Siddha Sky Phase 1
by Sejal Shakti Realtors LLP · Antop Hill, Mumbai
Possession date of Siddha Sky Phase 1: 30 October 2026, moved from 31 December 2025 (6 months later). This is the latest completion date the builder has filed on MahaRERA, and it has already passed. How to check it yourself
Registered on MahaRERA under P51900021027, and currently active. Its completion date has moved from December 2025 to October 2026: 6 months at the builder's request, plus MahaRERA's automatic 4-month extension for all eligible projects. 16 complaints are listed against it on MahaRERA.
Source: GharKundli’s check of MahaRERA records, October 2026.
The latest completion date on MahaRERA (October 2026) has passed.
What do you want to know about Siddha Sky Phase 1?
How the possession date of Siddha Sky Phase 1 has moved
31 December 2025
Completion date given when the project was registered
30 June 2026
Extended at the builder's request (MahaRERA application EA17112518346)
Reason the builder gave MahaRERA:
“Our project consist of 2 Plinth + Ground + 40 Story Building- entire residential premises. Wherein Original Proposed Completion Date is 31.12.2025. This is the first time we are seeking the extension. We have completed entire RCC work and 8…” Read the full reason
“Our project consist of 2 Plinth + Ground + 40 Story Building- entire residential premises. Wherein Original Proposed Completion Date is 31.12.2025. This is the first time we are seeking the extension. We have completed entire RCC work and 80% of finishing is been done. Some of fit out to be done and finishing of some floors is pending. For completion additional vendors have appointed and are working on the same to fulfil. Due to covid-19 pandemic, our project got delayed and supply of materials got disrupted. There was a large-scale reverse migration of labour from state of Maharashtra. Con…”30 October 2026
MahaRERA's automatic 4-month extension for all eligible projects, not the builder's request
Source: Siddha Sky Phase 1’s extension records on MahaRERA (P51900021027), read by GharKundli in October 2026. The builder’s reasons are quoted as filed. Your own possession date is the one in your agreement for sale.
What builders tell MahaRERA when they’re late: 14,973 applications analysed →GharKundli’s full report on Siddha Sky Phase 1
Read from every filing on MahaRERA when you open it
- Risk & trust score, every point explained
- What the title report says about the land
- Each of the 16 complaints, and how it ended
- Construction pace against the October 2026 deadline
- Agreement clauses weaker than the RERA model
- Escrow audit, loans and the builder's record
- Questions to get answered in writing before you pay
Other wings and phases of this project
Each is registered on MahaRERA separately, with its own possession date. Check the one your flat is in.
- Siddha Sky Phase 2P51900021040 · possession 30 Apr 2027
- Siddha Sky Phase 3P51900021044 · possession 31 Dec 2026
- Siddha Sky Phase 4P51900021031 · possession 30 Apr 2031
- SIDDHA SKY PHASE VP51900055793 · possession 31 Mar 2030
- MahaRERA registration
- P51900021027
- Status
- Registered and active
- Builder
- Sejal Shakti Realtors LLP
- Location
- Antop Hill, Mumbai · 400037
- Project type
- Others
- Registered on
- 27 May 2019
- Completion date at registration
- December 2025
- Latest completion date
- October 2026
- Delay so far
- 6 months
- MahaRERA's automatic extension
- +4 months (force majeure, all eligible projects)
- Homes
- 357
- Sold or booked
- 89%
- Towers
- 1
- Complaints on MahaRERA
- 16
- Court cases listed
- 0
- Appeals at the tribunal
- 1
- Title report on file
- Not found
- Builder's other MahaRERA projects
- 2
Construction progress of Siddha Sky Phase 1, as filed by the builder
What the builder has reported to MahaRERA, as GharKundli read it in October 2026. GharKundli’s full report compares it with the deadline.
| Tower / wing | Plinth | Slabs (structure) | Internal work | Lifts, fire & electrical |
|---|---|---|---|---|
| Siddha Sky Phase 1 | 100% | 100% | 100% | 97% |
Commencement certificate (CC), as filed on MahaRERA
- Siddha Sky Phase 1: covers Full
Want to know when this changes? Kundli Watch sends a free WhatsApp update on Siddha Sky Phase 1 every month.
Siddha Sky Phase 1: buildings, flats and land, as filed on MahaRERA
| Type | Carpet area (sq ft) | Units |
|---|---|---|
| 1 BHK | 404 – 428 | 211 |
| 2 BHK | 607 – 633 | 111 |
| 3 BHK | 869 | 35 |
- Buildings: Siddha Sky Phase 1 (43 floors, 357 units)
- Car parking: 252 covered
- Land: 7,299 sq m (about 1.8 acres) · sanctioned built-up 27,864 sq m
- Boundaries filed include: Mukund Rao Ambedkar Marg, Mhada Colony
The builder’s record and reviews
Sejal Shakti Realtors (a group of 4 linked companies) has 11 projects on MahaRERA since 2017, this one included. Of the 11 GharKundli has checked: 1 finished, all within the promised date; 9 still being built, none past the promised date yet; 1 lapsed. 44 complaints on MahaRERA across 6 projects.
Read Google reviews of Siddha Sky Phase 1 →Reviews on Google are opinions by Google users; GharKundli doesn’t check them.
Kundli Watch
Siddha Sky Phase 1: buyers & owners
Free: a WhatsApp update every month on this project, and straight away when anything changes on MahaRERA — a later completion date, new complaints, a red flag. Your number stays private: never shown to other members or the builder.
Be the first to watch this project.
How are you connected to this project?
Bought here? No document needed now. From the builder’s team? Join to answer buyers’ questions; you never see members’ details. You’ll sign in with a one-time code, then come straight back here.
Common questions about Siddha Sky Phase 1
What is the possession date of Siddha Sky Phase 1?
According to GharKundli's check of MahaRERA records (updated October 2026), the latest completion date filed on MahaRERA for Siddha Sky Phase 1 in Antop Hill, Mumbai is 30 October 2026 — 6 months later than 31 December 2025, the date given at registration, plus MahaRERA's automatic 4-month extension for all eligible projects. That date has already passed.
Is the builder's possession date different from the MahaRERA date for Siddha Sky Phase 1?
Builders and listing sites often quote an earlier "target" date for handover. The completion date Siddha Sky Phase 1's builder has filed on MahaRERA, the official one, is 30 October 2026, already 6 months later than the 31 December 2025 given at registration, per GharKundli's check of MahaRERA records. If possession is late, what counts under RERA (Section 18) is the possession date written in your agreement for sale.
Why was the possession date of Siddha Sky Phase 1 extended?
According to GharKundli's check of MahaRERA records (updated October 2026), Siddha Sky Phase 1's builder applied to MahaRERA to extend the completion date once: to 30 June 2026, giving the reason "Our project consist of 2 Plinth + Ground + 40 Story Building- entire residential premises. Wherein Original Proposed Completion Date is 31.12.2025. This is the first time we are seeking the extension. We have completed entire RCC work and 80% of finishing is been done. Some of fit out to be done and finishing of some floors is pending. For completion additional vendors have appointed and are working on the same to fulfil. Due to covid-19 pandemic, our project got delayed and supply of materials got disrupted. There was a large-scale reverse migration of labour from state of Maharashtra. Con…". MahaRERA also added its automatic 4-month extension for all eligible projects.
What is the RERA number of Siddha Sky Phase 1?
According to GharKundli's check of MahaRERA records (updated October 2026), the MahaRERA registration number of Siddha Sky Phase 1 in Antop Hill, Mumbai is P51900021027.
Is Siddha Sky Phase 1 registered with MahaRERA?
According to GharKundli's check of MahaRERA records (updated October 2026), Siddha Sky Phase 1 is registered as P51900021027 and its status is "Registered and active".
What is the construction status of Siddha Sky Phase 1?
According to GharKundli's check of MahaRERA records (updated October 2026), Siddha Sky Phase 1's status on MahaRERA is "Registered and active". As filed by the builder, slab work on Siddha Sky Phase 1 is 100% done and internal work 100%. GharKundli's full report compares construction progress with the deadline.
Does Siddha Sky Phase 1 have complaints on MahaRERA?
16 complaints were listed on MahaRERA as of October 2026, per GharKundli's weekly check. GharKundli's full report explains each case and how it ended.
Is Siddha Sky Phase 1 safe to buy?
According to GharKundli's check of MahaRERA records (updated October 2026), Siddha Sky Phase 1 is registered on MahaRERA as P51900021027, its completion date has moved 6 months since registration and 16 complaints are listed against it. GharKundli doesn't call a project safe or unsafe from these numbers alone: its full report gives a risk & trust score with every point explained.
Does Siddha Sky Phase 1 have other wings or phases?
Yes. MahaRERA lists 4 other registrations of the same project, each with its own possession date: Siddha Sky Phase 2 (P51900021040, possession 30 Apr 2027); Siddha Sky Phase 3 (P51900021044, possession 31 Dec 2026); Siddha Sky Phase 4 (P51900021031, possession 30 Apr 2031); SIDDHA SKY PHASE V (P51900055793, possession 31 Mar 2030). Check that your agreement names the registration of your own wing.
How can I get updates if Siddha Sky Phase 1's possession date changes?
The latest dates are on Siddha Sky Phase 1's MahaRERA page (P51900021027). GharKundli's Kundli Watch sends a free WhatsApp update on Siddha Sky Phase 1 every month, and straight away when anything changes on MahaRERA: a later completion date, new complaints or a red flag. Your number is never shown to the builder.
How many floors does Siddha Sky Phase 1 have?
According to GharKundli's check of MahaRERA records (updated October 2026), Siddha Sky Phase 1 has one building filed: Siddha Sky Phase 1 with 43 floors and 357 units.
What are the flat sizes (carpet area) in Siddha Sky Phase 1?
According to GharKundli's check of MahaRERA records (updated October 2026), the builder has filed these homes for Siddha Sky Phase 1: 1 BHK: 404 to 428 sq ft carpet (211 homes); 2 BHK: 607 to 633 sq ft carpet (111 homes); 3 BHK: 869 sq ft carpet (35 homes). Carpet area is the usable floor area inside the walls, as defined under RERA.
How much parking does Siddha Sky Phase 1 have?
According to GharKundli's check of MahaRERA records (updated October 2026), the builder has filed 252 covered car parking spaces for Siddha Sky Phase 1.
How big is the land of Siddha Sky Phase 1?
According to GharKundli's check of MahaRERA records (updated October 2026), Siddha Sky Phase 1 stands on 7,299 sq m of land (about 1.8 acres), with 27,864 sq m of sanctioned built-up area.
What is the track record of Siddha Sky Phase 1's builder?
According to GharKundli's check of MahaRERA records (updated October 2026), Sejal Shakti Realtors (a group of 4 linked companies) has 11 projects on MahaRERA since 2017, this one included. Of the 11 GharKundli has checked: 1 finished, all within the promised date; 9 still being built, none past the promised date yet; 1 lapsed. 44 complaints on MahaRERA across 6 projects. GharKundli's full report covers the builder's record in detail.
Where can I read reviews of Siddha Sky Phase 1?
Google Maps has reviews of Siddha Sky Phase 1 written by Google users; GharKundli links to them on this page but doesn't check them. For facts rather than opinions: 16 complaints are listed on MahaRERA, and Kundli Watch shows verified owners of the project.
Where is Siddha Sky Phase 1?
Siddha Sky Phase 1 by Sejal Shakti Realtors LLP is in Antop Hill, Mumbai (pincode 400037), Maharashtra, and is registered on MahaRERA as P51900021027, per GharKundli's check of MahaRERA records. Its boundaries filed there include Mukund Rao Ambedkar Marg, Mhada Colony.
How many homes are in Siddha Sky Phase 1?
According to GharKundli's check of MahaRERA records (updated October 2026), Siddha Sky Phase 1 has 357 homes in 1 tower registered on MahaRERA, and 89% of them are sold or booked.
When was Siddha Sky Phase 1 registered on MahaRERA?
According to GharKundli's check of MahaRERA records (updated October 2026), Siddha Sky Phase 1 was registered on MahaRERA on 27 May 2019. GharKundli did not find a title report on the land on file there.
Are there court cases on Siddha Sky Phase 1?
No court cases are listed for Siddha Sky Phase 1 on MahaRERA, and 1 appeal at the tribunal, per GharKundli's check of MahaRERA records (updated October 2026). GharKundli's full report explains each case and how it ended.
Who is the builder of Siddha Sky Phase 1?
According to GharKundli's check of MahaRERA records (updated October 2026), the builder is Sejal Shakti Realtors LLP, which has 2 other projects registered on MahaRERA.
Check it yourself on MahaRERA
- How to check the possession date of Siddha Sky Phase 1
- How to find and verify a MahaRERA number
- How to check construction status on MahaRERA
- Occupancy certificate (OC): what to check before possession
- Possession delayed? Work out the interest the builder owes
- How to file a MahaRERA complaint against a builder
- Where MahaRERA complaints are: the data
- Why builders ask MahaRERA for more time: the data
All projects with possession due in 2026 in Mumbai City →
Other projects in pincode 400037
- Shreeji Towers
- MAARIA ANNEXE
- Siddha Sky Phase 3
- Siddha Sky Phase 4
- Vanu Heights
- Bhavya Elite
- SIDDHA SKY PHASE V
- BUILDING NO 6 AJMERA GREENFINITY A WING B WING
Other projects by Sejal Shakti Realtors LLP
Data compiled by GharKundli (gharkundli.com) from MahaRERA public records, as of October 2026. Check the project’s MahaRERA page for the latest filings. Not legal advice.