STUVI RESIDENCY
by STUVI REALITY LLP · Goregaon, MumbaiAlso near Kalanagar, Jawahar Nagar, Kandivali West
Possession date of STUVI RESIDENCY: 30 April 2030, moved from 31 December 2027 (24 months later). This is the latest completion date the builder has filed on MahaRERA. How to check it yourself
Registered on MahaRERA under PR1180002600462, and currently active. Its completion date has moved from December 2027 to April 2030: 24 months at the builder's request, plus MahaRERA's automatic 4-month extension for all eligible projects.
Source: GharKundli’s check of MahaRERA records, October 2026.
What do you want to know about STUVI RESIDENCY?
How the possession date of STUVI RESIDENCY has moved
31 December 2027
Completion date given when the project was registered
31 December 2029
Extended at the builder's request (MahaRERA application EA25062621524)
Reason the builder gave MahaRERA: “There were liquidity issues and delays in funding. Labour and material shortages, along with disruptions in supply chains and workforce availability, are impacting construction timelines.”
30 April 2030
MahaRERA's automatic 4-month extension for all eligible projects, not the builder's request
Source: STUVI RESIDENCY’s extension records on MahaRERA (PR1180002600462), read by GharKundli in October 2026. The builder’s reasons are quoted as filed. Your own possession date is the one in your agreement for sale.
What builders tell MahaRERA when they’re late: 14,973 applications analysed →GharKundli’s full report on STUVI RESIDENCY
Read from every filing on MahaRERA when you open it
- Risk & trust score, every point explained
- What the title report says about the land
- Each of the 2 court cases, and how it ended
- Construction pace against the April 2030 deadline
- Agreement clauses weaker than the RERA model
- Escrow audit, loans and the builder's record
- Questions to get answered in writing before you pay
- MahaRERA registration
- PR1180002600462
- Status
- Registered and active
- Builder
- STUVI REALITY LLP
- Location
- Goregaon, Mumbai · 400062
- Project type
- Residential / Group Housing
- Registered on
- 18 May 2026
- Completion date at registration
- December 2027
- Latest completion date
- April 2030
- Delay so far
- 24 months
- MahaRERA's automatic extension
- +4 months (force majeure, all eligible projects)
- Homes
- 12
- Sold or booked
- 25%
- Towers
- 1
- Complaints on MahaRERA
- 0
- Court cases listed
- 2
- Title report on file
- Not found
Construction progress of STUVI RESIDENCY, as filed by the builder
What the builder has reported to MahaRERA, as GharKundli read it in October 2026. GharKundli’s full report compares it with the deadline.
| Tower / wing | Plinth | Slabs (structure) | Internal work | Lifts, fire & electrical |
|---|---|---|---|---|
| STUVI RESIDENCY | 0% | 0% | 0% | 0% |
Commencement certificate (CC), as filed on MahaRERA
- STUVI RESIDENCY: covers up to top of plinth level only
Latest CC order on MahaRERA: dated 01/12/2025.
Want to know when this changes? Kundli Watch sends a free WhatsApp update on STUVI RESIDENCY every month.
STUVI RESIDENCY: buildings, flats and land, as filed on MahaRERA
| Type | Carpet area (sq ft) | Units |
|---|---|---|
| 1 BHK | 323 – 571 | 12 |
- Buildings: STUVI RESIDENCY (4 floors, 12 units)
- Car parking: 12 covered
- Land: 545 sq m (about 0.1 acres) · sanctioned built-up 610 sq m
- Map: the location the builder filed on MahaRERA
The builder’s record and reviews
Not enough of this builder’s other MahaRERA projects have reached their promised date to judge yet.
Read Google reviews of STUVI RESIDENCY →Reviews on Google are opinions by Google users; GharKundli doesn’t check them.
Kundli Watch
STUVI RESIDENCY: buyers & owners
Free: a WhatsApp update every month on this project, and straight away when anything changes on MahaRERA — a later completion date, new complaints, a red flag. Your number stays private: never shown to other members or the builder.
Be the first to watch this project.
How are you connected to this project?
Bought here? No document needed now. From the builder’s team? Join to answer buyers’ questions; you never see members’ details. You’ll sign in with a one-time code, then come straight back here.
Common questions about STUVI RESIDENCY
What is the possession date of STUVI RESIDENCY?
According to GharKundli's check of MahaRERA records (updated October 2026), the latest completion date filed on MahaRERA for STUVI RESIDENCY in Goregaon, Mumbai is 30 April 2030 — 24 months later than 31 December 2027, the date given at registration, plus MahaRERA's automatic 4-month extension for all eligible projects.
Is the builder's possession date different from the MahaRERA date for STUVI RESIDENCY?
Builders and listing sites often quote an earlier "target" date for handover. The completion date STUVI RESIDENCY's builder has filed on MahaRERA, the official one, is 30 April 2030, already 24 months later than the 31 December 2027 given at registration, per GharKundli's check of MahaRERA records. If possession is late, what counts under RERA (Section 18) is the possession date written in your agreement for sale.
Why was the possession date of STUVI RESIDENCY extended?
According to GharKundli's check of MahaRERA records (updated October 2026), STUVI RESIDENCY's builder applied to MahaRERA to extend the completion date once: to 31 December 2029, giving the reason "There were liquidity issues and delays in funding. Labour and material shortages, along with disruptions in supply chains and workforce availability, are impacting construction timelines.". MahaRERA also added its automatic 4-month extension for all eligible projects.
What is the RERA number of STUVI RESIDENCY?
According to GharKundli's check of MahaRERA records (updated October 2026), the MahaRERA registration number of STUVI RESIDENCY in Goregaon, Mumbai is PR1180002600462.
Is STUVI RESIDENCY registered with MahaRERA?
According to GharKundli's check of MahaRERA records (updated October 2026), STUVI RESIDENCY is registered as PR1180002600462 and its status is "Registered and active".
What is the construction status of STUVI RESIDENCY?
According to GharKundli's check of MahaRERA records (updated October 2026), STUVI RESIDENCY's status on MahaRERA is "Registered and active". As filed by the builder, slab work on STUVI RESIDENCY is 0% done and internal work 0%. GharKundli's full report compares construction progress with the deadline.
Does STUVI RESIDENCY have complaints on MahaRERA?
No complaints were listed on MahaRERA as of October 2026, per GharKundli's weekly check.
Is STUVI RESIDENCY safe to buy?
According to GharKundli's check of MahaRERA records (updated October 2026), STUVI RESIDENCY is registered on MahaRERA as PR1180002600462, its completion date has moved 24 months since registration and no complaints are listed against it. GharKundli doesn't call a project safe or unsafe from these numbers alone: its full report gives a risk & trust score with every point explained.
How can I get updates if STUVI RESIDENCY's possession date changes?
The latest dates are on STUVI RESIDENCY's MahaRERA page (PR1180002600462). GharKundli's Kundli Watch sends a free WhatsApp update on STUVI RESIDENCY every month, and straight away when anything changes on MahaRERA: a later completion date, new complaints or a red flag. Your number is never shown to the builder.
How many floors does STUVI RESIDENCY have?
According to GharKundli's check of MahaRERA records (updated October 2026), STUVI RESIDENCY has one building filed: STUVI RESIDENCY with 4 floors and 12 units.
What are the flat sizes (carpet area) in STUVI RESIDENCY?
According to GharKundli's check of MahaRERA records (updated October 2026), the builder has filed these homes for STUVI RESIDENCY: 1 BHK: 323 to 571 sq ft carpet (12 homes). Carpet area is the usable floor area inside the walls, as defined under RERA.
How much parking does STUVI RESIDENCY have?
According to GharKundli's check of MahaRERA records (updated October 2026), the builder has filed 12 covered car parking spaces for STUVI RESIDENCY.
How big is the land of STUVI RESIDENCY?
According to GharKundli's check of MahaRERA records (updated October 2026), STUVI RESIDENCY stands on 545 sq m of land (about 0.1 acres), with 610 sq m of sanctioned built-up area.
Where can I read reviews of STUVI RESIDENCY?
Google Maps has reviews of STUVI RESIDENCY written by Google users; GharKundli links to them on this page but doesn't check them. For facts rather than opinions: no complaints are listed on MahaRERA, and Kundli Watch shows verified owners of the project.
Where is STUVI RESIDENCY?
STUVI RESIDENCY by STUVI REALITY LLP is in Goregaon, Mumbai (pincode 400062), near Kalanagar, Jawahar Nagar, Kandivali West, Maharashtra, and is registered on MahaRERA as PR1180002600462, per GharKundli's check of MahaRERA records.
How many homes are in STUVI RESIDENCY?
According to GharKundli's check of MahaRERA records (updated October 2026), STUVI RESIDENCY has 12 homes in 1 tower registered on MahaRERA, and 25% of them are sold or booked.
When was STUVI RESIDENCY registered on MahaRERA?
According to GharKundli's check of MahaRERA records (updated October 2026), STUVI RESIDENCY was registered on MahaRERA on 18 May 2026. GharKundli did not find a title report on the land on file there.
Are there court cases on STUVI RESIDENCY?
2 court cases are listed for STUVI RESIDENCY on MahaRERA, per GharKundli's check of MahaRERA records (updated October 2026). GharKundli's full report explains each case and how it ended.
Who is the builder of STUVI RESIDENCY?
According to GharKundli's check of MahaRERA records (updated October 2026), the builder is STUVI REALITY LLP.
Check it yourself on MahaRERA
- How to check the possession date of STUVI RESIDENCY
- How to find and verify a MahaRERA number
- How to check construction status on MahaRERA
- Occupancy certificate (OC): what to check before possession
- Possession delayed? Work out the interest the builder owes
- How to file a MahaRERA complaint against a builder
- Where MahaRERA complaints are: the data
- Why builders ask MahaRERA for more time: the data
Other projects in Goregaon
All Borivali projects with no pincode on MahaRERA →
Data compiled by GharKundli (gharkundli.com) from MahaRERA public records, as of October 2026. Check the project’s MahaRERA page for the latest filings. Not legal advice.