Richfeel Amalfi
by RICHFEEL REAL ESTATE PVT. LTD. · K/W Ward, Andheri West, Mumbai 400061Registered on MahaRERA as “Amalfi”
What’s in the report? →Possession date of Richfeel Amalfi (MahaRERA P51800076774): 30 April 2028. It has 45 homes (3 BHK and 4 BHK, 913–9094 sq ft carpet), 59% sold or booked. No complaints on MahaRERA. How to check it yourself
Registered on MahaRERA under P51800076774, and currently active. Its completion date is now April 2028, including MahaRERA's automatic 4-month extension for all eligible projects; the builder hasn't asked for more time.
Source: MahaRERA website — records for P51800076774, read and compiled by GharKundli. Facts as filed on MahaRERA, no opinions.
What do you want to know about Richfeel Amalfi?
Title report MahaRERA par nahi dikh rahi. Kya poochna hai?Tap a question. We’ll answer you on WhatsApp, free.
How the possession date of Richfeel Amalfi has moved
31 December 2027
Completion date given when the project was registered
30 April 2028
MahaRERA's automatic 4-month extension for all eligible projects, not the builder's request
Source: Richfeel Amalfi’s extension records on MahaRERA (P51800076774), read by GharKundli in October 2026. The builder’s reasons are quoted as filed. Your own possession date is the one in your agreement for sale.
What builders tell MahaRERA when they’re late: 14,973 applications analysed →GharKundli’s full report on Richfeel Amalfi
Read from every filing on MahaRERA when you open it
- Risk & trust score, every point explained
- What the title report says about the land
- Each complaint and court case, and how it ended
- Construction pace against the April 2028 deadline
- Agreement clauses weaker than the RERA model
- Escrow audit, loans and the builder's record
- Questions to get answered in writing before you pay
- MahaRERA registration
- P51800076774
- Status
- Registered and active
- Builder
- RICHFEEL REAL ESTATE PVT. LTD.
- Location
- K/W Ward, Andheri West, Mumbai · 400061
- Project type
- Residential / Group Housing
- Registered on
- 28 Jun 2024
- Completion date at registration
- December 2027
- Latest completion date
- April 2028
- MahaRERA's automatic extension
- +4 months (force majeure, all eligible projects)
- Homes
- 45
- Sold or booked
- 59%
- Towers
- 1
- Complaints on MahaRERA
- 0
- Court cases listed
- 0
- Title report on file
- Not found
Construction progress of Richfeel Amalfi, as filed by the builder
What the builder has reported to MahaRERA, as GharKundli read it in October 2026. GharKundli’s full report compares it with the deadline.
| Tower / wing | Plinth | Slabs (structure) | Internal work | Lifts, fire & electrical |
|---|---|---|---|---|
| Amalfi | 0% | 0% | 0% | 0% |
Commencement certificate (CC), as filed on MahaRERA
- Amalfi: covers plinth level
Latest CC order on MahaRERA: dated 19/11/2025.
Want to know when this changes? Kundli Watch sends a free WhatsApp update on Richfeel Amalfi every 1–2 months.
Richfeel Amalfi: buildings, flats and land, as filed on MahaRERA
| Type | Carpet area (sq ft) | Units |
|---|---|---|
| 4 BHK | 1,397 – 1,546 | 23 |
| 3 BHK | 913 – 1,123 | 21 |
| Other | 9,094 | 1 |
- Buildings: Amalfi (34 floors, 45 units)
- Car parking: 68 covered
- Land: 1,243 sq m (about 0.3 acres) · sanctioned built-up 6,694 sq m · recreational space 99 sq m
- Land, as filed: 1058
- Map: Get directions
The builder’s record and reviews
Richfeel Real Estate (a group of 2 linked companies) has 2 projects on MahaRERA since 2024, this one included. Of the 2 GharKundli has checked: 2 still being built, none past the promised date yet. No complaints on MahaRERA.
Read Google reviews of Richfeel Amalfi →Reviews on Google are opinions by Google users; GharKundli doesn’t check them.
Kundli Watch
Richfeel Amalfi: buyers & owners
Free: a construction progress update on WhatsApp every 1–2 months, and straight away when anything changes on MahaRERA — a later completion date, new complaints, a red flag. Your number stays private: never shown to other members or the builder.
Be the first to watch this project.
How are you connected to this project?
Watching needs only WhatsApp or your number. Bought here? No document needed now. From the builder’s team? Join to answer buyers’ questions; you never see members’ details. Owners and the builder’s team sign in with a one-time code, then come straight back here.
Common questions about Richfeel Amalfi
What is the possession date of Richfeel Amalfi?
According to GharKundli's check of MahaRERA records (updated October 2026), the latest completion date filed on MahaRERA for Richfeel Amalfi in K/W Ward, Andheri West, Mumbai is 30 April 2028, including MahaRERA's automatic 4-month extension for all eligible projects.
Is the builder's possession date different from the MahaRERA date for Richfeel Amalfi?
Builders and listing sites often quote an earlier "target" date for handover. The completion date Richfeel Amalfi's builder has filed on MahaRERA, the official one, is 30 April 2028, per GharKundli's check of MahaRERA records. If possession is late, what counts under RERA (Section 18) is the possession date written in your agreement for sale.
What is the RERA number of Richfeel Amalfi?
According to GharKundli's check of MahaRERA records (updated October 2026), the MahaRERA registration number of Richfeel Amalfi in K/W Ward, Andheri West, Mumbai is P51800076774.
Is Richfeel Amalfi registered with MahaRERA?
According to GharKundli's check of MahaRERA records (updated October 2026), Richfeel Amalfi is registered as P51800076774 and its status is "Registered and active".
What is the current construction status of Richfeel Amalfi? How much work is done?
According to GharKundli's check of MahaRERA records (updated October 2026), Richfeel Amalfi's status on MahaRERA is "Registered and active". As filed by the builder, slab work on Amalfi is 0% done and internal work 0%. GharKundli's full report compares construction progress with the deadline.
Does Richfeel Amalfi have complaints on MahaRERA?
No complaints were listed on MahaRERA as of October 2026, per GharKundli's weekly check.
Is Richfeel Amalfi safe to buy?
According to GharKundli's check of MahaRERA records (updated October 2026), Richfeel Amalfi is registered on MahaRERA as P51800076774, its completion date has not been moved by the builder and no complaints are listed against it. GharKundli doesn't call a project safe or unsafe from these numbers alone: its full report gives a risk & trust score with every point explained.
How much GST is payable on a flat in Richfeel Amalfi?
Richfeel Amalfi is under construction, so GST applies to a new flat: 5% of the price, with no input tax credit. The lower 1% rate is only for "affordable" homes: carpet area up to 60 sq m (about 646 sq ft) in the Mumbai region, and price up to ₹45 lakh. Flats in Richfeel Amalfi start at 913 sq ft carpet, above that limit, so expect 5%. There is no GST on stamp duty or registration, and none once the occupancy certificate is issued.
What is the stamp duty and registration cost for a flat in Richfeel Amalfi?
For a flat in Richfeel Amalfi (Mumbai), stamp duty is 6% of the agreement value, or of the ready reckoner value if that's higher, including 1% Metro Cess. A woman buying in her own name pays 5%. Registration is 1% of the value, capped at ₹30,000. On a ₹1 crore flat that's about ₹6 lakh in stamp duty plus ₹30,000 registration. GharKundli's property cost calculator works it out for your price: gharkundli.com/tools/property-cost-calculator
Has Richfeel Amalfi received its OC? Is it ready to move in?
Not yet. According to GharKundli's check of MahaRERA records (updated October 2026), Richfeel Amalfi is still under construction, with 30 April 2028 as the latest completion date filed on MahaRERA. A flat is ready to move in only once the occupancy certificate (OC) is issued, after construction is complete.
Is Richfeel Amalfi a redevelopment or SRA project?
According to GharKundli's check of MahaRERA records (updated October 2026), Richfeel Amalfi is a redevelopment: 18 of its flats are set aside for existing occupants (rehab), and the rest are for sale.
Has Richfeel Amalfi uploaded its title report on MahaRERA?
According to GharKundli's check of MahaRERA records (updated October 2026), no title report for Richfeel Amalfi was found on MahaRERA. Builders are expected to upload one; before booking, ask the builder for the advocate's title certificate in writing.
No title report is on MahaRERA for this project. See which documents are missing →
How can I get updates if Richfeel Amalfi's possession date changes?
The latest dates are on Richfeel Amalfi's MahaRERA page (P51800076774). GharKundli's Kundli Watch sends a free WhatsApp update on Richfeel Amalfi every 1–2 months, and straight away when anything changes on MahaRERA: a later completion date, new complaints or a red flag. Your number is never shown to the builder.
How many floors does Richfeel Amalfi have?
According to GharKundli's check of MahaRERA records (updated October 2026), Richfeel Amalfi has one building filed: Amalfi with 34 floors and 45 units.
What are the flat sizes (carpet area) in Richfeel Amalfi?
According to GharKundli's check of MahaRERA records (updated October 2026), the builder has filed these homes for Richfeel Amalfi: 4 BHK: 1397 to 1546 sq ft carpet (23 homes); 3 BHK: 913 to 1123 sq ft carpet (21 homes); Other: 9094 sq ft carpet (1 homes). Carpet area is the usable floor area inside the walls, as defined under RERA.
How much parking does Richfeel Amalfi have?
According to GharKundli's check of MahaRERA records (updated October 2026), the builder has filed 68 covered car parking spaces for Richfeel Amalfi.
How big is the land of Richfeel Amalfi?
According to GharKundli's check of MahaRERA records (updated October 2026), Richfeel Amalfi stands on 1,243 sq m of land (about 0.3 acres), with 6,694 sq m of sanctioned built-up area and 99 sq m of recreational open space.
What is the track record of Richfeel Amalfi's builder?
According to GharKundli's check of MahaRERA records (updated October 2026), Richfeel Real Estate (a group of 2 linked companies) has 2 projects on MahaRERA since 2024, this one included. Of the 2 GharKundli has checked: 2 still being built, none past the promised date yet. No complaints on MahaRERA. GharKundli's full report covers the builder's record in detail.
What are the reviews of Richfeel Amalfi?
Google Maps has reviews of Richfeel Amalfi written by Google users; GharKundli links to them on this page but doesn't check them. For facts rather than opinions: no complaints are listed on MahaRERA, and Kundli Watch shows verified owners of the project.
What is the address and pincode of Richfeel Amalfi?
Richfeel Amalfi by RICHFEEL REAL ESTATE PVT. LTD. is in K/W Ward, Andheri West, Mumbai, pincode 400061, Maharashtra, and is registered on MahaRERA as P51800076774, per GharKundli's check of MahaRERA records. Its land is filed as 1058. GharKundli lists all 21 MahaRERA projects in Vesava (400061).
How many flats are in Richfeel Amalfi, and how many are sold?
According to GharKundli's check of MahaRERA records (updated October 2026), Richfeel Amalfi has 45 homes in 1 tower registered on MahaRERA, and 59% of them are sold or booked.
When was Richfeel Amalfi registered on MahaRERA?
According to GharKundli's check of MahaRERA records (updated October 2026), Richfeel Amalfi was registered on MahaRERA on 28 June 2024. GharKundli did not find a title report on the land on file there.
Does Richfeel Amalfi have any legal issues or court cases?
No court cases are listed for Richfeel Amalfi on MahaRERA, per GharKundli's check of MahaRERA records (updated October 2026).
Who is the builder / developer of Richfeel Amalfi?
According to GharKundli's check of MahaRERA records (updated October 2026), the builder is RICHFEEL REAL ESTATE PVT. LTD..
Check it yourself on MahaRERA
- How to check the possession date of Richfeel Amalfi
- How to find and verify a MahaRERA number
- How to check construction status on MahaRERA
- Occupancy certificate (OC): what to check before possession
- Possession delayed? Work out the interest the builder owes
- How to file a MahaRERA complaint against a builder
- Where MahaRERA complaints are: the data
- Why builders ask MahaRERA for more time: the data
All projects with possession due in 2028 in Mumbai Suburban →
Other projects in Andheri
- Shraddha West Residency
- Green Bay
- Shivsai Sra CHS
- Live Well Chs Ltd
- Esto Arkis
- Therese
- DLH One
- Fiona Garden
Data compiled by GharKundli (gharkundli.com) from MahaRERA public records, as of October 2026. Check the project’s MahaRERA page for the latest filings. Not legal advice.