Possession date of Amboli Composite Building Rehab Wing A1 (MahaRERA PR1180002600194): 30 April 2029. It has 87 homes (1 BHK, 300–318 sq ft carpet), 0% sold or booked. No complaints on MahaRERA. How to check it yourself

Registered on MahaRERA under PR1180002600194, and currently active. Its completion date is now April 2029, including MahaRERA's automatic 4-month extension for all eligible projects; the builder hasn't asked for more time.

Source: MahaRERA website — records for PR1180002600194, read and compiled by GharKundli. Facts as filed on MahaRERA, no opinions.

What do you want to know about Amboli Composite Building Rehab Wing A1?

Title report MahaRERA par nahi dikh rahi. Kya poochna hai?Tap a question. We’ll answer you on WhatsApp, free.

Ask something else on WhatsAppNo login needed. A real person replies.

Or leave your number, we’ll message you:

How the possession date of Amboli Composite Building Rehab Wing A1 has moved

  1. 31 December 2028

    Completion date given when the project was registered

  2. 30 April 2029

    MahaRERA's automatic 4-month extension for all eligible projects, not the builder's request

Source: Amboli Composite Building Rehab Wing A1’s extension records on MahaRERA (PR1180002600194), read by GharKundli in October 2026. The builder’s reasons are quoted as filed. Your own possession date is the one in your agreement for sale.

What builders tell MahaRERA when they’re late: 14,973 applications analysed →

GharKundli’s full report on Amboli Composite Building Rehab Wing A1

Read from every filing on MahaRERA when you open it

  • Risk & trust score, every point explained
  • What the title report says about the land
  • Each complaint and court case, and how it ended
  • Construction pace against the April 2029 deadline
  • Agreement clauses weaker than the RERA model
  • Escrow audit, loans and the builder's record
  • Questions to get answered in writing before you pay
MahaRERA registration
PR1180002600194
Status
Registered and active
Builder
A R AMBOLI DEVELOPERS PRIVATE LIMITED
Location
Amboli, Mumbai · 400058
Project type
Residential / Group Housing
Registered on
18 Apr 2026
Completion date at registration
December 2028
Latest completion date
April 2029
MahaRERA's automatic extension
+4 months (force majeure, all eligible projects)
Homes
87
Sold or booked
0%
Towers
1
Complaints on MahaRERA
0
Court cases listed
0
Title report on file
Not found
Builder's other MahaRERA projects
2

Construction progress of Amboli Composite Building Rehab Wing A1, as filed by the builder

What the builder has reported to MahaRERA, as GharKundli read it in October 2026. GharKundli’s full report compares it with the deadline.

Tower / wingPlinthSlabs (structure)Internal workLifts, fire & electrical
Composite Buidling Rehab Wing A1100%———

Commencement certificate (CC), as filed on MahaRERA

  • Composite Buidling Rehab Wing A1: covers plinth level

Latest CC order on MahaRERA: dated 01/09/2025.

Want to know when this changes? Kundli Watch sends a free WhatsApp update on Amboli Composite Building Rehab Wing A1 every 1–2 months.

Amboli Composite Building Rehab Wing A1: buildings, flats and land, as filed on MahaRERA

TypeCarpet area (sq ft)Units
1 BHK300 – 31887

The builder’s record and reviews

A R Amboli Developers (a group of 2 linked companies) has 4 projects on MahaRERA since 2019, this one included. Of the 4 GharKundli has checked: 1 finished, all within the promised date; 2 still being built, none past the promised date yet; 1 lapsed. No complaints on MahaRERA.

Read Google reviews of Amboli Composite Building Rehab Wing A1 →Reviews on Google are opinions by Google users; GharKundli doesn’t check them.

Kundli Watch

Amboli Composite Building Rehab Wing A1: buyers & owners

Free: a construction progress update on WhatsApp every 1–2 months, and straight away when anything changes on MahaRERA — a later completion date, new complaints, a red flag. Your number stays private: never shown to other members or the builder.

Be the first to watch this project.

How are you connected to this project?

Watching needs only WhatsApp or your number. Bought here? No document needed now. From the builder’s team? Join to answer buyers’ questions; you never see members’ details. Owners and the builder’s team sign in with a one-time code, then come straight back here.

Common questions about Amboli Composite Building Rehab Wing A1

What is the possession date of Amboli Composite Building Rehab Wing A1?

According to GharKundli's check of MahaRERA records (updated October 2026), the latest completion date filed on MahaRERA for Amboli Composite Building Rehab Wing A1 in Amboli, Mumbai is 30 April 2029, including MahaRERA's automatic 4-month extension for all eligible projects.

Is the builder's possession date different from the MahaRERA date for Amboli Composite Building Rehab Wing A1?

Builders and listing sites often quote an earlier "target" date for handover. The completion date Amboli Composite Building Rehab Wing A1's builder has filed on MahaRERA, the official one, is 30 April 2029, per GharKundli's check of MahaRERA records. If possession is late, what counts under RERA (Section 18) is the possession date written in your agreement for sale.

What is the RERA number of Amboli Composite Building Rehab Wing A1?

According to GharKundli's check of MahaRERA records (updated October 2026), the MahaRERA registration number of Amboli Composite Building Rehab Wing A1 in Amboli, Mumbai is PR1180002600194.

Is Amboli Composite Building Rehab Wing A1 registered with MahaRERA?

According to GharKundli's check of MahaRERA records (updated October 2026), Amboli Composite Building Rehab Wing A1 is registered as PR1180002600194 and its status is "Registered and active".

What is the current construction status of Amboli Composite Building Rehab Wing A1? How much work is done?

According to GharKundli's check of MahaRERA records (updated October 2026), Amboli Composite Building Rehab Wing A1's status on MahaRERA is "Registered and active". GharKundli's full report compares construction progress with the deadline.

Does Amboli Composite Building Rehab Wing A1 have complaints on MahaRERA?

No complaints were listed on MahaRERA as of October 2026, per GharKundli's weekly check.

Is Amboli Composite Building Rehab Wing A1 safe to buy?

According to GharKundli's check of MahaRERA records (updated October 2026), Amboli Composite Building Rehab Wing A1 is registered on MahaRERA as PR1180002600194, its completion date has not been moved by the builder and no complaints are listed against it. GharKundli doesn't call a project safe or unsafe from these numbers alone: its full report gives a risk & trust score with every point explained.

How much GST is payable on a flat in Amboli Composite Building Rehab Wing A1?

Amboli Composite Building Rehab Wing A1 is under construction, so GST applies to a new flat: 5% of the price, with no input tax credit. The lower 1% rate is only for "affordable" homes: carpet area up to 60 sq m (about 646 sq ft) in the Mumbai region, and price up to ₹45 lakh. Some flats in Amboli Composite Building Rehab Wing A1 are 300 sq ft carpet, small enough for 1% if the price is ₹45 lakh or less. There is no GST on stamp duty or registration, and none once the occupancy certificate is issued.

What is the stamp duty and registration cost for a flat in Amboli Composite Building Rehab Wing A1?

For a flat in Amboli Composite Building Rehab Wing A1 (Mumbai), stamp duty is 6% of the agreement value, or of the ready reckoner value if that's higher, including 1% Metro Cess. A woman buying in her own name pays 5%. Registration is 1% of the value, capped at ₹30,000. On a ₹1 crore flat that's about ₹6 lakh in stamp duty plus ₹30,000 registration. GharKundli's property cost calculator works it out for your price: gharkundli.com/tools/property-cost-calculator

Has Amboli Composite Building Rehab Wing A1 received its OC? Is it ready to move in?

Not yet. According to GharKundli's check of MahaRERA records (updated October 2026), Amboli Composite Building Rehab Wing A1 is still under construction, with 30 April 2029 as the latest completion date filed on MahaRERA. A flat is ready to move in only once the occupancy certificate (OC) is issued, after construction is complete.

Has Amboli Composite Building Rehab Wing A1 uploaded its title report on MahaRERA?

According to GharKundli's check of MahaRERA records (updated October 2026), no title report for Amboli Composite Building Rehab Wing A1 was found on MahaRERA. Builders are expected to upload one; before booking, ask the builder for the advocate's title certificate in writing.

No title report is on MahaRERA for this project. See which documents are missing →

How can I get updates if Amboli Composite Building Rehab Wing A1's possession date changes?

The latest dates are on Amboli Composite Building Rehab Wing A1's MahaRERA page (PR1180002600194). GharKundli's Kundli Watch sends a free WhatsApp update on Amboli Composite Building Rehab Wing A1 every 1–2 months, and straight away when anything changes on MahaRERA: a later completion date, new complaints or a red flag. Your number is never shown to the builder.

How many floors does Amboli Composite Building Rehab Wing A1 have?

According to GharKundli's check of MahaRERA records (updated October 2026), Amboli Composite Building Rehab Wing A1 has one building filed: Composite Buidling Rehab Wing A1 with 20 floors and 87 units.

What are the flat sizes (carpet area) in Amboli Composite Building Rehab Wing A1?

According to GharKundli's check of MahaRERA records (updated October 2026), the builder has filed these homes for Amboli Composite Building Rehab Wing A1: 1 BHK: 300 to 318 sq ft carpet (87 homes). Carpet area is the usable floor area inside the walls, as defined under RERA.

How much parking does Amboli Composite Building Rehab Wing A1 have?

According to GharKundli's check of MahaRERA records (updated October 2026), the builder has filed 9 covered car parking spaces for Amboli Composite Building Rehab Wing A1.

How big is the land of Amboli Composite Building Rehab Wing A1?

According to GharKundli's check of MahaRERA records (updated October 2026), Amboli Composite Building Rehab Wing A1 stands on 424 sq m of land (about 0.1 acres), with 3,445 sq m of sanctioned built-up area and 53 sq m of recreational open space.

What is the track record of Amboli Composite Building Rehab Wing A1's builder?

According to GharKundli's check of MahaRERA records (updated October 2026), A R Amboli Developers (a group of 2 linked companies) has 4 projects on MahaRERA since 2019, this one included. Of the 4 GharKundli has checked: 1 finished, all within the promised date; 2 still being built, none past the promised date yet; 1 lapsed. No complaints on MahaRERA. GharKundli's full report covers the builder's record in detail.

What are the reviews of Amboli Composite Building Rehab Wing A1?

Google Maps has reviews of Amboli Composite Building Rehab Wing A1 written by Google users; GharKundli links to them on this page but doesn't check them. For facts rather than opinions: no complaints are listed on MahaRERA, and Kundli Watch shows verified owners of the project.

What is the address and pincode of Amboli Composite Building Rehab Wing A1?

Amboli Composite Building Rehab Wing A1 by A R AMBOLI DEVELOPERS PRIVATE LIMITED is in Amboli, Mumbai, pincode 400058 (near Andheri West, Jogeshwari East, Ambivali West), Maharashtra, and is registered on MahaRERA as PR1180002600194, per GharKundli's check of MahaRERA records. GharKundli lists all 148 MahaRERA projects in Andheri West (400058).

How many flats are in Amboli Composite Building Rehab Wing A1, and how many are sold?

According to GharKundli's check of MahaRERA records (updated October 2026), Amboli Composite Building Rehab Wing A1 has 87 homes in 1 tower registered on MahaRERA, and 0% of them are sold or booked.

When was Amboli Composite Building Rehab Wing A1 registered on MahaRERA?

According to GharKundli's check of MahaRERA records (updated October 2026), Amboli Composite Building Rehab Wing A1 was registered on MahaRERA on 18 April 2026. GharKundli did not find a title report on the land on file there.

Does Amboli Composite Building Rehab Wing A1 have any legal issues or court cases?

No court cases are listed for Amboli Composite Building Rehab Wing A1 on MahaRERA, per GharKundli's check of MahaRERA records (updated October 2026).

Who is the builder / developer of Amboli Composite Building Rehab Wing A1?

According to GharKundli's check of MahaRERA records (updated October 2026), the builder is A R AMBOLI DEVELOPERS PRIVATE LIMITED, which has 2 other projects registered on MahaRERA.

All projects with possession due in 2029 in Mumbai Suburban →

Other projects in Andheri

All 148 projects in Andheri West (400058) →

Other projects by A R AMBOLI DEVELOPERS PRIVATE LIMITED

Data compiled by GharKundli (gharkundli.com) from MahaRERA public records, as of October 2026. Check the project’s MahaRERA page for the latest filings. Not legal advice.