by Lalitambika Builders & Developers Private Limited · Worli, MumbaiAlso near Lower Parel, Kalanagar, Bandra East, Delisle Road

Possession date of AKSHAY: 29 December 2026, moved from 30 December 2023 (36 months later). This is the latest completion date the builder has filed on MahaRERA. How to check it yourself

Registered on MahaRERA under P51900021927, and currently active. 1 complaint is listed against it on MahaRERA.

Source: GharKundli’s check of MahaRERA records, October 2026.

What do you want to know about AKSHAY?

Ask us on WhatsAppNo login needed. A real person replies.

How the possession date of AKSHAY has moved

  1. 30 December 2023

    Completion date given when the project was registered

  2. 29 December 2024

    Extended at the builder's request (MahaRERA application EXT51900018184)

    Reason the builder gave MahaRERA:
    “The project Akshay comprising of one sale building is completed in all respects and infact occupancy permissions for all the flats in the sale building have been issued by MCGM authorities way back on 9th March 2023 by way of part Occupancy…” Read the full reason“The project Akshay comprising of one sale building is completed in all respects and infact occupancy permissions for all the flats in the sale building have been issued by MCGM authorities way back on 9th March 2023 by way of part Occupancy certificate copy of the said occupancy certificate is attached herewith for your information and records. As can be seen from the Occupancy certificate, all the units in the sale building have been permitted to occupy save and accept one sale NR office which is proposed at Ground floor level it is to be mentioned here that no third party rights have been…”
  3. 29 December 2025

    Extended at the builder's request (MahaRERA application EXT51900024927)

    Reason the builder gave MahaRERA:
    “Reason for Extension and status of Project : 3.1 The Project ‘Akshay’ is comprising of Wing A and Wing B being the sale component in the subject property. The remaining Wing C and D is a rehab building for accommodation of Municipal Tenants…” Read the full reason“Reason for Extension and status of Project : 3.1 The Project ‘Akshay’ is comprising of Wing A and Wing B being the sale component in the subject property. The remaining Wing C and D is a rehab building for accommodation of Municipal Tenants. 3.2 The MCGM has issued Occupation Certificate for all the Flats comprised in the New Building i.e. Wing A and Wing B on 09-03-2023 and Wing C and Wing D on 01-12-2020, except for a single NR office located on the ground level of Wing B; 3.3 After receipt of Occupation certificate, all the Allottees and municipal tenant has been accommodated in their re…”
  4. 29 December 2026

    Extended at the builder's request (MahaRERA application EA13022619830)

    Reason the builder gave MahaRERA:
    “Reason for Extension and status of Project : 3.1 The Project ‘Akshay’ is comprising of Wing A and Wing B being the sale component in the subject property. 3.2 The MCGM issued the Occupation Certificate for all flats in the new building, com…” Read the full reason“Reason for Extension and status of Project : 3.1 The Project ‘Akshay’ is comprising of Wing A and Wing B being the sale component in the subject property. 3.2 The MCGM issued the Occupation Certificate for all flats in the new building, comprising Wing A and Wing B, on 09/03/2023, except for one NR office located on the ground floor of Wing B. 3.3 The Occupation Certificate for single NR Office is restricted by MCGM for the very reason that there are some encroachment on the small portion of the subject plot and MCGM being the owner of the subject Plot, is unable to remove the encroachments…”

Source: AKSHAY’s extension records on MahaRERA (P51900021927), read by GharKundli in October 2026. The builder’s reasons are quoted as filed. Your own possession date is the one in your agreement for sale.

What builders tell MahaRERA when they’re late: 14,973 applications analysed →

GharKundli’s full report on AKSHAY

Read from every filing on MahaRERA when you open it

  • Risk & trust score, every point explained
  • What the title report says about the land
  • Each of the 1 complaint, and how it ended
  • Construction pace against the December 2026 deadline
  • Agreement clauses weaker than the RERA model
  • Escrow audit, loans and the builder's record
  • Questions to get answered in writing before you pay
MahaRERA registration
P51900021927
Status
Registered and active
Builder
Lalitambika Builders & Developers Private Limited
Location
Worli, Mumbai · 400013
Project type
Others
Registered on
8 Aug 2019
Completion date at registration
December 2023
Latest completion date
December 2026
Delay so far
36 months
Homes
93
Sold or booked
100%
Towers
1
Complaints on MahaRERA
1
Court cases listed
0
Appeals at the tribunal
2
Title report on file
Not found

Construction progress of AKSHAY, as filed by the builder

What the builder has reported to MahaRERA, as GharKundli read it in October 2026. GharKundli’s full report compares it with the deadline.

Tower / wingPlinthSlabs (structure)Internal workLifts, fire & electrical
AKSHAY WING A and B100%100%100%100%

Commencement certificate (CC), as filed on MahaRERA

  • AKSHAY WING A and B: covers 19 floors

Want to know when this changes? Kundli Watch sends a free WhatsApp update on AKSHAY every month.

AKSHAY: buildings, flats and land, as filed on MahaRERA

TypeCarpet area (sq ft)Units
1 BHK424 – 43562
2 BHK605 – 61030
Shops132 – 1502
3 BHK6981

The builder’s record and reviews

Not enough of this builder’s other MahaRERA projects have reached their promised date to judge yet.

Read Google reviews of AKSHAY →Reviews on Google are opinions by Google users; GharKundli doesn’t check them.

Kundli Watch

AKSHAY: buyers & owners

Free: a WhatsApp update every month on this project, and straight away when anything changes on MahaRERA — a later completion date, new complaints, a red flag. Your number stays private: never shown to other members or the builder.

Be the first to watch this project.

How are you connected to this project?

Bought here? No document needed now. From the builder’s team? Join to answer buyers’ questions; you never see members’ details. You’ll sign in with a one-time code, then come straight back here.

Common questions about AKSHAY

What is the possession date of AKSHAY?

According to GharKundli's check of MahaRERA records (updated October 2026), the latest completion date filed on MahaRERA for AKSHAY in Worli, Mumbai is 29 December 2026 — 36 months later than 30 December 2023, the date given at registration.

Is the builder's possession date different from the MahaRERA date for AKSHAY?

Builders and listing sites often quote an earlier "target" date for handover. The completion date AKSHAY's builder has filed on MahaRERA, the official one, is 29 December 2026, already 36 months later than the 30 December 2023 given at registration, per GharKundli's check of MahaRERA records. If possession is late, what counts under RERA (Section 18) is the possession date written in your agreement for sale.

Why was the possession date of AKSHAY extended?

According to GharKundli's check of MahaRERA records (updated October 2026), AKSHAY's builder applied to MahaRERA to extend the completion date 3 times: to 29 December 2024, giving the reason "The project Akshay comprising of one sale building is completed in all respects and infact occupancy permissions for all the flats in the sale building have been issued by MCGM authorities way back on 9th March 2023 by way of part Occupancy certificate copy of the said occupancy certificate is attached herewith for your information and records. As can be seen from the Occupancy certificate, all the units in the sale building have been permitted to occupy save and accept one sale NR office which is proposed at Ground floor level it is to be mentioned here that no third party rights have been…"; to 29 December 2025, giving the reason "Reason for Extension and status of Project : 3.1 The Project ‘Akshay’ is comprising of Wing A and Wing B being the sale component in the subject property. The remaining Wing C and D is a rehab building for accommodation of Municipal Tenants. 3.2 The MCGM has issued Occupation Certificate for all the Flats comprised in the New Building i.e. Wing A and Wing B on 09-03-2023 and Wing C and Wing D on 01-12-2020, except for a single NR office located on the ground level of Wing B; 3.3 After receipt of Occupation certificate, all the Allottees and municipal tenant has been accommodated in their re…"; to 29 December 2026, giving the reason "Reason for Extension and status of Project : 3.1 The Project ‘Akshay’ is comprising of Wing A and Wing B being the sale component in the subject property. 3.2 The MCGM issued the Occupation Certificate for all flats in the new building, comprising Wing A and Wing B, on 09/03/2023, except for one NR office located on the ground floor of Wing B. 3.3 The Occupation Certificate for single NR Office is restricted by MCGM for the very reason that there are some encroachment on the small portion of the subject plot and MCGM being the owner of the subject Plot, is unable to remove the encroachments…".

What is the RERA number of AKSHAY?

According to GharKundli's check of MahaRERA records (updated October 2026), the MahaRERA registration number of AKSHAY in Worli, Mumbai is P51900021927.

Is AKSHAY registered with MahaRERA?

According to GharKundli's check of MahaRERA records (updated October 2026), AKSHAY is registered as P51900021927 and its status is "Registered and active".

What is the construction status of AKSHAY?

According to GharKundli's check of MahaRERA records (updated October 2026), AKSHAY's status on MahaRERA is "Registered and active". As filed by the builder, slab work on AKSHAY WING A and B is 100% done and internal work 100%. GharKundli's full report compares construction progress with the deadline.

Does AKSHAY have complaints on MahaRERA?

1 complaint was listed on MahaRERA as of October 2026, per GharKundli's weekly check. GharKundli's full report explains each case and how it ended.

Is AKSHAY safe to buy?

According to GharKundli's check of MahaRERA records (updated October 2026), AKSHAY is registered on MahaRERA as P51900021927, its completion date has moved 36 months since registration and 1 complaint is listed against it. GharKundli doesn't call a project safe or unsafe from these numbers alone: its full report gives a risk & trust score with every point explained.

How can I get updates if AKSHAY's possession date changes?

The latest dates are on AKSHAY's MahaRERA page (P51900021927). GharKundli's Kundli Watch sends a free WhatsApp update on AKSHAY every month, and straight away when anything changes on MahaRERA: a later completion date, new complaints or a red flag. Your number is never shown to the builder.

How many floors does AKSHAY have?

According to GharKundli's check of MahaRERA records (updated October 2026), AKSHAY has one building filed: AKSHAY WING A and B with 22 floors and 95 units.

What are the flat sizes (carpet area) in AKSHAY?

According to GharKundli's check of MahaRERA records (updated October 2026), the builder has filed these homes for AKSHAY: 1 BHK: 424 to 435 sq ft carpet (62 homes); 2 BHK: 605 to 610 sq ft carpet (30 homes); 3 BHK: 698 sq ft carpet (1 homes). Carpet area is the usable floor area inside the walls, as defined under RERA.

How big is the land of AKSHAY?

According to GharKundli's check of MahaRERA records (updated October 2026), AKSHAY stands on 1,991 sq m of land (about 0.5 acres), with 5,141 sq m of sanctioned built-up area and 133 sq m of recreational open space.

Where can I read reviews of AKSHAY?

Google Maps has reviews of AKSHAY written by Google users; GharKundli links to them on this page but doesn't check them. For facts rather than opinions: 1 complaint is listed on MahaRERA, and Kundli Watch shows verified owners of the project.

Where is AKSHAY?

AKSHAY by Lalitambika Builders & Developers Private Limited is in Worli, Mumbai (pincode 400013), near Lower Parel, Kalanagar, Bandra East, Delisle Road, Maharashtra, and is registered on MahaRERA as P51900021927, per GharKundli's check of MahaRERA records.

How many homes are in AKSHAY?

According to GharKundli's check of MahaRERA records (updated October 2026), AKSHAY has 93 homes in 1 tower registered on MahaRERA, and 100% of them are sold or booked.

When was AKSHAY registered on MahaRERA?

According to GharKundli's check of MahaRERA records (updated October 2026), AKSHAY was registered on MahaRERA on 8 August 2019. GharKundli did not find a title report on the land on file there.

Are there court cases on AKSHAY?

No court cases are listed for AKSHAY on MahaRERA, and 2 appeals at the tribunal, per GharKundli's check of MahaRERA records (updated October 2026). GharKundli's full report explains each case and how it ended.

Who is the builder of AKSHAY?

According to GharKundli's check of MahaRERA records (updated October 2026), the builder is Lalitambika Builders & Developers Private Limited.

All projects with possession due in 2026 in Mumbai City →

Other projects in Worli

All 61 projects in Lower Parel (400013) →

Data compiled by GharKundli (gharkundli.com) from MahaRERA public records, as of October 2026. Check the project’s MahaRERA page for the latest filings. Not legal advice.