Platinum Crest
by PLATINUMCORP ELEGANT HOUSING LLP (Platinum) · D N Nagar Andheri West, Mumbai 400053
What’s in the report? →Possession date of Platinum Crest (MahaRERA P51800079919): 30 April 2029. It has 128 homes (1 BHK and 2 BHK, 415–610 sq ft carpet), 27% sold or booked. No complaints on MahaRERA. How to check it yourself
Registered on MahaRERA under P51800079919, and currently active. Its completion date is now April 2029, including MahaRERA's automatic 4-month extension for all eligible projects; the builder hasn't asked for more time.
Source: MahaRERA website — records for P51800079919, read and compiled by GharKundli. Facts as filed on MahaRERA, no opinions.
What do you want to know about Platinum Crest?
7 court cases MahaRERA par listed. Kya jaanna hai?Tap a question. We’ll answer you on WhatsApp, free.
How the possession date of Platinum Crest has moved
31 December 2028
Completion date given when the project was registered
30 April 2029
MahaRERA's automatic 4-month extension for all eligible projects, not the builder's request
Source: Platinum Crest’s extension records on MahaRERA (P51800079919), read by GharKundli in October 2026. The builder’s reasons are quoted as filed. Your own possession date is the one in your agreement for sale.
What builders tell MahaRERA when they’re late: 14,973 applications analysed →GharKundli’s full report on Platinum Crest
Read from every filing on MahaRERA when you open it
- Risk & trust score, every point explained
- What the title report says about the land
- Each of the 7 court cases, and how it ended
- Construction pace against the April 2029 deadline
- Agreement clauses weaker than the RERA model
- Escrow audit, loans and the builder's record
- Questions to get answered in writing before you pay
- MahaRERA registration
- P51800079919
- Status
- Registered and active
- Builder
- PLATINUMCORP ELEGANT HOUSING LLP
- Location
- D N Nagar Andheri West, Mumbai · 400053
- Project type
- Residential / Group Housing
- Registered on
- 1 Apr 2025
- Completion date at registration
- December 2028
- Latest completion date
- April 2029
- MahaRERA's automatic extension
- +4 months (force majeure, all eligible projects)
- Homes
- 128
- Sold or booked
- 27%
- Towers
- 1
- Complaints on MahaRERA
- 0
- Court cases listed
- 7
- Title report on file
- Not found
Construction progress of Platinum Crest, as filed by the builder
What the builder has reported to MahaRERA, as GharKundli read it in October 2026. GharKundli’s full report compares it with the deadline.
| Tower / wing | Plinth | Slabs (structure) | Internal work | Lifts, fire & electrical |
|---|---|---|---|---|
| D N NAGAR SAI KRUPA CHSL, BUILDING NO 27 | 0% | 0% | 0% | 0% |
Commencement certificate (CC), as filed on MahaRERA
- D N NAGAR SAI KRUPA CHSL, BUILDING NO 27: covers CC Issued up to Plinth
Latest CC order on MahaRERA: dated 31/10/2025.
Want to know when this changes? Kundli Watch sends a free WhatsApp update on Platinum Crest every 1–2 months.
Platinum Crest: buildings, flats and land, as filed on MahaRERA
| Type | Carpet area (sq ft) | Units |
|---|---|---|
| 2 BHK | 560 – 610 | 95 |
| 1 BHK | 415 – 560 | 33 |
- Buildings: D N NAGAR SAI KRUPA CHSL, BUILDING NO 27 (18 floors, 128 units)
- Car parking: 90 covered
- Land: 1,057 sq m (about 0.3 acres) · sanctioned built-up 7,435 sq m
- Land, as filed: CTS No. 195 PT BLDG No. 27
- Map: Get directions
The builder’s record and reviews
Platinumcorp Urban Developers (a group of 15 linked companies) has 16 projects on MahaRERA since 2017, this one included. Of the 16 GharKundli has checked: 8 finished, 5 within the promised date and 3 needed more time (typically 9 months); 8 still being built, 1 past the promised date (typically 6 months late). 20 complaints on MahaRERA across 5 projects.
Read Google reviews of Platinum Crest →Reviews on Google are opinions by Google users; GharKundli doesn’t check them.
Kundli Watch
Platinum Crest: buyers & owners
Free: a construction progress update on WhatsApp every 1–2 months, and straight away when anything changes on MahaRERA — a later completion date, new complaints, a red flag. Your number stays private: never shown to other members or the builder.
Be the first to watch this project.
How are you connected to this project?
Watching needs only WhatsApp or your number. Bought here? No document needed now. From the builder’s team? Join to answer buyers’ questions; you never see members’ details. Owners and the builder’s team sign in with a one-time code, then come straight back here.
Common questions about Platinum Crest
What is the possession date of Platinum Crest?
According to GharKundli's check of MahaRERA records (updated October 2026), the latest completion date filed on MahaRERA for Platinum Crest in D N Nagar Andheri West, Mumbai is 30 April 2029, including MahaRERA's automatic 4-month extension for all eligible projects.
Is the builder's possession date different from the MahaRERA date for Platinum Crest?
Builders and listing sites often quote an earlier "target" date for handover. The completion date Platinum Crest's builder has filed on MahaRERA, the official one, is 30 April 2029, per GharKundli's check of MahaRERA records. If possession is late, what counts under RERA (Section 18) is the possession date written in your agreement for sale.
What is the RERA number of Platinum Crest?
According to GharKundli's check of MahaRERA records (updated October 2026), the MahaRERA registration number of Platinum Crest in D N Nagar Andheri West, Mumbai is P51800079919.
Is Platinum Crest registered with MahaRERA?
According to GharKundli's check of MahaRERA records (updated October 2026), Platinum Crest is registered as P51800079919 and its status is "Registered and active".
What is the current construction status of Platinum Crest? How much work is done?
According to GharKundli's check of MahaRERA records (updated October 2026), Platinum Crest's status on MahaRERA is "Registered and active". As filed by the builder, slab work on D N NAGAR SAI KRUPA CHSL, BUILDING NO 27 is 0% done and internal work 0%. GharKundli's full report compares construction progress with the deadline.
Does Platinum Crest have complaints on MahaRERA?
No complaints were listed on MahaRERA as of October 2026, per GharKundli's weekly check.
Is Platinum Crest safe to buy?
According to GharKundli's check of MahaRERA records (updated October 2026), Platinum Crest is registered on MahaRERA as P51800079919, its completion date has not been moved by the builder and no complaints are listed against it. GharKundli doesn't call a project safe or unsafe from these numbers alone: its full report gives a risk & trust score with every point explained.
How much GST is payable on a flat in Platinum Crest?
Platinum Crest is under construction, so GST applies to a new flat: 5% of the price, with no input tax credit. The lower 1% rate is only for "affordable" homes: carpet area up to 60 sq m (about 646 sq ft) in the Mumbai region, and price up to ₹45 lakh. Some flats in Platinum Crest are 415 sq ft carpet, small enough for 1% if the price is ₹45 lakh or less. There is no GST on stamp duty or registration, and none once the occupancy certificate is issued.
What is the stamp duty and registration cost for a flat in Platinum Crest?
For a flat in Platinum Crest (Mumbai), stamp duty is 6% of the agreement value, or of the ready reckoner value if that's higher, including 1% Metro Cess. A woman buying in her own name pays 5%. Registration is 1% of the value, capped at ₹30,000. On a ₹1 crore flat that's about ₹6 lakh in stamp duty plus ₹30,000 registration. GharKundli's property cost calculator works it out for your price: gharkundli.com/tools/property-cost-calculator
Has Platinum Crest received its OC? Is it ready to move in?
Not yet. According to GharKundli's check of MahaRERA records (updated October 2026), Platinum Crest is still under construction, with 30 April 2029 as the latest completion date filed on MahaRERA. A flat is ready to move in only once the occupancy certificate (OC) is issued, after construction is complete.
Has Platinum Crest uploaded its title report on MahaRERA?
According to GharKundli's check of MahaRERA records (updated October 2026), no title report for Platinum Crest was found on MahaRERA. Builders are expected to upload one; before booking, ask the builder for the advocate's title certificate in writing.
No title report is on MahaRERA for this project. See which documents are missing →
How can I get updates if Platinum Crest's possession date changes?
The latest dates are on Platinum Crest's MahaRERA page (P51800079919). GharKundli's Kundli Watch sends a free WhatsApp update on Platinum Crest every 1–2 months, and straight away when anything changes on MahaRERA: a later completion date, new complaints or a red flag. Your number is never shown to the builder.
How many floors does Platinum Crest have?
According to GharKundli's check of MahaRERA records (updated October 2026), Platinum Crest has one building filed: D N NAGAR SAI KRUPA CHSL, BUILDING NO 27 with 18 floors and 128 units.
What are the flat sizes (carpet area) in Platinum Crest?
According to GharKundli's check of MahaRERA records (updated October 2026), the builder has filed these homes for Platinum Crest: 2 BHK: 560 to 610 sq ft carpet (95 homes); 1 BHK: 415 to 560 sq ft carpet (33 homes). Carpet area is the usable floor area inside the walls, as defined under RERA.
How much parking does Platinum Crest have?
According to GharKundli's check of MahaRERA records (updated October 2026), the builder has filed 90 covered car parking spaces for Platinum Crest.
How big is the land of Platinum Crest?
According to GharKundli's check of MahaRERA records (updated October 2026), Platinum Crest stands on 1,057 sq m of land (about 0.3 acres), with 7,435 sq m of sanctioned built-up area.
What is the track record of Platinum Crest's builder?
According to GharKundli's check of MahaRERA records (updated October 2026), Platinumcorp Urban Developers (a group of 15 linked companies) has 16 projects on MahaRERA since 2017, this one included. Of the 16 GharKundli has checked: 8 finished, 5 within the promised date and 3 needed more time (typically 9 months); 8 still being built, 1 past the promised date (typically 6 months late). 20 complaints on MahaRERA across 5 projects. GharKundli's full report covers the builder's record in detail.
What are the reviews of Platinum Crest?
Google Maps has reviews of Platinum Crest written by Google users; GharKundli links to them on this page but doesn't check them. For facts rather than opinions: no complaints are listed on MahaRERA, and Kundli Watch shows verified owners of the project.
What is the address and pincode of Platinum Crest?
Platinum Crest by PLATINUMCORP ELEGANT HOUSING LLP (Platinum) is in D N Nagar Andheri West, Mumbai, pincode 400053, Maharashtra, and is registered on MahaRERA as P51800079919, per GharKundli's check of MahaRERA records. Its land is filed as CTS No. 195 PT BLDG No. 27. GharKundli lists all 162 MahaRERA projects in Andheri West (400053).
How many flats are in Platinum Crest, and how many are sold?
According to GharKundli's check of MahaRERA records (updated October 2026), Platinum Crest has 128 homes in 1 tower registered on MahaRERA, and 27% of them are sold or booked.
When was Platinum Crest registered on MahaRERA?
According to GharKundli's check of MahaRERA records (updated October 2026), Platinum Crest was registered on MahaRERA on 1 April 2025. GharKundli did not find a title report on the land on file there.
Does Platinum Crest have any legal issues or court cases?
7 court cases are listed for Platinum Crest on MahaRERA, per GharKundli's check of MahaRERA records (updated October 2026). GharKundli's full report explains each case and how it ended.
A court case can stall a project or tie up the land. See what each case is about →
Who is the builder / developer of Platinum Crest?
According to GharKundli's check of MahaRERA records (updated October 2026), the builder is PLATINUMCORP ELEGANT HOUSING LLP, the company Platinum files this project under.
Check it yourself on MahaRERA
- How to check the possession date of Platinum Crest
- How to find and verify a MahaRERA number
- How to check construction status on MahaRERA
- Occupancy certificate (OC): what to check before possession
- Possession delayed? Work out the interest the builder owes
- How to file a MahaRERA complaint against a builder
- Where MahaRERA complaints are: the data
- Why builders ask MahaRERA for more time: the data
All projects with possession due in 2029 in Mumbai Suburban →
Other projects in Andheri
- Shraddha West Residency
- Shivsai Sra CHS
- Live Well Chs Ltd
- Green Bay
- Pruthvi Symphony
- Therese
- KK 415 West
- Venus CHS
Data compiled by GharKundli (gharkundli.com) from MahaRERA public records, as of October 2026. Check the project’s MahaRERA page for the latest filings. Not legal advice.