The New Green Chambers CHS

by ELITE CONSTRUCTION CO · Byculla, Mumbai 400008

What’s in the report? →

Possession date of The New Green Chambers CHS (MahaRERA P51900022675): 31 December 2025, moved from 30 June 2022 (42 months later), and it has already passed. It has 17 homes. No complaints on MahaRERA. How to check it yourself

Registered on MahaRERA under P51900022675. Status: Lapsed (registration period ended).

Source: MahaRERA website — records for P51900022675, read and compiled by GharKundli. Facts as filed on MahaRERA, no opinions.

The latest completion date on MahaRERA (December 2025) has passed.

What do you want to know about The New Green Chambers CHS?

Completion date nikal chuki hai. Kya poochna hai?Tap a question. We’ll answer you on WhatsApp, free.

Ask something else on WhatsAppNo login needed. A real person replies.

Or leave your number, we’ll message you:

How the possession date of The New Green Chambers CHS has moved

  1. 30 June 2022

    Completion date given when the project was registered

  2. 30 June 2023

    Extended at the builder's request (MahaRERA application EXT51900012166)

    Reason the builder gave MahaRERA:
    “Due to the lockdown in 2020 and most of 2021, our construction work had come to a stand still. Moreover, there was shortage of labors as most of them had moved to their hometown. The work has now resumed and is in full swing. Kindly allow u…” Read the full reason“Due to the lockdown in 2020 and most of 2021, our construction work had come to a stand still. Moreover, there was shortage of labors as most of them had moved to their hometown. The work has now resumed and is in full swing. Kindly allow us to extend the project.”
  3. 31 December 2023

    Extended at the builder's request (MahaRERA application EXT51900017391)

    Reason the builder gave MahaRERA:
    “In accordance with circular no 28, we hereby apply for extension of our project u/s 7(3) in Format B. The project was delayed for reasons beyond our control on account of various reasons and more particularly on account of the pandemic of C…” Read the full reason“In accordance with circular no 28, we hereby apply for extension of our project u/s 7(3) in Format B. The project was delayed for reasons beyond our control on account of various reasons and more particularly on account of the pandemic of Covid-19. We have consent of 66.67% allottees for purpose of extension of RERA registration period of the said project”
  4. 31 December 2024

    Extended at the builder's request (MahaRERA application EXT51900019191)

    Reason the builder gave MahaRERA:
    “In accordance with circular no 28, we hereby apply for extension of our project u/s 7(3) in Format B. The project was delayed for reasons beyond our control on account of various reasons and more particularly on account of the pandemic of C…” Read the full reason“In accordance with circular no 28, we hereby apply for extension of our project u/s 7(3) in Format B. The project was delayed for reasons beyond our control on account of various reasons and more particularly on account of the pandemic of Covid-19. We have consent of 88.89% allottees for purpose of extension of RERA registration period of the said project.”
  5. 31 December 2025

    Extended at the builder's request (MahaRERA application EXT51900027191)

    Reason the builder gave MahaRERA:
    “We apologize for the delay in the completion of the project and the submission of this request. The delay has occurred due to issues with procurement, unforeseen site conditions, coordination challenges and delay in OC. Despite these setbac…” Read the full reason“We apologize for the delay in the completion of the project and the submission of this request. The delay has occurred due to issues with procurement, unforeseen site conditions, coordination challenges and delay in OC. Despite these setbacks, we are working diligently to address these issues and complete the remaining work. We are closely monitoring progress and taking all necessary steps to ensure timely completion. Given the circumstances, we kindly request an extension until 31-12-2025 to complete the project and fulfil all regulatory requirements. We seek your understanding and approva…”

Source: The New Green Chambers CHS’s extension records on MahaRERA (P51900022675), read by GharKundli in October 2026. The builder’s reasons are quoted as filed. Your own possession date is the one in your agreement for sale.

What builders tell MahaRERA when they’re late: 14,973 applications analysed →

GharKundli’s full report on The New Green Chambers CHS

Read from every filing on MahaRERA when you open it

  • Risk & trust score, every point explained
  • What the title report says about the land
  • Each complaint and court case, and how it ended
  • Construction pace against the December 2025 deadline
  • Agreement clauses weaker than the RERA model
  • Escrow audit, loans and the builder's record
  • Questions to get answered in writing before you pay
MahaRERA registration
P51900022675
Status
Lapsed (registration period ended)
Builder
ELITE CONSTRUCTION CO
Location
Byculla, Mumbai · 400008
Project type
Others
Registered on
12 Oct 2019
Completion date at registration
June 2022
Latest completion date
December 2025
Delay so far
42 months
Homes
17
Towers
1
Complaints on MahaRERA
0
Court cases listed
0
Title report on file
Not found

Construction progress of The New Green Chambers CHS, as filed by the builder

What the builder has reported to MahaRERA, as GharKundli read it in October 2026. GharKundli’s full report compares it with the deadline.

Tower / wingPlinthSlabs (structure)Internal workLifts, fire & electrical
THE NEW GREEN CHAMBERS CHS100%100%100%100%

Want to know when this changes? Kundli Watch sends a free WhatsApp update on The New Green Chambers CHS every 1–2 months.

The New Green Chambers CHS: buildings, flats and land, as filed on MahaRERA

  • Buildings: THE NEW GREEN CHAMBERS CHS (23 floors)
  • Land: 334 sq m (about 0.1 acres) · sanctioned built-up 1,811 sq m
  • Boundaries filed include: Sofia Zubair Road
  • Land, as filed: Plot No - 29
  • Map: Get directions

The builder’s record and reviews

Not enough of this builder’s other MahaRERA projects have reached their promised date to judge yet.

Read Google reviews of The New Green Chambers CHS →Reviews on Google are opinions by Google users; GharKundli doesn’t check them.

Kundli Watch

The New Green Chambers CHS: buyers & owners

Free: a construction progress update on WhatsApp every 1–2 months, and straight away when anything changes on MahaRERA — a later completion date, new complaints, a red flag. Your number stays private: never shown to other members or the builder.

Be the first to watch this project.

How are you connected to this project?

Watching needs only WhatsApp or your number. Bought here? No document needed now. From the builder’s team? Join to answer buyers’ questions; you never see members’ details. Owners and the builder’s team sign in with a one-time code, then come straight back here.

Common questions about The New Green Chambers CHS

What is the possession date of The New Green Chambers CHS?

According to GharKundli's check of MahaRERA records (updated October 2026), the latest completion date filed on MahaRERA for The New Green Chambers CHS in Byculla, Mumbai is 31 December 2025 — 42 months later than 30 June 2022, the date given at registration. That date has already passed.

The date has already moved 42 months. Will it move again? Check the real pace of construction →

Is the builder's possession date different from the MahaRERA date for The New Green Chambers CHS?

Builders and listing sites often quote an earlier "target" date for handover. The completion date The New Green Chambers CHS's builder has filed on MahaRERA, the official one, is 31 December 2025, already 42 months later than the 30 June 2022 given at registration, per GharKundli's check of MahaRERA records. If possession is late, what counts under RERA (Section 18) is the possession date written in your agreement for sale.

Why was the possession date of The New Green Chambers CHS extended?

According to GharKundli's check of MahaRERA records (updated October 2026), The New Green Chambers CHS's builder applied to MahaRERA to extend the completion date 4 times: to 30 June 2023, giving the reason "Due to the lockdown in 2020 and most of 2021, our construction work had come to a stand still. Moreover, there was shortage of labors as most of them had moved to their hometown. The work has now resumed and is in full swing. Kindly allow us to extend the project."; to 31 December 2023, giving the reason "In accordance with circular no 28, we hereby apply for extension of our project u/s 7(3) in Format B. The project was delayed for reasons beyond our control on account of various reasons and more particularly on account of the pandemic of Covid-19. We have consent of 66.67% allottees for purpose of extension of RERA registration period of the said project"; to 31 December 2024, giving the reason "In accordance with circular no 28, we hereby apply for extension of our project u/s 7(3) in Format B. The project was delayed for reasons beyond our control on account of various reasons and more particularly on account of the pandemic of Covid-19. We have consent of 88.89% allottees for purpose of extension of RERA registration period of the said project."; to 31 December 2025, giving the reason "We apologize for the delay in the completion of the project and the submission of this request. The delay has occurred due to issues with procurement, unforeseen site conditions, coordination challenges and delay in OC. Despite these setbacks, we are working diligently to address these issues and complete the remaining work. We are closely monitoring progress and taking all necessary steps to ensure timely completion. Given the circumstances, we kindly request an extension until 31-12-2025 to complete the project and fulfil all regulatory requirements. We seek your understanding and approva…".

What is the RERA number of The New Green Chambers CHS?

According to GharKundli's check of MahaRERA records (updated October 2026), the MahaRERA registration number of The New Green Chambers CHS in Byculla, Mumbai is P51900022675.

Is The New Green Chambers CHS registered with MahaRERA?

According to GharKundli's check of MahaRERA records (updated October 2026), The New Green Chambers CHS is registered as P51900022675 and its status is "Lapsed (registration period ended)".

What is the current construction status of The New Green Chambers CHS? How much work is done?

According to GharKundli's check of MahaRERA records (updated October 2026), The New Green Chambers CHS's status on MahaRERA is "Lapsed (registration period ended)". As filed by the builder, slab work on THE NEW GREEN CHAMBERS CHS is 100% done and internal work 100%. GharKundli's full report compares construction progress with the deadline.

Does The New Green Chambers CHS have complaints on MahaRERA?

No complaints were listed on MahaRERA as of October 2026, per GharKundli's weekly check.

Is The New Green Chambers CHS safe to buy?

According to GharKundli's check of MahaRERA records (updated October 2026), The New Green Chambers CHS is registered on MahaRERA as P51900022675, its MahaRERA status is "Lapsed (registration period ended)", its completion date has moved 42 months since registration and no complaints are listed against it. GharKundli doesn't call a project safe or unsafe from these numbers alone: its full report gives a risk & trust score with every point explained.

How much GST is payable on a flat in The New Green Chambers CHS?

The New Green Chambers CHS isn't marked completed on MahaRERA, so until the occupancy certificate is issued GST applies to a new flat: 5% of the price, with no input tax credit. The lower 1% rate is only for "affordable" homes: carpet area up to 60 sq m (about 646 sq ft) in the Mumbai region, and price up to ₹45 lakh. There is no GST on stamp duty or registration, and none once the occupancy certificate is issued.

What is the stamp duty and registration cost for a flat in The New Green Chambers CHS?

For a flat in The New Green Chambers CHS (Mumbai), stamp duty is 6% of the agreement value, or of the ready reckoner value if that's higher, including 1% Metro Cess. A woman buying in her own name pays 5%. Registration is 1% of the value, capped at ₹30,000. On a ₹1 crore flat that's about ₹6 lakh in stamp duty plus ₹30,000 registration. GharKundli's property cost calculator works it out for your price: gharkundli.com/tools/property-cost-calculator

Has The New Green Chambers CHS received its OC? Is it ready to move in?

Not yet. According to GharKundli's check of MahaRERA records (updated October 2026), The New Green Chambers CHS isn't completed: its MahaRERA status is "Lapsed (registration period ended)", with 31 December 2025 as the latest completion date filed on MahaRERA, and that date has passed. A flat is ready to move in only once the occupancy certificate (OC) is issued, after construction is complete.

What does "lapsed" mean for The New Green Chambers CHS?

According to GharKundli's check of MahaRERA records (updated October 2026), The New Green Chambers CHS's registration shows as lapsed on MahaRERA. Lapsed means the completion date on MahaRERA (31 December 2025) passed without the project being marked complete or the registration being extended. Before paying anything, ask the builder in writing whether an extension has been applied for.

Has The New Green Chambers CHS uploaded its title report on MahaRERA?

According to GharKundli's check of MahaRERA records (updated October 2026), no title report for The New Green Chambers CHS was found on MahaRERA. Builders are expected to upload one; before booking, ask the builder for the advocate's title certificate in writing.

No title report is on MahaRERA for this project. See which documents are missing →

How can I get updates if The New Green Chambers CHS's possession date changes?

The latest dates are on The New Green Chambers CHS's MahaRERA page (P51900022675). GharKundli's Kundli Watch sends a free WhatsApp update on The New Green Chambers CHS every 1–2 months, and straight away when anything changes on MahaRERA: a later completion date, new complaints or a red flag. Your number is never shown to the builder.

How many floors does The New Green Chambers CHS have?

According to GharKundli's check of MahaRERA records (updated October 2026), The New Green Chambers CHS has one building filed: THE NEW GREEN CHAMBERS CHS with 23 floors.

How big is the land of The New Green Chambers CHS?

According to GharKundli's check of MahaRERA records (updated October 2026), The New Green Chambers CHS stands on 334 sq m of land (about 0.1 acres), with 1,811 sq m of sanctioned built-up area.

What are the reviews of The New Green Chambers CHS?

Google Maps has reviews of The New Green Chambers CHS written by Google users; GharKundli links to them on this page but doesn't check them. For facts rather than opinions: no complaints are listed on MahaRERA, and Kundli Watch shows verified owners of the project.

What is the address and pincode of The New Green Chambers CHS?

The New Green Chambers CHS by ELITE CONSTRUCTION CO is in Byculla, Mumbai, pincode 400008, Maharashtra, and is registered on MahaRERA as P51900022675, per GharKundli's check of MahaRERA records. Its boundaries filed there include Sofia Zubair Road. Its land is filed as Plot No - 29. GharKundli lists all 75 MahaRERA projects in Mumbai Central (400008).

How many flats are in The New Green Chambers CHS?

According to GharKundli's check of MahaRERA records (updated October 2026), The New Green Chambers CHS has 17 homes in 1 tower registered on MahaRERA.

When was The New Green Chambers CHS registered on MahaRERA?

According to GharKundli's check of MahaRERA records (updated October 2026), The New Green Chambers CHS was registered on MahaRERA on 12 October 2019. GharKundli did not find a title report on the land on file there.

Does The New Green Chambers CHS have any legal issues or court cases?

No court cases are listed for The New Green Chambers CHS on MahaRERA, per GharKundli's check of MahaRERA records (updated October 2026).

Who is the builder / developer of The New Green Chambers CHS?

According to GharKundli's check of MahaRERA records (updated October 2026), the builder is ELITE CONSTRUCTION CO.