Skip to content
GharKundli

Rudra Starlight

by RT HOUSING PRIVATE LIMITED (Yashodanand) · Malad, Mumbai 400070

What’s in the report? →

Possession date of Rudra Starlight (MahaRERA PM1180002501130): 30 November 2029. It has 159 homes (1 BHK and 2 BHK, 415–997 sq ft carpet), 51% sold or booked. No complaints on MahaRERA. How to check it yourself

Registered on MahaRERA under PM1180002501130, and currently active. Its completion date is now November 2029, including MahaRERA's automatic 4-month extension for all eligible projects; the builder hasn't asked for more time.

Source: MahaRERA website — records for PM1180002501130, read and compiled by GharKundli. Facts as filed on MahaRERA, no opinions.

What do you want to know about Rudra Starlight?

3 court cases MahaRERA par listed. Kya jaanna hai?Tap a question. We’ll answer you on WhatsApp, free.

Ask something else on WhatsAppNo login needed. A real person replies.

Or leave your number, we’ll message you:

How the possession date of Rudra Starlight has moved

  1. 31 July 2029

    Completion date given when the project was registered

  2. 30 November 2029

    MahaRERA's automatic 4-month extension for all eligible projects, not the builder's request

Source: Rudra Starlight’s extension records on MahaRERA (PM1180002501130), read by GharKundli in October 2026. The builder’s reasons are quoted as filed. Your own possession date is the one in your agreement for sale.

What builders tell MahaRERA when they’re late: 14,973 applications analysed →

GharKundli’s full report on Rudra Starlight

Read from every filing on MahaRERA when you open it

  • Risk & trust score, every point explained
  • What the title report says about the land
  • Each of the 3 court cases, and how it ended
  • Construction pace against the November 2029 deadline
  • Agreement clauses weaker than the RERA model
  • Escrow audit, loans and the builder's record
  • Questions to get answered in writing before you pay
MahaRERA registration
PM1180002501130
Status
Registered and active
Builder
RT HOUSING PRIVATE LIMITED
Location
Malad, Mumbai · 400070
Project type
Mixed
Registered on
9 Oct 2025
Completion date at registration
July 2029
Latest completion date
November 2029
MahaRERA's automatic extension
+4 months (force majeure, all eligible projects)
Homes
159
Sold or booked
51%
Towers
1
Complaints on MahaRERA
0
Court cases listed
3
Title report on file
Not found

Construction progress of Rudra Starlight, as filed by the builder

What the builder has reported to MahaRERA, as GharKundli read it in October 2026. GharKundli’s full report compares it with the deadline.

Tower / wingPlinthSlabs (structure)Internal workLifts, fire & electrical
RUDRA STARLIGHT18%0%0%0%

Commencement certificate (CC), as filed on MahaRERA

  • RUDRA STARLIGHT: covers PLINTH CC UPTO TOP OF BASAMENT

Latest CC order on MahaRERA: dated 27/05/2025.

Want to know when this changes? Kundli Watch sends a free WhatsApp update on Rudra Starlight every 1–2 months.

Rudra Starlight: buildings, flats and land, as filed on MahaRERA

TypeCarpet area (sq ft)Units
1 BHK415 – 45182
2 BHK488 – 99777
Office Space399 – 3,62211
  • Buildings: RUDRA STARLIGHT (27 floors, 170 units)
  • Car parking: 210 covered
  • Land: 1,922 sq m (about 0.5 acres) · sanctioned built-up 10,376 sq m
  • Map: Get directions

The builder’s record and reviews

Yashodanand Infra (a group of 5 linked companies) has 7 projects on MahaRERA since 2022, this one included. Of the 7 GharKundli has checked: 7 still being built, 3 past the promised date (typically 21 months late). No complaints on MahaRERA.

Read Google reviews of Rudra Starlight →Reviews on Google are opinions by Google users; GharKundli doesn’t check them.

Kundli Watch

Rudra Starlight: buyers & owners

Free: a construction progress update on WhatsApp every 1–2 months, and straight away when anything changes on MahaRERA — a later completion date, new complaints, a red flag. Your number stays private: never shown to other members or the builder.

Be the first to watch this project.

How are you connected to this project?

Watching needs only WhatsApp or your number. Bought here? No document needed now. From the builder’s team? Join to answer buyers’ questions; you never see members’ details. Owners and the builder’s team sign in with a one-time code, then come straight back here.

Common questions about Rudra Starlight

What is the possession date of Rudra Starlight?

According to GharKundli's check of MahaRERA records (updated October 2026), the latest completion date filed on MahaRERA for Rudra Starlight in Malad, Mumbai is 30 November 2029, including MahaRERA's automatic 4-month extension for all eligible projects.

Is the builder's possession date different from the MahaRERA date for Rudra Starlight?

Builders and listing sites often quote an earlier "target" date for handover. The completion date Rudra Starlight's builder has filed on MahaRERA, the official one, is 30 November 2029, per GharKundli's check of MahaRERA records. If possession is late, what counts under RERA (Section 18) is the possession date written in your agreement for sale.

What is the RERA number of Rudra Starlight?

According to GharKundli's check of MahaRERA records (updated October 2026), the MahaRERA registration number of Rudra Starlight in Malad, Mumbai is PM1180002501130.

Is Rudra Starlight registered with MahaRERA?

According to GharKundli's check of MahaRERA records (updated October 2026), Rudra Starlight is registered as PM1180002501130 and its status is "Registered and active".

What is the current construction status of Rudra Starlight? How much work is done?

According to GharKundli's check of MahaRERA records (updated October 2026), Rudra Starlight's status on MahaRERA is "Registered and active". As filed by the builder, slab work on RUDRA STARLIGHT is 0% done and internal work 0%. GharKundli's full report compares construction progress with the deadline.

Does Rudra Starlight have complaints on MahaRERA?

No complaints were listed on MahaRERA as of October 2026, per GharKundli's weekly check.

Is Rudra Starlight safe to buy?

According to GharKundli's check of MahaRERA records (updated October 2026), Rudra Starlight is registered on MahaRERA as PM1180002501130, its completion date has not been moved by the builder and no complaints are listed against it. GharKundli doesn't call a project safe or unsafe from these numbers alone: its full report gives a risk & trust score with every point explained.

How much GST is payable on a flat in Rudra Starlight?

Rudra Starlight is under construction, so GST applies to a new flat: 5% of the price, with no input tax credit. The lower 1% rate is only for "affordable" homes: carpet area up to 60 sq m (about 646 sq ft) in the Mumbai region, and price up to ₹45 lakh. Some flats in Rudra Starlight are 415 sq ft carpet, small enough for 1% if the price is ₹45 lakh or less. There is no GST on stamp duty or registration, and none once the occupancy certificate is issued.

What is the stamp duty and registration cost for a flat in Rudra Starlight?

For a flat in Rudra Starlight (Mumbai), stamp duty is 6% of the agreement value, or of the ready reckoner value if that's higher, including 1% Metro Cess. A woman buying in her own name pays 5%. Registration is 1% of the value, capped at ₹30,000. On a ₹1 crore flat that's about ₹6 lakh in stamp duty plus ₹30,000 registration. GharKundli's property cost calculator works it out for your price: gharkundli.com/tools/property-cost-calculator

Has Rudra Starlight received its OC? Is it ready to move in?

Not yet. According to GharKundli's check of MahaRERA records (updated October 2026), Rudra Starlight is still under construction, with 30 November 2029 as the latest completion date filed on MahaRERA. A flat is ready to move in only once the occupancy certificate (OC) is issued, after construction is complete.

Is Rudra Starlight a redevelopment or SRA project?

According to GharKundli's check of MahaRERA records (updated October 2026), Rudra Starlight is a redevelopment: 61 of its flats are set aside for existing occupants (rehab), and the rest are for sale.

Has Rudra Starlight uploaded its title report on MahaRERA?

According to GharKundli's check of MahaRERA records (updated October 2026), no title report for Rudra Starlight was found on MahaRERA. Builders are expected to upload one; before booking, ask the builder for the advocate's title certificate in writing.

No title report is on MahaRERA for this project. See which documents are missing →

How can I get updates if Rudra Starlight's possession date changes?

The latest dates are on Rudra Starlight's MahaRERA page (PM1180002501130). GharKundli's Kundli Watch sends a free WhatsApp update on Rudra Starlight every 1–2 months, and straight away when anything changes on MahaRERA: a later completion date, new complaints or a red flag. Your number is never shown to the builder.

How many floors does Rudra Starlight have?

According to GharKundli's check of MahaRERA records (updated October 2026), Rudra Starlight has one building filed: RUDRA STARLIGHT with 27 floors and 170 units.

What are the flat sizes (carpet area) in Rudra Starlight?

According to GharKundli's check of MahaRERA records (updated October 2026), the builder has filed these homes for Rudra Starlight: 1 BHK: 415 to 451 sq ft carpet (82 homes); 2 BHK: 488 to 997 sq ft carpet (77 homes). Carpet area is the usable floor area inside the walls, as defined under RERA.

How much parking does Rudra Starlight have?

According to GharKundli's check of MahaRERA records (updated October 2026), the builder has filed 210 covered car parking spaces for Rudra Starlight.

How big is the land of Rudra Starlight?

According to GharKundli's check of MahaRERA records (updated October 2026), Rudra Starlight stands on 1,922 sq m of land (about 0.5 acres), with 10,376 sq m of sanctioned built-up area.

What is the track record of Rudra Starlight's builder?

According to GharKundli's check of MahaRERA records (updated October 2026), Yashodanand Infra (a group of 5 linked companies) has 7 projects on MahaRERA since 2022, this one included. Of the 7 GharKundli has checked: 7 still being built, 3 past the promised date (typically 21 months late). No complaints on MahaRERA. GharKundli's full report covers the builder's record in detail.

What are the reviews of Rudra Starlight?

Google Maps has reviews of Rudra Starlight written by Google users; GharKundli links to them on this page but doesn't check them. For facts rather than opinions: no complaints are listed on MahaRERA, and Kundli Watch shows verified owners of the project.

What is the address and pincode of Rudra Starlight?

Rudra Starlight by RT HOUSING PRIVATE LIMITED (Yashodanand) is in Malad, Mumbai, pincode 400070, Maharashtra, and is registered on MahaRERA as PM1180002501130, per GharKundli's check of MahaRERA records. GharKundli lists all 92 MahaRERA projects in Kurla West (400070).

How many flats are in Rudra Starlight, and how many are sold?

According to GharKundli's check of MahaRERA records (updated October 2026), Rudra Starlight has 159 homes in 1 tower registered on MahaRERA, and 51% of them are sold or booked.

When was Rudra Starlight registered on MahaRERA?

According to GharKundli's check of MahaRERA records (updated October 2026), Rudra Starlight was registered on MahaRERA on 9 October 2025. GharKundli did not find a title report on the land on file there.

Does Rudra Starlight have any legal issues or court cases?

3 court cases are listed for Rudra Starlight on MahaRERA, per GharKundli's check of MahaRERA records (updated October 2026). GharKundli's full report explains each case and how it ended.

A court case can stall a project or tie up the land. See what each case is about →

Who is the builder / developer of Rudra Starlight?

According to GharKundli's check of MahaRERA records (updated October 2026), the builder is RT HOUSING PRIVATE LIMITED, the company Yashodanand files this project under.

All projects with possession due in 2029 in Mumbai Suburban →

Other projects in Kurla West (400070)

All 92 projects in Kurla West (400070) →

Data compiled by GharKundli (gharkundli.com) from MahaRERA public records, as of October 2026. Check the project’s MahaRERA page for the latest filings. Not legal advice.