Skip to content
GharKundli

Kelvin Palkhi Viraya

by KELVIN ENGINEERING AND SUPPLIES PRIVATE LIMITED · Pahadi Goregaon, Mumbai 400104Also near Goregaon West, Goregaon East, KalanagarRegistered on MahaRERA as “PALKHI VIRAYA”

What’s in the report? →

Possession date of Kelvin Palkhi Viraya (MahaRERA PR1180002501127): 31 December 2028. It has 29 homes (1 BHK, 1 Room Kitchen and 2 BHK, 269–1068 sq ft carpet), 0% sold or booked. No complaints on MahaRERA. How to check it yourself

Registered on MahaRERA under PR1180002501127, and currently active. Its completion date is now December 2028, including MahaRERA's automatic 4-month extension for all eligible projects; the builder hasn't asked for more time.

Source: MahaRERA website — records for PR1180002501127, read and compiled by GharKundli. Facts as filed on MahaRERA, no opinions.

What do you want to know about Kelvin Palkhi Viraya?

Title report MahaRERA par nahi dikh rahi. Kya poochna hai?Tap a question. We’ll answer you on WhatsApp, free.

Ask something else on WhatsAppNo login needed. A real person replies.

Or leave your number, we’ll message you:

How the possession date of Kelvin Palkhi Viraya has moved

  1. 31 August 2028

    Completion date given when the project was registered

  2. 31 December 2028

    MahaRERA's automatic 4-month extension for all eligible projects, not the builder's request

Source: Kelvin Palkhi Viraya’s extension records on MahaRERA (PR1180002501127), read by GharKundli in October 2026. The builder’s reasons are quoted as filed. Your own possession date is the one in your agreement for sale.

What builders tell MahaRERA when they’re late: 14,973 applications analysed →

GharKundli’s full report on Kelvin Palkhi Viraya

Read from every filing on MahaRERA when you open it

  • Risk & trust score, every point explained
  • What the title report says about the land
  • Each complaint and court case, and how it ended
  • Construction pace against the December 2028 deadline
  • Agreement clauses weaker than the RERA model
  • Escrow audit, loans and the builder's record
  • Questions to get answered in writing before you pay
MahaRERA registration
PR1180002501127
Status
Registered and active
Builder
KELVIN ENGINEERING AND SUPPLIES PRIVATE LIMITED
Location
Pahadi Goregaon, Mumbai · 400104
Project type
Residential / Group Housing
Registered on
9 Oct 2025
Completion date at registration
August 2028
Latest completion date
December 2028
MahaRERA's automatic extension
+4 months (force majeure, all eligible projects)
Homes
29
Sold or booked
0%
Towers
1
Complaints on MahaRERA
0
Court cases listed
0
Title report on file
Not found

Construction progress of Kelvin Palkhi Viraya, as filed by the builder

What the builder has reported to MahaRERA, as GharKundli read it in October 2026. GharKundli’s full report compares it with the deadline.

Tower / wingPlinthSlabs (structure)Internal workLifts, fire & electrical
PALKHI VIRAYA100%40%0%0%

Commencement certificate (CC), as filed on MahaRERA

  • PALKHI VIRAYA: covers upto top of plinth level

Latest CC order on MahaRERA: dated 29/07/2025.

Want to know when this changes? Kundli Watch sends a free WhatsApp update on Kelvin Palkhi Viraya every 1–2 months.

Kelvin Palkhi Viraya: buildings, flats and land, as filed on MahaRERA

TypeCarpet area (sq ft)Units
2 BHK588 – 1,06821
1 BHK358 – 4597
1 Room Kitchen2691

The builder’s record and reviews

Palkhi Realty (a group of 4 linked companies) has 7 projects on MahaRERA since 2017, this one included. Of the 7 GharKundli has checked: 5 finished, 4 within the promised date and 1 needed more time (typically 13 months); 2 still being built, none past the promised date yet. 3 complaints on MahaRERA across 2 projects.

Read Google reviews of Kelvin Palkhi Viraya →Reviews on Google are opinions by Google users; GharKundli doesn’t check them.

Kundli Watch

Kelvin Palkhi Viraya: buyers & owners

Free: a construction progress update on WhatsApp every 1–2 months, and straight away when anything changes on MahaRERA — a later completion date, new complaints, a red flag. Your number stays private: never shown to other members or the builder.

Be the first to watch this project.

How are you connected to this project?

Watching needs only WhatsApp or your number. Bought here? No document needed now. From the builder’s team? Join to answer buyers’ questions; you never see members’ details. Owners and the builder’s team sign in with a one-time code, then come straight back here.

Common questions about Kelvin Palkhi Viraya

What is the possession date of Kelvin Palkhi Viraya?

According to GharKundli's check of MahaRERA records (updated October 2026), the latest completion date filed on MahaRERA for Kelvin Palkhi Viraya in Pahadi Goregaon, Mumbai is 31 December 2028, including MahaRERA's automatic 4-month extension for all eligible projects.

Is the builder's possession date different from the MahaRERA date for Kelvin Palkhi Viraya?

Builders and listing sites often quote an earlier "target" date for handover. The completion date Kelvin Palkhi Viraya's builder has filed on MahaRERA, the official one, is 31 December 2028, per GharKundli's check of MahaRERA records. If possession is late, what counts under RERA (Section 18) is the possession date written in your agreement for sale.

What is the RERA number of Kelvin Palkhi Viraya?

According to GharKundli's check of MahaRERA records (updated October 2026), the MahaRERA registration number of Kelvin Palkhi Viraya in Pahadi Goregaon, Mumbai is PR1180002501127.

Is Kelvin Palkhi Viraya registered with MahaRERA?

According to GharKundli's check of MahaRERA records (updated October 2026), Kelvin Palkhi Viraya is registered as PR1180002501127 and its status is "Registered and active".

What is the current construction status of Kelvin Palkhi Viraya? How much work is done?

According to GharKundli's check of MahaRERA records (updated October 2026), Kelvin Palkhi Viraya's status on MahaRERA is "Registered and active". As filed by the builder, slab work on PALKHI VIRAYA is 40% done and internal work 0%. GharKundli's full report compares construction progress with the deadline.

Does Kelvin Palkhi Viraya have complaints on MahaRERA?

No complaints were listed on MahaRERA as of October 2026, per GharKundli's weekly check.

Is Kelvin Palkhi Viraya safe to buy?

According to GharKundli's check of MahaRERA records (updated October 2026), Kelvin Palkhi Viraya is registered on MahaRERA as PR1180002501127, its completion date has not been moved by the builder and no complaints are listed against it. GharKundli doesn't call a project safe or unsafe from these numbers alone: its full report gives a risk & trust score with every point explained.

How much GST is payable on a flat in Kelvin Palkhi Viraya?

Kelvin Palkhi Viraya is under construction, so GST applies to a new flat: 5% of the price, with no input tax credit. The lower 1% rate is only for "affordable" homes: carpet area up to 60 sq m (about 646 sq ft) in the Mumbai region, and price up to ₹45 lakh. Some flats in Kelvin Palkhi Viraya are 269 sq ft carpet, small enough for 1% if the price is ₹45 lakh or less. There is no GST on stamp duty or registration, and none once the occupancy certificate is issued.

What is the stamp duty and registration cost for a flat in Kelvin Palkhi Viraya?

For a flat in Kelvin Palkhi Viraya (Mumbai), stamp duty is 6% of the agreement value, or of the ready reckoner value if that's higher, including 1% Metro Cess. A woman buying in her own name pays 5%. Registration is 1% of the value, capped at ₹30,000. On a ₹1 crore flat that's about ₹6 lakh in stamp duty plus ₹30,000 registration. GharKundli's property cost calculator works it out for your price: gharkundli.com/tools/property-cost-calculator

Has Kelvin Palkhi Viraya received its OC? Is it ready to move in?

Not yet. According to GharKundli's check of MahaRERA records (updated October 2026), Kelvin Palkhi Viraya is still under construction, with 31 December 2028 as the latest completion date filed on MahaRERA. A flat is ready to move in only once the occupancy certificate (OC) is issued, after construction is complete.

Is Kelvin Palkhi Viraya a redevelopment or SRA project?

According to GharKundli's check of MahaRERA records (updated October 2026), Kelvin Palkhi Viraya is a redevelopment: 16 of its flats are set aside for existing occupants (rehab), and the rest are for sale. Its planning authority is MCGM, not the Slum Rehabilitation Authority, so it isn't an SRA scheme.

Has Kelvin Palkhi Viraya uploaded its title report on MahaRERA?

According to GharKundli's check of MahaRERA records (updated October 2026), no title report for Kelvin Palkhi Viraya was found on MahaRERA. Builders are expected to upload one; before booking, ask the builder for the advocate's title certificate in writing.

No title report is on MahaRERA for this project. See which documents are missing →

How can I get updates if Kelvin Palkhi Viraya's possession date changes?

The latest dates are on Kelvin Palkhi Viraya's MahaRERA page (PR1180002501127). GharKundli's Kundli Watch sends a free WhatsApp update on Kelvin Palkhi Viraya every 1–2 months, and straight away when anything changes on MahaRERA: a later completion date, new complaints or a red flag. Your number is never shown to the builder.

How many floors does Kelvin Palkhi Viraya have?

According to GharKundli's check of MahaRERA records (updated October 2026), Kelvin Palkhi Viraya has one building filed: PALKHI VIRAYA with 10 floors and 29 units.

What are the flat sizes (carpet area) in Kelvin Palkhi Viraya?

According to GharKundli's check of MahaRERA records (updated October 2026), the builder has filed these homes for Kelvin Palkhi Viraya: 2 BHK: 588 to 1068 sq ft carpet (21 homes); 1 BHK: 358 to 459 sq ft carpet (7 homes); 1 Room Kitchen: 269 sq ft carpet (1 homes). Carpet area is the usable floor area inside the walls, as defined under RERA.

How much parking does Kelvin Palkhi Viraya have?

According to GharKundli's check of MahaRERA records (updated October 2026), the builder has filed 26 covered car parking spaces for Kelvin Palkhi Viraya.

How big is the land of Kelvin Palkhi Viraya?

According to GharKundli's check of MahaRERA records (updated October 2026), Kelvin Palkhi Viraya stands on 573 sq m of land (about 0.1 acres), with 2,080 sq m of sanctioned built-up area.

What is the track record of Kelvin Palkhi Viraya's builder?

According to GharKundli's check of MahaRERA records (updated October 2026), Palkhi Realty (a group of 4 linked companies) has 7 projects on MahaRERA since 2017, this one included. Of the 7 GharKundli has checked: 5 finished, 4 within the promised date and 1 needed more time (typically 13 months); 2 still being built, none past the promised date yet. 3 complaints on MahaRERA across 2 projects. GharKundli's full report covers the builder's record in detail.

What are the reviews of Kelvin Palkhi Viraya?

Google Maps has reviews of Kelvin Palkhi Viraya written by Google users; GharKundli links to them on this page but doesn't check them. For facts rather than opinions: no complaints are listed on MahaRERA, and Kundli Watch shows verified owners of the project.

What is the address and pincode of Kelvin Palkhi Viraya?

Kelvin Palkhi Viraya by KELVIN ENGINEERING AND SUPPLIES PRIVATE LIMITED is in Pahadi Goregaon, Mumbai, pincode 400104 (near Goregaon West, Goregaon East, Kalanagar), Maharashtra, and is registered on MahaRERA as PR1180002501127, per GharKundli's check of MahaRERA records. GharKundli lists all 183 MahaRERA projects in Goregaon West (400104).

How many flats are in Kelvin Palkhi Viraya, and how many are sold?

According to GharKundli's check of MahaRERA records (updated October 2026), Kelvin Palkhi Viraya has 29 homes in 1 tower registered on MahaRERA, and 0% of them are sold or booked.

When was Kelvin Palkhi Viraya registered on MahaRERA?

According to GharKundli's check of MahaRERA records (updated October 2026), Kelvin Palkhi Viraya was registered on MahaRERA on 9 October 2025. GharKundli did not find a title report on the land on file there.

Does Kelvin Palkhi Viraya have any legal issues or court cases?

No court cases are listed for Kelvin Palkhi Viraya on MahaRERA, per GharKundli's check of MahaRERA records (updated October 2026).

Who is the builder / developer of Kelvin Palkhi Viraya?

According to GharKundli's check of MahaRERA records (updated October 2026), the builder is KELVIN ENGINEERING AND SUPPLIES PRIVATE LIMITED.

All projects with possession due in 2028 in Mumbai Suburban →

Other projects in Goregaon West (400104)

All 183 projects in Goregaon West (400104) →

Data compiled by GharKundli (gharkundli.com) from MahaRERA public records, as of October 2026. Check the project’s MahaRERA page for the latest filings. Not legal advice.