BALI PRIMERA

by BALI LANDMARKS LLP · Goregaon (W), Mumbai

Registered on MahaRERA under P51800077934, and currently active. Its completion date has moved from September 2027 to January 2028, 4 months later.

Source: GharKundli’s check of MahaRERA records, October 2026.

GharKundli’s full report on BALI PRIMERA

Read from every filing on MahaRERA when you open it

  • Risk & trust score, every point explained
  • What the title report says about the land
  • Each complaint and court case, and how it ended
  • Construction pace against the deadline
  • Agreement clauses weaker than the RERA model
  • Escrow audit, loans and the builder's record
  • Questions to get answered in writing before you pay
MahaRERA registration
P51800077934
Status
Registered and active
Builder
BALI LANDMARKS LLP
Location
Goregaon (W), Mumbai · 400104
Project type
Others
Registered on
13 Nov 2024
Completion date at registration
September 2027
Latest completion date
January 2028
Delay so far
4 months
Homes
25
Sold or booked
67%
Towers
1
Complaints on MahaRERA
0
Court cases listed
0
Title report on file
Not found
Builder's other MahaRERA projects
1

Kundli Watch

BALI PRIMERA: buyers & owners

Free. You talk to our team privately — no one sees your number.

How are you connected to this project?

You’ll sign in with your mobile number first, then come straight back here.

Common questions about BALI PRIMERA

Is BALI PRIMERA registered with MahaRERA?

According to GharKundli's check of MahaRERA records (updated October 2026), BALI PRIMERA is registered as P51800077934 and its status is "Registered and active".

Where is BALI PRIMERA?

BALI PRIMERA by BALI LANDMARKS LLP is in Goregaon (W), Mumbai (pincode 400104), Maharashtra, and is registered on MahaRERA as P51800077934, per GharKundli's check of MahaRERA records.

When is possession of BALI PRIMERA due?

According to GharKundli's check of MahaRERA records (updated October 2026), the latest completion date filed on MahaRERA for BALI PRIMERA in Goregaon (W), Mumbai is 30 January 2028 — 4 months later than 30 September 2027, the date given at registration.

Does BALI PRIMERA have complaints on MahaRERA?

No complaints were listed on MahaRERA as of October 2026, per GharKundli's weekly check. GharKundli's full report explains each case and how it ended.

Who is the builder of BALI PRIMERA?

According to GharKundli's check of MahaRERA records (updated October 2026), the builder is BALI LANDMARKS LLP, which has 1 other project registered on MahaRERA.

Other projects in pincode 400104

Data compiled by GharKundli (gharkundli.com) from MahaRERA public records, as of October 2026. Check the project’s MahaRERA page for the latest filings. Not legal advice.