by PLATINUM URBAN DEVELOPERS LLP (Platinumcorp) · Ambivali, Mumbai 400053Also near Andheri West, Amboli, Azad Nagar

What’s in the report? →

Possession date of Platinum Vibe (MahaRERA PR1180002600307): 30 April 2031. It has 107 homes (1 BHK, 2 BHK and 3 BHK, 300–1180 sq ft carpet), 1% sold or booked. No complaints on MahaRERA. How to check it yourself

Registered on MahaRERA under PR1180002600307, and currently active. Its completion date is now April 2031, including MahaRERA's automatic 4-month extension for all eligible projects; the builder hasn't asked for more time.

Source: MahaRERA website — records for PR1180002600307, read and compiled by GharKundli. Facts as filed on MahaRERA, no opinions.

What do you want to know about Platinum Vibe?

Title report MahaRERA par nahi dikh rahi. Kya poochna hai?Tap a question. We’ll answer you on WhatsApp, free.

Ask something else on WhatsAppNo login needed. A real person replies.

Or leave your number, we’ll message you:

How the possession date of Platinum Vibe has moved

  1. 31 December 2030

    Completion date given when the project was registered

  2. 30 April 2031

    MahaRERA's automatic 4-month extension for all eligible projects, not the builder's request

Source: Platinum Vibe’s extension records on MahaRERA (PR1180002600307), read by GharKundli in October 2026. The builder’s reasons are quoted as filed. Your own possession date is the one in your agreement for sale.

What builders tell MahaRERA when they’re late: 14,973 applications analysed →

GharKundli’s full report on Platinum Vibe

Read from every filing on MahaRERA when you open it

  • Risk & trust score, every point explained
  • What the title report says about the land
  • Each complaint and court case, and how it ended
  • Construction pace against the April 2031 deadline
  • Agreement clauses weaker than the RERA model
  • Escrow audit, loans and the builder's record
  • Questions to get answered in writing before you pay
MahaRERA registration
PR1180002600307
Status
Registered and active
Builder
PLATINUM URBAN DEVELOPERS LLP
Location
Ambivali, Mumbai · 400053
Project type
Residential / Group Housing
Registered on
30 Apr 2026
Completion date at registration
December 2030
Latest completion date
April 2031
MahaRERA's automatic extension
+4 months (force majeure, all eligible projects)
Homes
107
Sold or booked
1%
Towers
2
Complaints on MahaRERA
0
Court cases listed
0
Title report on file
Not found

Construction progress of Platinum Vibe, as filed by the builder

What the builder has reported to MahaRERA, as GharKundli read it in October 2026. GharKundli’s full report compares it with the deadline.

Tower / wingPlinthSlabs (structure)Internal workLifts, fire & electrical
PLATINUM VIBE / Wing-A0%0%0%0%
PLATINUM VIBE / Wing-B0%0%0%0%

Commencement certificate (CC), as filed on MahaRERA

  • PLATINUM VIBE: covers Upto Plinth Level
  • PLATINUM VIBE: covers Upto Plinth Level

Latest CC order on MahaRERA: dated 27/03/2026.

Want to know when this changes? Kundli Watch sends a free WhatsApp update on Platinum Vibe every 1–2 months.

Platinum Vibe: buildings, flats and land, as filed on MahaRERA

TypeCarpet area (sq ft)Units
Other30067
3 BHK732 – 89514
2 BHK591 – 70514
4 BHK969 – 1,18011
Shops2,760 – 5,8504
1 BHK4301

The builder’s record and reviews

Platinumcorp Elegant Housing (a group of 15 linked companies) has 16 projects on MahaRERA since 2017, this one included. Of the 16 GharKundli has checked: 8 finished, 5 within the promised date and 3 needed more time (typically 9 months); 8 still being built, 1 past the promised date (typically 6 months late). 20 complaints on MahaRERA across 5 projects.

Read Google reviews of Platinum Vibe →Reviews on Google are opinions by Google users; GharKundli doesn’t check them.

Kundli Watch

Platinum Vibe: buyers & owners

Free: a construction progress update on WhatsApp every 1–2 months, and straight away when anything changes on MahaRERA — a later completion date, new complaints, a red flag. Your number stays private: never shown to other members or the builder.

Be the first to watch this project.

How are you connected to this project?

Watching needs only WhatsApp or your number. Bought here? No document needed now. From the builder’s team? Join to answer buyers’ questions; you never see members’ details. Owners and the builder’s team sign in with a one-time code, then come straight back here.

Common questions about Platinum Vibe

What is the possession date of Platinum Vibe?

According to GharKundli's check of MahaRERA records (updated October 2026), the latest completion date filed on MahaRERA for Platinum Vibe in Ambivali, Mumbai is 30 April 2031, including MahaRERA's automatic 4-month extension for all eligible projects.

Is the builder's possession date different from the MahaRERA date for Platinum Vibe?

Builders and listing sites often quote an earlier "target" date for handover. The completion date Platinum Vibe's builder has filed on MahaRERA, the official one, is 30 April 2031, per GharKundli's check of MahaRERA records. If possession is late, what counts under RERA (Section 18) is the possession date written in your agreement for sale.

What is the RERA number of Platinum Vibe?

According to GharKundli's check of MahaRERA records (updated October 2026), the MahaRERA registration number of Platinum Vibe in Ambivali, Mumbai is PR1180002600307.

Is Platinum Vibe registered with MahaRERA?

According to GharKundli's check of MahaRERA records (updated October 2026), Platinum Vibe is registered as PR1180002600307 and its status is "Registered and active".

What is the current construction status of Platinum Vibe? How much work is done?

According to GharKundli's check of MahaRERA records (updated October 2026), Platinum Vibe's status on MahaRERA is "Registered and active". As filed by the builder, slab work is 0% done across 2 towers. GharKundli's full report compares construction progress with the deadline.

Does Platinum Vibe have complaints on MahaRERA?

No complaints were listed on MahaRERA as of October 2026, per GharKundli's weekly check.

Is Platinum Vibe safe to buy?

According to GharKundli's check of MahaRERA records (updated October 2026), Platinum Vibe is registered on MahaRERA as PR1180002600307, its completion date has not been moved by the builder and no complaints are listed against it. GharKundli doesn't call a project safe or unsafe from these numbers alone: its full report gives a risk & trust score with every point explained.

How much GST is payable on a flat in Platinum Vibe?

Platinum Vibe is under construction, so GST applies to a new flat: 5% of the price, with no input tax credit. The lower 1% rate is only for "affordable" homes: carpet area up to 60 sq m (about 646 sq ft) in the Mumbai region, and price up to ₹45 lakh. Some flats in Platinum Vibe are 300 sq ft carpet, small enough for 1% if the price is ₹45 lakh or less. There is no GST on stamp duty or registration, and none once the occupancy certificate is issued.

What is the stamp duty and registration cost for a flat in Platinum Vibe?

For a flat in Platinum Vibe (Mumbai), stamp duty is 6% of the agreement value, or of the ready reckoner value if that's higher, including 1% Metro Cess. A woman buying in her own name pays 5%. Registration is 1% of the value, capped at ₹30,000. On a ₹1 crore flat that's about ₹6 lakh in stamp duty plus ₹30,000 registration. GharKundli's property cost calculator works it out for your price: gharkundli.com/tools/property-cost-calculator

Has Platinum Vibe received its OC? Is it ready to move in?

Not yet. According to GharKundli's check of MahaRERA records (updated October 2026), Platinum Vibe is still under construction, with 30 April 2031 as the latest completion date filed on MahaRERA. A flat is ready to move in only once the occupancy certificate (OC) is issued, after construction is complete.

Is Platinum Vibe a redevelopment or SRA project?

According to GharKundli's check of MahaRERA records (updated October 2026), Platinum Vibe is a redevelopment: 33 of its flats are set aside for existing occupants (rehab), and the rest are for sale.

Has Platinum Vibe uploaded its title report on MahaRERA?

According to GharKundli's check of MahaRERA records (updated October 2026), no title report for Platinum Vibe was found on MahaRERA. Builders are expected to upload one; before booking, ask the builder for the advocate's title certificate in writing.

No title report is on MahaRERA for this project. See which documents are missing →

How can I get updates if Platinum Vibe's possession date changes?

The latest dates are on Platinum Vibe's MahaRERA page (PR1180002600307). GharKundli's Kundli Watch sends a free WhatsApp update on Platinum Vibe every 1–2 months, and straight away when anything changes on MahaRERA: a later completion date, new complaints or a red flag. Your number is never shown to the builder.

How many floors does Platinum Vibe have?

According to GharKundli's check of MahaRERA records (updated October 2026), Platinum Vibe has 2 buildings filed: PLATINUM VIBE with 20 floors and 60 units; PLATINUM VIBE with 20 floors and 51 units.

What are the flat sizes (carpet area) in Platinum Vibe?

According to GharKundli's check of MahaRERA records (updated October 2026), the builder has filed these homes for Platinum Vibe: Other: 300 sq ft carpet (67 homes); 3 BHK: 732 to 895 sq ft carpet (14 homes); 2 BHK: 591 to 705 sq ft carpet (14 homes); 4 BHK: 969 to 1180 sq ft carpet (11 homes); 1 BHK: 430 sq ft carpet (1 homes). Carpet area is the usable floor area inside the walls, as defined under RERA.

How much parking does Platinum Vibe have?

According to GharKundli's check of MahaRERA records (updated October 2026), the builder has filed 129 covered car parking spaces for Platinum Vibe.

How big is the land of Platinum Vibe?

According to GharKundli's check of MahaRERA records (updated October 2026), Platinum Vibe stands on 1,672 sq m of land (about 0.4 acres), with 7,258 sq m of sanctioned built-up area.

What is the track record of Platinum Vibe's builder?

According to GharKundli's check of MahaRERA records (updated October 2026), Platinumcorp Elegant Housing (a group of 15 linked companies) has 16 projects on MahaRERA since 2017, this one included. Of the 16 GharKundli has checked: 8 finished, 5 within the promised date and 3 needed more time (typically 9 months); 8 still being built, 1 past the promised date (typically 6 months late). 20 complaints on MahaRERA across 5 projects. GharKundli's full report covers the builder's record in detail.

What are the reviews of Platinum Vibe?

Google Maps has reviews of Platinum Vibe written by Google users; GharKundli links to them on this page but doesn't check them. For facts rather than opinions: no complaints are listed on MahaRERA, and Kundli Watch shows verified owners of the project.

What is the address and pincode of Platinum Vibe?

Platinum Vibe by PLATINUM URBAN DEVELOPERS LLP (Platinumcorp) is in Ambivali, Mumbai, pincode 400053 (near Andheri West, Amboli, Azad Nagar), Maharashtra, and is registered on MahaRERA as PR1180002600307, per GharKundli's check of MahaRERA records. GharKundli lists all 162 MahaRERA projects in Andheri West (400053).

How many flats are in Platinum Vibe, and how many are sold?

According to GharKundli's check of MahaRERA records (updated October 2026), Platinum Vibe has 107 homes in 2 towers registered on MahaRERA, and 1% of them are sold or booked.

When was Platinum Vibe registered on MahaRERA?

According to GharKundli's check of MahaRERA records (updated October 2026), Platinum Vibe was registered on MahaRERA on 30 April 2026. GharKundli did not find a title report on the land on file there.

Does Platinum Vibe have any legal issues or court cases?

No court cases are listed for Platinum Vibe on MahaRERA, per GharKundli's check of MahaRERA records (updated October 2026).

Who is the builder / developer of Platinum Vibe?

According to GharKundli's check of MahaRERA records (updated October 2026), the builder is PLATINUM URBAN DEVELOPERS LLP, the company Platinumcorp files this project under.

All projects with possession due in 2031 in Mumbai Suburban →

Other projects in Andheri

All 162 projects in Andheri West (400053) →

Data compiled by GharKundli (gharkundli.com) from MahaRERA public records, as of October 2026. Check the project’s MahaRERA page for the latest filings. Not legal advice.