PARAS GOREGAON CO-OP HSG SOC LTD
by Madhav Enterprise · Goregaon West, Mumbai
Registered on MahaRERA under PM1180002501006, and currently active. Its completion date has moved from December 2028 to April 2029, 4 months later.
Source: GharKundli’s check of MahaRERA records, October 2026.
- MahaRERA registration
- PM1180002501006
- Status
- Registered and active
- Builder
- Madhav Enterprise
- Location
- Goregaon West, Mumbai · 400104
- Project type
- Mixed
- Registered on
- 29 Sep 2025
- Completion date at registration
- December 2028
- Latest completion date
- April 2029
- Delay so far
- 4 months
- Homes
- 6
- Sold or booked
- 0%
- Towers
- 1
- Complaints on MahaRERA
- 0
- Court cases listed
- 0
- Title report on file
- Not found
GharKundli’s full report on PARAS GOREGAON CO-OP HSG SOC LTD
Read from every filing on MahaRERA when you open it
- Risk & trust score, every point explained
- What the title report says about the land
- Each complaint and court case, and how it ended
- Construction pace against the deadline
- Agreement clauses weaker than the RERA model
- Escrow audit, loans and the builder's record
- Questions to get answered in writing before you pay
Kundli Watch
PARAS GOREGAON CO-OP HSG SOC LTD: buyers & owners
Free. You talk to our team privately — no one sees your number.
How are you connected to this project?
You’ll sign in with your mobile number first, then come straight back here.
Common questions about PARAS GOREGAON CO-OP HSG SOC LTD
Is PARAS GOREGAON CO-OP HSG SOC LTD registered with MahaRERA?
According to GharKundli's check of MahaRERA records (updated October 2026), PARAS GOREGAON CO-OP HSG SOC LTD is registered as PM1180002501006 and its status is "Registered and active".
Where is PARAS GOREGAON CO-OP HSG SOC LTD?
PARAS GOREGAON CO-OP HSG SOC LTD by Madhav Enterprise is in Goregaon West, Mumbai (pincode 400104), Maharashtra, and is registered on MahaRERA as PM1180002501006, per GharKundli's check of MahaRERA records.
When is possession of PARAS GOREGAON CO-OP HSG SOC LTD due?
According to GharKundli's check of MahaRERA records (updated October 2026), the latest completion date filed on MahaRERA for PARAS GOREGAON CO-OP HSG SOC LTD in Goregaon West, Mumbai is 30 April 2029 — 4 months later than 31 December 2028, the date given at registration.
Does PARAS GOREGAON CO-OP HSG SOC LTD have complaints on MahaRERA?
No complaints were listed on MahaRERA as of October 2026, per GharKundli's weekly check. GharKundli's full report explains each case and how it ended.
Who is the builder of PARAS GOREGAON CO-OP HSG SOC LTD?
According to GharKundli's check of MahaRERA records (updated October 2026), the builder is Madhav Enterprise.
Other projects in pincode 400104
Data compiled by GharKundli (gharkundli.com) from MahaRERA public records, as of October 2026. Check the project’s MahaRERA page for the latest filings. Not legal advice.