Lodha Adrina
by LODHA DEVELOPERS LIMITED · Worli, MumbaiAlso near Lower Parel, Prabhadevi, Kalanagar, Bandra East
Possession: Lodha Adrina is marked completed on MahaRERA. How to check it yourself
Registered on MahaRERA under P51900014937. Status: Completed. 1 complaint is listed against it on MahaRERA.
Source: GharKundli’s check of MahaRERA records, October 2026.
What do you want to know about Lodha Adrina?
How the possession date of Lodha Adrina has moved
31 July 2024
Completion date given when the project was registered
31 December 2025
Extended at the builder's request (MahaRERA application EXT51900011141)
Reason the builder gave MahaRERA: “Delay in Launch of Project”
30 June 2026
Extended at the builder's request (MahaRERA application EA03042620547)
Reason the builder gave MahaRERA:
“the Full Occupancy Certificate dated 31th July 2025 on the MahaRERA portal for your kind reference. However, the project is currently reflecting under the category of “Lapsed Projects.” In this regard, we request you to kindly grant an exte…” Read the full reason
“the Full Occupancy Certificate dated 31th July 2025 on the MahaRERA portal for your kind reference. However, the project is currently reflecting under the category of “Lapsed Projects.” In this regard, we request you to kindly grant an extension Eighteen months (18) upto 30th June 2026 for the above-mentioned project. The purpose of seeking this extension is to complete necessary corrections and updates, including alignment of BUA, Units, FSI, and other project details with the approved Full Occupancy Certificate plans”
Source: Lodha Adrina’s extension records on MahaRERA (P51900014937), read by GharKundli in October 2026. The builder’s reasons are quoted as filed. Your own possession date is the one in your agreement for sale.
What builders tell MahaRERA when they’re late: 14,973 applications analysed →GharKundli’s full report on Lodha Adrina
Read from every filing on MahaRERA when you open it
- Risk & trust score, every point explained
- What the title report says about the land
- Each of the 1 complaint, and how it ended
- Construction pace against the June 2026 deadline
- Agreement clauses weaker than the RERA model
- Escrow audit, loans and the builder's record
- Questions to get answered in writing before you pay
- MahaRERA registration
- P51900014937
- Status
- Completed
- Builder
- LODHA DEVELOPERS LIMITED
- Location
- Worli, Mumbai · 400013
- Project type
- Residential / Group Housing
- Registered on
- 15 Jan 2018
- Completion date at registration
- July 2024
- Latest completion date
- June 2026
- Delay so far
- 23 months
- Homes
- 401
- Sold or booked
- 60%
- Towers
- 1
- Complaints on MahaRERA
- 1
- Court cases listed
- 0
- Title report on file
- Not found
- Builder's other MahaRERA projects
- 180
Construction progress of Lodha Adrina, as filed by the builder
What the builder has reported to MahaRERA, as GharKundli read it in October 2026. GharKundli’s full report compares it with the deadline.
| Tower / wing | Plinth | Slabs (structure) | Internal work | Lifts, fire & electrical |
|---|---|---|---|---|
| Wing 6 | 100% | 100% | 100% | 90% |
Commencement certificate (CC), as filed on MahaRERA
- Wing 6: covers 71 floors
Latest CC order on MahaRERA: dated 04/12/2024.
Want to know when this changes? Kundli Watch sends a free WhatsApp update on Lodha Adrina every month.
Lodha Adrina: buildings, flats and land, as filed on MahaRERA
| Type | Carpet area (sq ft) | Units |
|---|---|---|
| Other | 936 – 2,455 | 343 |
| 2 BHK | 918 | 58 |
- Buildings: Wing 6 (71 floors, 401 units)
- Car parking: 751 covered
- Land: 2,241 sq m (about 0.6 acres) · sanctioned built-up 47,632 sq m · recreational space 1,420 sq m
- Boundaries filed include: Senapati Bapat Marg
- Map: the location the builder filed on MahaRERA
The builder’s record and reviews
Lodha (Macrotech) (a group of 4 linked companies) has 387 projects on MahaRERA since 2017, this one included. Of the 375 GharKundli has checked: 208 finished, 190 within the promised date and 18 needed more time (typically 11 months); 167 still being built, 13 past the promised date (typically 3 months late). 584 complaints on MahaRERA across 155 projects.
Read Google reviews of Lodha Adrina →Reviews on Google are opinions by Google users; GharKundli doesn’t check them.
Kundli Watch
Lodha Adrina: buyers & owners
Free: a WhatsApp update every month on this project, and straight away when anything changes on MahaRERA — a later completion date, new complaints, a red flag. Your number stays private: never shown to other members or the builder.
Be the first to watch this project.
How are you connected to this project?
Bought here? No document needed now. From the builder’s team? Join to answer buyers’ questions; you never see members’ details. You’ll sign in with a one-time code, then come straight back here.
Common questions about Lodha Adrina
What is the possession date of Lodha Adrina?
According to GharKundli's check of MahaRERA records (updated October 2026), the latest completion date filed on MahaRERA for Lodha Adrina in Worli, Mumbai is 30 June 2026 — 23 months later than 31 July 2024, the date given at registration.
Is the builder's possession date different from the MahaRERA date for Lodha Adrina?
Builders and listing sites often quote an earlier "target" date for handover. The completion date Lodha Adrina's builder has filed on MahaRERA, the official one, is 30 June 2026, already 23 months later than the 31 July 2024 given at registration, per GharKundli's check of MahaRERA records. If possession is late, what counts under RERA (Section 18) is the possession date written in your agreement for sale.
Why was the possession date of Lodha Adrina extended?
According to GharKundli's check of MahaRERA records (updated October 2026), Lodha Adrina's builder applied to MahaRERA to extend the completion date 2 times: to 31 December 2025, giving the reason "Delay in Launch of Project"; to 30 June 2026, giving the reason "the Full Occupancy Certificate dated 31th July 2025 on the MahaRERA portal for your kind reference. However, the project is currently reflecting under the category of “Lapsed Projects.” In this regard, we request you to kindly grant an extension Eighteen months (18) upto 30th June 2026 for the above-mentioned project. The purpose of seeking this extension is to complete necessary corrections and updates, including alignment of BUA, Units, FSI, and other project details with the approved Full Occupancy Certificate plans".
What is the RERA number of Lodha Adrina?
According to GharKundli's check of MahaRERA records (updated October 2026), the MahaRERA registration number of Lodha Adrina in Worli, Mumbai is P51900014937.
Is Lodha Adrina registered with MahaRERA?
According to GharKundli's check of MahaRERA records (updated October 2026), Lodha Adrina is registered as P51900014937 and its status is "Completed".
What is the construction status of Lodha Adrina?
According to GharKundli's check of MahaRERA records (updated October 2026), Lodha Adrina's status on MahaRERA is "Completed". As filed by the builder, slab work on Wing 6 is 100% done and internal work 100%. GharKundli's full report compares construction progress with the deadline.
Does Lodha Adrina have complaints on MahaRERA?
1 complaint was listed on MahaRERA as of October 2026, per GharKundli's weekly check. GharKundli's full report explains each case and how it ended.
Is Lodha Adrina safe to buy?
According to GharKundli's check of MahaRERA records (updated October 2026), Lodha Adrina is registered on MahaRERA as P51900014937, its MahaRERA status is "Completed", its completion date has moved 23 months since registration and 1 complaint is listed against it. GharKundli doesn't call a project safe or unsafe from these numbers alone: its full report gives a risk & trust score with every point explained.
How can I get updates if Lodha Adrina's possession date changes?
The latest dates are on Lodha Adrina's MahaRERA page (P51900014937). GharKundli's Kundli Watch sends a free WhatsApp update on Lodha Adrina every month, and straight away when anything changes on MahaRERA: a later completion date, new complaints or a red flag. Your number is never shown to the builder.
How many floors does Lodha Adrina have?
According to GharKundli's check of MahaRERA records (updated October 2026), Lodha Adrina has one building filed: Wing 6 with 71 floors and 401 units.
What are the flat sizes (carpet area) in Lodha Adrina?
According to GharKundli's check of MahaRERA records (updated October 2026), the builder has filed these homes for Lodha Adrina: Other: 936 to 2455 sq ft carpet (343 homes); 2 BHK: 918 sq ft carpet (58 homes). Carpet area is the usable floor area inside the walls, as defined under RERA.
How much parking does Lodha Adrina have?
According to GharKundli's check of MahaRERA records (updated October 2026), the builder has filed 751 covered car parking spaces for Lodha Adrina.
How big is the land of Lodha Adrina?
According to GharKundli's check of MahaRERA records (updated October 2026), Lodha Adrina stands on 2,241 sq m of land (about 0.6 acres), with 47,632 sq m of sanctioned built-up area and 1,420 sq m of recreational open space.
What is the track record of Lodha Adrina's builder?
According to GharKundli's check of MahaRERA records (updated October 2026), Lodha (Macrotech) (a group of 4 linked companies) has 387 projects on MahaRERA since 2017, this one included. Of the 375 GharKundli has checked: 208 finished, 190 within the promised date and 18 needed more time (typically 11 months); 167 still being built, 13 past the promised date (typically 3 months late). 584 complaints on MahaRERA across 155 projects. GharKundli's full report covers the builder's record in detail.
Where can I read reviews of Lodha Adrina?
Google Maps has reviews of Lodha Adrina written by Google users; GharKundli links to them on this page but doesn't check them. For facts rather than opinions: 1 complaint is listed on MahaRERA, and Kundli Watch shows verified owners of the project.
Where is Lodha Adrina?
Lodha Adrina by LODHA DEVELOPERS LIMITED is in Worli, Mumbai (pincode 400013), near Lower Parel, Prabhadevi, Kalanagar, Bandra East, Maharashtra, and is registered on MahaRERA as P51900014937, per GharKundli's check of MahaRERA records. Its boundaries filed there include Senapati Bapat Marg.
How many homes are in Lodha Adrina?
According to GharKundli's check of MahaRERA records (updated October 2026), Lodha Adrina has 401 homes in 1 tower registered on MahaRERA, and 60% of them are sold or booked.
When was Lodha Adrina registered on MahaRERA?
According to GharKundli's check of MahaRERA records (updated October 2026), Lodha Adrina was registered on MahaRERA on 15 January 2018. GharKundli did not find a title report on the land on file there.
Are there court cases on Lodha Adrina?
No court cases are listed for Lodha Adrina on MahaRERA, per GharKundli's check of MahaRERA records (updated October 2026).
Who is the builder of Lodha Adrina?
According to GharKundli's check of MahaRERA records (updated October 2026), the builder is LODHA DEVELOPERS LIMITED, which has 180 other projects registered on MahaRERA.
Check it yourself on MahaRERA
- How to check the possession date of Lodha Adrina
- How to find and verify a MahaRERA number
- How to check construction status on MahaRERA
- Occupancy certificate (OC): what to check before possession
- Possession delayed? Work out the interest the builder owes
- How to file a MahaRERA complaint against a builder
- Where MahaRERA complaints are: the data
- Why builders ask MahaRERA for more time: the data
Other projects in Worli
- Lodha Promina
- AKSHAY
- Prestige Nautilus
- Birla Niyaara Phase-2
- Mahindra Marina64 - Phase 1
- Mahindra Marina64 - Phase 2
- Lodha Worli Residential Project
- Mahindra Marina64 - Phase 3
Other projects by LODHA DEVELOPERS LIMITED
Data compiled by GharKundli (gharkundli.com) from MahaRERA public records, as of October 2026. Check the project’s MahaRERA page for the latest filings. Not legal advice.