects.
What is the RERA number of Horizon Tower?
According to GharKundli's check of MahaRERA records (updated October 2026), the MahaRERA registration number of Horizon Tower in Sher -E-Punjab CHS , Andheri East, Mumbai is P51800056381.
Is Horizon Tower registered with MahaRERA?
According to GharKundli's check of MahaRERA records (updated October 2026), Horizon Tower is registered as P51800056381 and its status is "Registered and active".
What is the current construction status of Horizon Tower? How much work is done?
According to GharKundli's check of MahaRERA records (updated October 2026), Horizon Tower's status on MahaRERA is "Registered and active". As filed by the builder, slab work on Horizon Tower is 100% done and internal work 90%. GharKundli's full report compares construction progress with the deadline.
Does Horizon Tower have complaints on MahaRERA?
No complaints were listed on MahaRERA as of October 2026, per GharKundli's weekly check.
Is Horizon Tower safe to buy?
According to GharKundli's check of MahaRERA records (updated October 2026), Horizon Tower is registered on MahaRERA as P51800056381, its completion date has moved 12 months since registration and no complaints are listed against it. GharKundli doesn't call a project safe or unsafe from these numbers alone: its full report gives a risk & trust score with every point explained.
How much GST is payable on a flat in Horizon Tower?
Horizon Tower is under construction, so GST applies to a new flat: 5% of the price, with no input tax credit. The lower 1% rate is only for "affordable" homes: carpet area up to 60 sq m (about 646 sq ft) in the Mumbai region, and price up to ₹45 lakh. Flats in Horizon Tower start at 880 sq ft carpet, above that limit, so expect 5%. There is no GST on stamp duty or registration, and none once the occupancy certificate is issued.
What is the stamp duty and registration cost for a flat in Horizon Tower?
For a flat in Horizon Tower (Mumbai), stamp duty is 6% of the agreement value, or of the ready reckoner value if that's higher, including 1% Metro Cess. A woman buying in her own name pays 5%. Registration is 1% of the value, capped at ₹30,000. On a ₹1 crore flat that's about ₹6 lakh in stamp duty plus ₹30,000 registration. GharKundli's property cost calculator works it out for your price: gharkundli.com/tools/property-cost-calculator
Has Horizon Tower received its OC? Is it ready to move in?
Not yet. According to GharKundli's check of MahaRERA records (updated October 2026), Horizon Tower is still under construction, with 31 July 2027 as the latest completion date filed on MahaRERA. A flat is ready to move in only once the occupancy certificate (OC) is issued, after construction is complete.
Is Horizon Tower a redevelopment or SRA project?
According to GharKundli's check of MahaRERA records (updated October 2026), Horizon Tower is a redevelopment: 12 of its flats are set aside for existing occupants (rehab), and the rest are for sale. Its planning authority is MCGM, not the Slum Rehabilitation Authority, so it isn't an SRA scheme.
Has Horizon Tower uploaded its title report on MahaRERA?
According to GharKundli's check of MahaRERA records (updated October 2026), no title report for Horizon Tower was found on MahaRERA. Builders are expected to upload one; before booking, ask the builder for the advocate's title certificate in writing.
No title report is on MahaRERA for this project. See which documents are missing →
How can I get updates if Horizon Tower's possession date changes?
The latest dates are on Horizon Tower's MahaRERA page (P51800056381). GharKundli's Kundli Watch sends a free WhatsApp update on Horizon Tower every 1–2 months, and straight away when anything changes on MahaRERA: a later completion date, new complaints or a red flag. Your number is never shown to the builder.
How many floors does Horizon Tower have?
According to GharKundli's check of MahaRERA records (updated October 2026), Horizon Tower has one building filed: Horizon Tower with 16 floors and 25 units.
What are the flat sizes (carpet area) in Horizon Tower?
According to GharKundli's check of MahaRERA records (updated October 2026), the builder has filed these homes for Horizon Tower: 3 BHK: 880 to 934 sq ft carpet (25 homes). Carpet area is the usable floor area inside the walls, as defined under RERA.
How much parking does Horizon Tower have?
According to GharKundli's check of MahaRERA records (updated October 2026), the builder has filed 35 covered car parking spaces for Horizon Tower.
How big is the land of Horizon Tower?
According to GharKundli's check of MahaRERA records (updated October 2026), Horizon Tower stands on 836 sq m of land (about 0.2 acres), with 1,672 sq m of sanctioned built-up area.
What is the track record of Horizon Tower's builder?
According to GharKundli's check of MahaRERA records (updated October 2026), I R Developers has 5 projects on MahaRERA since 2022, this one included. Of the 5 GharKundli has checked: 3 finished, all within the promised date; 2 still being built, 1 past the promised date (typically 3 months late). 1 complaint on MahaRERA across 1 project. GharKundli's full report covers the builder's record in detail.
What are the reviews of Horizon Tower?
Google Maps has reviews of Horizon Tower written by Google users; GharKundli links to them on this page but doesn't check them. For facts rather than opinions: no complaints are listed on MahaRERA, and Kundli Watch shows verified owners of the project.
What is the address and pincode of Horizon Tower?
Horizon Tower by I.R.Developers LLP is in Sher -E-Punjab CHS , Andheri East, Mumbai, pincode 400093 (near Jogeshwari East, Andheri West, Mogra), Maharashtra, and is registered on MahaRERA as P51800056381, per GharKundli's check of MahaRERA records. Its land is filed as 368/301 ,368/302. GharKundli lists all 74 MahaRERA projects in Andheri East (400093).
How many flats are in Horizon Tower, and how many are sold?
According to GharKundli's check of MahaRERA records (updated October 2026), Horizon Tower has 25 homes in 1 tower registered on MahaRERA, and 15% of them are sold or booked.
When was Horizon Tower registered on MahaRERA?
According to GharKundli's check of MahaRERA records (updated October 2026), Horizon Tower was registered on MahaRERA on 31 May 2024. GharKundli did not find a title report on the land on file there.
Does Horizon Tower have any legal issues or court cases?
No court cases are listed for Horizon Tower on MahaRERA, per GharKundli's check of MahaRERA records (updated October 2026).
Who is the builder / developer of Horizon Tower?
According to GharKundli's check of MahaRERA records (updated October 2026), the builder is I.R.Developers LLP, which has 4 other projects registered on MahaRERA.
Check it yourself on MahaRERA
- How to check the possession date of Horizon Tower
- How to find and verify a MahaRERA number
- How to check construction status on MahaRERA
- Occupancy certificate (OC): what to check before possession
- Possession delayed? Work out the interest the builder owes
- How to file a MahaRERA complaint against a builder
- Where MahaRERA complaints are: the data
- Why builders ask MahaRERA for more time: the data
All projects with possession due in 2027 in Mumbai Suburban →
Other projects in Andheri
- Shraddha West Residency
- Shivsai Sra CHS
- Live Well Chs Ltd
- Green Bay
- Pruthvi Symphony
- Therese
- KK 415 West
- Venus CHS
Other projects by I.R.Developers LLP
Data compiled by GharKundli (gharkundli.com) from MahaRERA public records, as of October 2026. Check the project’s MahaRERA page for the latest filings. Not legal advice.