Adityaraj Pavilion

by ADITYARAJ INFINITY DEVELOPERS · Kannamwar Nagar Vikhroli East, Mumbai 400083Also near Hariyali, Vikhroli East, kanamwar Nagar, Tagore Nagar

What’s in the report? →

Possession date of Adityaraj Pavilion (MahaRERA PM1180002500674): 31 December 2029. No complaints on MahaRERA. How to check it yourself

Registered on MahaRERA under PM1180002500674, and currently active.

Source: MahaRERA website — records for PM1180002500674, read and compiled by GharKundli. Facts as filed on MahaRERA, no opinions.

What do you want to know about Adityaraj Pavilion?

Title report MahaRERA par nahi dikh rahi. Kya poochna hai?Tap a question. We’ll answer you on WhatsApp, free.

Ask something else on WhatsAppNo login needed. A real person replies.

Or leave your number, we’ll message you:

GharKundli’s full report on Adityaraj Pavilion

Read from every filing on MahaRERA when you open it

  • Risk & trust score, every point explained
  • What the title report says about the land
  • Each complaint and court case, and how it ended
  • Construction pace against the December 2029 deadline
  • Agreement clauses weaker than the RERA model
  • Escrow audit, loans and the builder's record
  • Questions to get answered in writing before you pay
MahaRERA registration
PM1180002500674
Status
Registered and active
Builder
ADITYARAJ INFINITY DEVELOPERS
Location
Kannamwar Nagar Vikhroli East, Mumbai · 400083
Project type
Mixed
Registered on
28 Aug 2025
Completion date at registration
December 2029
Towers
1
Complaints on MahaRERA
0
Court cases listed
0
Title report on file
Not found

Construction progress of Adityaraj Pavilion, as filed by the builder

What the builder has reported to MahaRERA, as GharKundli read it in October 2026. GharKundli’s full report compares it with the deadline.

Tower / wingPlinthSlabs (structure)Internal workLifts, fire & electrical
"Kannamwar Nagar MA. Dadasaheb Rupwate Co Op Hsg Soc. LTD.100%4.34%0%0%

Commencement certificate (CC), as filed on MahaRERA

  • "Kannamwar Nagar MA. Dadasaheb Rupwate Co Op Hsg Soc. LTD.: covers up to plinth level

Latest CC order on MahaRERA: dated 12/06/2025.

Want to know when this changes? Kundli Watch sends a free WhatsApp update on Adityaraj Pavilion every 1–2 months.

Adityaraj Pavilion: buildings, flats and land, as filed on MahaRERA

The builder’s record and reviews

Not enough of this builder’s other MahaRERA projects have reached their promised date to judge yet.

Read Google reviews of Adityaraj Pavilion →Reviews on Google are opinions by Google users; GharKundli doesn’t check them.

Kundli Watch

Adityaraj Pavilion: buyers & owners

Free: a construction progress update on WhatsApp every 1–2 months, and straight away when anything changes on MahaRERA — a later completion date, new complaints, a red flag. Your number stays private: never shown to other members or the builder.

Be the first to watch this project.

How are you connected to this project?

Watching needs only WhatsApp or your number. Bought here? No document needed now. From the builder’s team? Join to answer buyers’ questions; you never see members’ details. Owners and the builder’s team sign in with a one-time code, then come straight back here.

Common questions about Adityaraj Pavilion

What is the possession date of Adityaraj Pavilion?

According to GharKundli's check of MahaRERA records (updated October 2026), the latest completion date filed on MahaRERA for Adityaraj Pavilion in Kannamwar Nagar Vikhroli East, Mumbai is 31 December 2029.

Is the builder's possession date different from the MahaRERA date for Adityaraj Pavilion?

Builders and listing sites often quote an earlier "target" date for handover. The completion date Adityaraj Pavilion's builder has filed on MahaRERA, the official one, is 31 December 2029, per GharKundli's check of MahaRERA records. If possession is late, what counts under RERA (Section 18) is the possession date written in your agreement for sale.

What is the RERA number of Adityaraj Pavilion?

According to GharKundli's check of MahaRERA records (updated October 2026), the MahaRERA registration number of Adityaraj Pavilion in Kannamwar Nagar Vikhroli East, Mumbai is PM1180002500674.

Is Adityaraj Pavilion registered with MahaRERA?

According to GharKundli's check of MahaRERA records (updated October 2026), Adityaraj Pavilion is registered as PM1180002500674 and its status is "Registered and active".

What is the current construction status of Adityaraj Pavilion? How much work is done?

According to GharKundli's check of MahaRERA records (updated October 2026), Adityaraj Pavilion's status on MahaRERA is "Registered and active". As filed by the builder, slab work on "Kannamwar Nagar MA. Dadasaheb Rupwate Co Op Hsg Soc. LTD. is 4.34% done and internal work 0%. GharKundli's full report compares construction progress with the deadline.

Does Adityaraj Pavilion have complaints on MahaRERA?

No complaints were listed on MahaRERA as of October 2026, per GharKundli's weekly check.

Is Adityaraj Pavilion safe to buy?

According to GharKundli's check of MahaRERA records (updated October 2026), Adityaraj Pavilion is registered on MahaRERA as PM1180002500674, its completion date has not been moved by the builder and no complaints are listed against it. GharKundli doesn't call a project safe or unsafe from these numbers alone: its full report gives a risk & trust score with every point explained.

How much GST is payable on a flat in Adityaraj Pavilion?

Adityaraj Pavilion is under construction, so GST applies to a new flat: 5% of the price, with no input tax credit. The lower 1% rate is only for "affordable" homes: carpet area up to 60 sq m (about 646 sq ft) in the Mumbai region, and price up to ₹45 lakh. There is no GST on stamp duty or registration, and none once the occupancy certificate is issued.

What is the stamp duty and registration cost for a flat in Adityaraj Pavilion?

For a flat in Adityaraj Pavilion (Mumbai), stamp duty is 6% of the agreement value, or of the ready reckoner value if that's higher, including 1% Metro Cess. A woman buying in her own name pays 5%. Registration is 1% of the value, capped at ₹30,000. On a ₹1 crore flat that's about ₹6 lakh in stamp duty plus ₹30,000 registration. GharKundli's property cost calculator works it out for your price: gharkundli.com/tools/property-cost-calculator

Has Adityaraj Pavilion received its OC? Is it ready to move in?

Not yet. According to GharKundli's check of MahaRERA records (updated October 2026), Adityaraj Pavilion is still under construction, with 31 December 2029 as the latest completion date filed on MahaRERA. A flat is ready to move in only once the occupancy certificate (OC) is issued, after construction is complete.

Has Adityaraj Pavilion uploaded its title report on MahaRERA?

According to GharKundli's check of MahaRERA records (updated October 2026), no title report for Adityaraj Pavilion was found on MahaRERA. Builders are expected to upload one; before booking, ask the builder for the advocate's title certificate in writing.

No title report is on MahaRERA for this project. See which documents are missing →

How can I get updates if Adityaraj Pavilion's possession date changes?

The latest dates are on Adityaraj Pavilion's MahaRERA page (PM1180002500674). GharKundli's Kundli Watch sends a free WhatsApp update on Adityaraj Pavilion every 1–2 months, and straight away when anything changes on MahaRERA: a later completion date, new complaints or a red flag. Your number is never shown to the builder.

How big is the land of Adityaraj Pavilion?

According to GharKundli's check of MahaRERA records (updated October 2026), Adityaraj Pavilion stands on 1,110 sq m of land (about 0.3 acres).

What are the reviews of Adityaraj Pavilion?

Google Maps has reviews of Adityaraj Pavilion written by Google users; GharKundli links to them on this page but doesn't check them. For facts rather than opinions: no complaints are listed on MahaRERA, and Kundli Watch shows verified owners of the project.

What is the address and pincode of Adityaraj Pavilion?

Adityaraj Pavilion by ADITYARAJ INFINITY DEVELOPERS is in Kannamwar Nagar Vikhroli East, Mumbai, pincode 400083 (near Hariyali, Vikhroli East, kanamwar Nagar, Tagore Nagar), Maharashtra, and is registered on MahaRERA as PM1180002500674, per GharKundli's check of MahaRERA records. Its boundaries filed there include 40" -0" WIDE CIRCULAR ROAD. GharKundli lists all 176 MahaRERA projects in Vikhroli East (400083).

When was Adityaraj Pavilion registered on MahaRERA?

According to GharKundli's check of MahaRERA records (updated October 2026), Adityaraj Pavilion was registered on MahaRERA on 28 August 2025. GharKundli did not find a title report on the land on file there.

Does Adityaraj Pavilion have any legal issues or court cases?

No court cases are listed for Adityaraj Pavilion on MahaRERA, per GharKundli's check of MahaRERA records (updated October 2026).

Who is the builder / developer of Adityaraj Pavilion?

According to GharKundli's check of MahaRERA records (updated October 2026), the builder is ADITYARAJ INFINITY DEVELOPERS.

All projects with possession due in 2029 in Mumbai Suburban →

Other projects in Vikhroli East (400083)

All 176 projects in Vikhroli East (400083) →

Data compiled by GharKundli (gharkundli.com) from MahaRERA public records, as of October 2026. Check the project’s MahaRERA page for the latest filings. Not legal advice.