TSM Anand Heritage

by TSM Infra · Andheri East, Mumbai 400093Also near Jogeshwari East, Goregaon East, Chakala MIDCRegistered on MahaRERA as “Anand Heritage”

What’s in the report? →

Possession date of TSM Anand Heritage (MahaRERA PR1180002500917): 30 April 2029. It has 36 homes (1 BHK, 2 BHK and 3 BHK, 216–1155 sq ft carpet), 0% sold or booked. No complaints on MahaRERA. How to check it yourself

Registered on MahaRERA under PR1180002500917, and currently active. Its completion date is now April 2029, including MahaRERA's automatic 4-month extension for all eligible projects; the builder hasn't asked for more time.

Source: MahaRERA website — records for PR1180002500917, read and compiled by GharKundli. Facts as filed on MahaRERA, no opinions.

What do you want to know about TSM Anand Heritage?

Title report MahaRERA par nahi dikh rahi. Kya poochna hai?Tap a question. We’ll answer you on WhatsApp, free.

Ask something else on WhatsAppNo login needed. A real person replies.

Or leave your number, we’ll message you:

How the possession date of TSM Anand Heritage has moved

  1. 31 December 2028

    Completion date given when the project was registered

  2. 30 April 2029

    MahaRERA's automatic 4-month extension for all eligible projects, not the builder's request

Source: TSM Anand Heritage’s extension records on MahaRERA (PR1180002500917), read by GharKundli in October 2026. The builder’s reasons are quoted as filed. Your own possession date is the one in your agreement for sale.

What builders tell MahaRERA when they’re late: 14,973 applications analysed →

GharKundli’s full report on TSM Anand Heritage

Read from every filing on MahaRERA when you open it

  • Risk & trust score, every point explained
  • What the title report says about the land
  • Each complaint and court case, and how it ended
  • Construction pace against the April 2029 deadline
  • Agreement clauses weaker than the RERA model
  • Escrow audit, loans and the builder's record
  • Questions to get answered in writing before you pay
MahaRERA registration
PR1180002500917
Status
Registered and active
Builder
TSM Infra
Location
Andheri East, Mumbai · 400093
Project type
Residential / Group Housing
Registered on
23 Sep 2025
Completion date at registration
December 2028
Latest completion date
April 2029
MahaRERA's automatic extension
+4 months (force majeure, all eligible projects)
Homes
36
Sold or booked
0%
Towers
1
Complaints on MahaRERA
0
Court cases listed
0
Title report on file
Not found

Construction progress of TSM Anand Heritage, as filed by the builder

What the builder has reported to MahaRERA, as GharKundli read it in October 2026. GharKundli’s full report compares it with the deadline.

Tower / wingPlinthSlabs (structure)Internal workLifts, fire & electrical
Anand Heritage0%0%0%0%

Commencement certificate (CC), as filed on MahaRERA

  • Anand Heritage: covers Plinth Level

Latest CC order on MahaRERA: dated 21/08/2025.

Want to know when this changes? Kundli Watch sends a free WhatsApp update on TSM Anand Heritage every 1–2 months.

TSM Anand Heritage: buildings, flats and land, as filed on MahaRERA

TypeCarpet area (sq ft)Units
1 BHK300 – 52022
Shops105 – 3448
2 BHK585 – 8148
3 BHK824 – 1,1553
Multi Purpose Room2163
Other1,8822

The builder’s record and reviews

Not enough of this builder’s other MahaRERA projects have reached their promised date to judge yet.

Read Google reviews of TSM Anand Heritage →Reviews on Google are opinions by Google users; GharKundli doesn’t check them.

Kundli Watch

TSM Anand Heritage: buyers & owners

Free: a construction progress update on WhatsApp every 1–2 months, and straight away when anything changes on MahaRERA — a later completion date, new complaints, a red flag. Your number stays private: never shown to other members or the builder.

Be the first to watch this project.

How are you connected to this project?

Watching needs only WhatsApp or your number. Bought here? No document needed now. From the builder’s team? Join to answer buyers’ questions; you never see members’ details. Owners and the builder’s team sign in with a one-time code, then come straight back here.

Common questions about TSM Anand Heritage

What is the possession date of TSM Anand Heritage?

According to GharKundli's check of MahaRERA records (updated October 2026), the latest completion date filed on MahaRERA for TSM Anand Heritage in Andheri East, Mumbai is 30 April 2029, including MahaRERA's automatic 4-month extension for all eligible projects.

Is the builder's possession date different from the MahaRERA date for TSM Anand Heritage?

Builders and listing sites often quote an earlier "target" date for handover. The completion date TSM Anand Heritage's builder has filed on MahaRERA, the official one, is 30 April 2029, per GharKundli's check of MahaRERA records. If possession is late, what counts under RERA (Section 18) is the possession date written in your agreement for sale.

What is the RERA number of TSM Anand Heritage?

According to GharKundli's check of MahaRERA records (updated October 2026), the MahaRERA registration number of TSM Anand Heritage in Andheri East, Mumbai is PR1180002500917.

Is TSM Anand Heritage registered with MahaRERA?

According to GharKundli's check of MahaRERA records (updated October 2026), TSM Anand Heritage is registered as PR1180002500917 and its status is "Registered and active".

What is the current construction status of TSM Anand Heritage? How much work is done?

According to GharKundli's check of MahaRERA records (updated October 2026), TSM Anand Heritage's status on MahaRERA is "Registered and active". As filed by the builder, slab work on Anand Heritage is 0% done and internal work 0%. GharKundli's full report compares construction progress with the deadline.

Does TSM Anand Heritage have complaints on MahaRERA?

No complaints were listed on MahaRERA as of October 2026, per GharKundli's weekly check.

Is TSM Anand Heritage safe to buy?

According to GharKundli's check of MahaRERA records (updated October 2026), TSM Anand Heritage is registered on MahaRERA as PR1180002500917, its completion date has not been moved by the builder and no complaints are listed against it. GharKundli doesn't call a project safe or unsafe from these numbers alone: its full report gives a risk & trust score with every point explained.

How much GST is payable on a flat in TSM Anand Heritage?

TSM Anand Heritage is under construction, so GST applies to a new flat: 5% of the price, with no input tax credit. The lower 1% rate is only for "affordable" homes: carpet area up to 60 sq m (about 646 sq ft) in the Mumbai region, and price up to ₹45 lakh. Some flats in TSM Anand Heritage are 216 sq ft carpet, small enough for 1% if the price is ₹45 lakh or less. There is no GST on stamp duty or registration, and none once the occupancy certificate is issued.

What is the stamp duty and registration cost for a flat in TSM Anand Heritage?

For a flat in TSM Anand Heritage (Mumbai), stamp duty is 6% of the agreement value, or of the ready reckoner value if that's higher, including 1% Metro Cess. A woman buying in her own name pays 5%. Registration is 1% of the value, capped at ₹30,000. On a ₹1 crore flat that's about ₹6 lakh in stamp duty plus ₹30,000 registration. GharKundli's property cost calculator works it out for your price: gharkundli.com/tools/property-cost-calculator

Has TSM Anand Heritage received its OC? Is it ready to move in?

Not yet. According to GharKundli's check of MahaRERA records (updated October 2026), TSM Anand Heritage is still under construction, with 30 April 2029 as the latest completion date filed on MahaRERA. A flat is ready to move in only once the occupancy certificate (OC) is issued, after construction is complete.

Has TSM Anand Heritage uploaded its title report on MahaRERA?

According to GharKundli's check of MahaRERA records (updated October 2026), no title report for TSM Anand Heritage was found on MahaRERA. Builders are expected to upload one; before booking, ask the builder for the advocate's title certificate in writing.

No title report is on MahaRERA for this project. See which documents are missing →

How can I get updates if TSM Anand Heritage's possession date changes?

The latest dates are on TSM Anand Heritage's MahaRERA page (PR1180002500917). GharKundli's Kundli Watch sends a free WhatsApp update on TSM Anand Heritage every 1–2 months, and straight away when anything changes on MahaRERA: a later completion date, new complaints or a red flag. Your number is never shown to the builder.

How many floors does TSM Anand Heritage have?

According to GharKundli's check of MahaRERA records (updated October 2026), TSM Anand Heritage has one building filed: Anand Heritage with 17 floors and 46 units.

What are the flat sizes (carpet area) in TSM Anand Heritage?

According to GharKundli's check of MahaRERA records (updated October 2026), the builder has filed these homes for TSM Anand Heritage: 1 BHK: 300 to 520 sq ft carpet (22 homes); 2 BHK: 585 to 814 sq ft carpet (8 homes); 3 BHK: 824 to 1155 sq ft carpet (3 homes); Multi Purpose Room: 216 sq ft carpet (3 homes). Carpet area is the usable floor area inside the walls, as defined under RERA.

How much parking does TSM Anand Heritage have?

According to GharKundli's check of MahaRERA records (updated October 2026), the builder has filed 33 covered car parking spaces for TSM Anand Heritage.

How big is the land of TSM Anand Heritage?

According to GharKundli's check of MahaRERA records (updated October 2026), TSM Anand Heritage stands on 579 sq m of land (about 0.1 acres), with 1,625 sq m of sanctioned built-up area.

What are the reviews of TSM Anand Heritage?

Google Maps has reviews of TSM Anand Heritage written by Google users; GharKundli links to them on this page but doesn't check them. For facts rather than opinions: no complaints are listed on MahaRERA, and Kundli Watch shows verified owners of the project.

What is the address and pincode of TSM Anand Heritage?

TSM Anand Heritage by TSM Infra is in Andheri East, Mumbai, pincode 400093 (near Jogeshwari East, Goregaon East, Chakala MIDC), Maharashtra, and is registered on MahaRERA as PR1180002500917, per GharKundli's check of MahaRERA records. Its boundaries filed there include 18.30 M Jitamata Road. GharKundli lists all 74 MahaRERA projects in Andheri East (400093).

How many flats are in TSM Anand Heritage, and how many are sold?

According to GharKundli's check of MahaRERA records (updated October 2026), TSM Anand Heritage has 36 homes in 1 tower registered on MahaRERA, and 0% of them are sold or booked.

When was TSM Anand Heritage registered on MahaRERA?

According to GharKundli's check of MahaRERA records (updated October 2026), TSM Anand Heritage was registered on MahaRERA on 23 September 2025. GharKundli did not find a title report on the land on file there.

Does TSM Anand Heritage have any legal issues or court cases?

No court cases are listed for TSM Anand Heritage on MahaRERA, per GharKundli's check of MahaRERA records (updated October 2026).

Who is the builder / developer of TSM Anand Heritage?

According to GharKundli's check of MahaRERA records (updated October 2026), the builder is TSM Infra.

All projects with possession due in 2029 in Mumbai Suburban →

Other projects in Andheri East (400093)

All 74 projects in Andheri East (400093) →

Data compiled by GharKundli (gharkundli.com) from MahaRERA public records, as of October 2026. Check the project’s MahaRERA page for the latest filings. Not legal advice.