Kalpataru Elaara
by Kalpataru Gardens Limited (Agile) · Bangur Nagar, Mumbai 400104Also near Goregaon West, Andheri East, Malad East
What’s in the report? →Possession date of Kalpataru Elaara (MahaRERA PM1180002600918): 30 October 2032, moved from 31 May 2030 (25 months later). It has 237 homes (2 BHK and 3 BHK, 635–1431 sq ft carpet), 0% sold or booked. No complaints on MahaRERA. How to check it yourself
Registered on MahaRERA under PM1180002600918, and currently active. Its completion date has moved from May 2030 to October 2032: 25 months at the builder's request, plus MahaRERA's automatic 4-month extension for all eligible projects.
Source: MahaRERA website — records for PM1180002600918, read and compiled by GharKundli. Facts as filed on MahaRERA, no opinions.
What do you want to know about Kalpataru Elaara?
Title report MahaRERA par nahi dikh rahi. Kya poochna hai?Tap a question. We’ll answer you on WhatsApp, free.
How the possession date of Kalpataru Elaara has moved
31 May 2030
Completion date given when the project was registered
30 June 2032
Extended at the builder's request (MahaRERA application EA08072621694)
Reason the builder gave MahaRERA:
“Due to typographical error, the proposed Project Completion Date was inadvertently mentioned as 31st May 2030 instead of the originally intended date of 30th June 2032 while registering the Project with MahaRERA. This discrepancy was identi…” Read the full reason
“Due to typographical error, the proposed Project Completion Date was inadvertently mentioned as 31st May 2030 instead of the originally intended date of 30th June 2032 while registering the Project with MahaRERA. This discrepancy was identified by the Promoter upon receipt of the registration certificate. Accordingly, the Promoter is seeking correction of the project completion date by way of an extension. The intended and actual proposed completion timeline for the project is 30th June 2032. In light of the above, the Promoter hereby requests that the project completion date be corrected t…”30 October 2032
MahaRERA's automatic 4-month extension for all eligible projects, not the builder's request
Source: Kalpataru Elaara’s extension records on MahaRERA (PM1180002600918), read by GharKundli in October 2026. The builder’s reasons are quoted as filed. Your own possession date is the one in your agreement for sale.
What builders tell MahaRERA when they’re late: 14,973 applications analysed →GharKundli’s full report on Kalpataru Elaara
Read from every filing on MahaRERA when you open it
- Risk & trust score, every point explained
- What the title report says about the land
- Each complaint and court case, and how it ended
- Construction pace against the October 2032 deadline
- Agreement clauses weaker than the RERA model
- Escrow audit, loans and the builder's record
- Questions to get answered in writing before you pay
- MahaRERA registration
- PM1180002600918
- Status
- Registered and active
- Builder
- Kalpataru Gardens Limited
- Location
- Bangur Nagar, Mumbai · 400104
- Project type
- Mixed
- Registered on
- 24 Jun 2026
- Completion date at registration
- May 2030
- Latest completion date
- October 2032
- Delay so far
- 25 months
- MahaRERA's automatic extension
- +4 months (force majeure, all eligible projects)
- Homes
- 237
- Sold or booked
- 0%
- Towers
- 2
- Complaints on MahaRERA
- 0
- Court cases listed
- 0
- Title report on file
- Not found
Construction progress of Kalpataru Elaara, as filed by the builder
What the builder has reported to MahaRERA, as GharKundli read it in October 2026. GharKundli’s full report compares it with the deadline.
| Tower / wing | Plinth | Slabs (structure) | Internal work | Lifts, fire & electrical |
|---|---|---|---|---|
| Kalpataru Elaara / Tower A | 0% | 0% | 0% | 0% |
| Kalpataru Elaara / Tower B | 0% | 0% | 0% | 0% |
Commencement certificate (CC), as filed on MahaRERA
- Kalpataru Elaara: covers Plinth
- Kalpataru Elaara: covers Plinth
Latest CC order on MahaRERA: dated 27/05/2026.
Want to know when this changes? Kundli Watch sends a free WhatsApp update on Kalpataru Elaara every 1–2 months.
Kalpataru Elaara: buildings, flats and land, as filed on MahaRERA
| Type | Carpet area (sq ft) | Units |
|---|---|---|
| 2 BHK | 635 – 787 | 162 |
| 3 BHK | 1,034 – 1,431 | 75 |
| Shops | 251 – 2,998 | 15 |
- Buildings: Kalpataru Elaara (29 floors, 162 units) · Kalpataru Elaara (29 floors, 90 units)
- Car parking: 571 covered
- Land: 9,629 sq m (about 2.4 acres) · sanctioned built-up 23,154 sq m · recreational space 1,690 sq m
- Map: the location the builder filed on MahaRERA · Get directions
The builder’s record and reviews
Kalpataru (a group of 21 linked companies) has 96 projects on MahaRERA since 2017, this one included. Of the 96 GharKundli has checked: 61 finished, 57 within the promised date and 4 needed more time (typically 5 months); 33 still being built, 2 past the promised date (typically 5 months late); 2 lapsed. 392 complaints on MahaRERA across 60 projects.
Read Google reviews of Kalpataru Elaara →Reviews on Google are opinions by Google users; GharKundli doesn’t check them.
Kundli Watch
Kalpataru Elaara: buyers & owners
Free: a construction progress update on WhatsApp every 1–2 months, and straight away when anything changes on MahaRERA — a later completion date, new complaints, a red flag. Your number stays private: never shown to other members or the builder.
Be the first to watch this project.
How are you connected to this project?
Watching needs only WhatsApp or your number. Bought here? No document needed now. From the builder’s team? Join to answer buyers’ questions; you never see members’ details. Owners and the builder’s team sign in with a one-time code, then come straight back here.
Common questions about Kalpataru Elaara
What is the possession date of Kalpataru Elaara?
According to GharKundli's check of MahaRERA records (updated October 2026), the latest completion date filed on MahaRERA for Kalpataru Elaara in Bangur Nagar, Mumbai is 30 October 2032 — 25 months later than 31 May 2030, the date given at registration, plus MahaRERA's automatic 4-month extension for all eligible projects.
The date has already moved 25 months. Will it move again? Check the real pace of construction →
Is the builder's possession date different from the MahaRERA date for Kalpataru Elaara?
Builders and listing sites often quote an earlier "target" date for handover. The completion date Kalpataru Elaara's builder has filed on MahaRERA, the official one, is 30 October 2032, already 25 months later than the 31 May 2030 given at registration, per GharKundli's check of MahaRERA records. If possession is late, what counts under RERA (Section 18) is the possession date written in your agreement for sale.
Why was the possession date of Kalpataru Elaara extended?
According to GharKundli's check of MahaRERA records (updated October 2026), Kalpataru Elaara's builder applied to MahaRERA to extend the completion date once: to 30 June 2032, giving the reason "Due to typographical error, the proposed Project Completion Date was inadvertently mentioned as 31st May 2030 instead of the originally intended date of 30th June 2032 while registering the Project with MahaRERA. This discrepancy was identified by the Promoter upon receipt of the registration certificate. Accordingly, the Promoter is seeking correction of the project completion date by way of an extension. The intended and actual proposed completion timeline for the project is 30th June 2032. In light of the above, the Promoter hereby requests that the project completion date be corrected t…". MahaRERA also added its automatic 4-month extension for all eligible projects.
What is the RERA number of Kalpataru Elaara?
According to GharKundli's check of MahaRERA records (updated October 2026), the MahaRERA registration number of Kalpataru Elaara in Bangur Nagar, Mumbai is PM1180002600918.
Is Kalpataru Elaara registered with MahaRERA?
According to GharKundli's check of MahaRERA records (updated October 2026), Kalpataru Elaara is registered as PM1180002600918 and its status is "Registered and active".
What is the current construction status of Kalpataru Elaara? How much work is done?
According to GharKundli's check of MahaRERA records (updated October 2026), Kalpataru Elaara's status on MahaRERA is "Registered and active". As filed by the builder, slab work is 0% done across 2 towers. GharKundli's full report compares construction progress with the deadline.
Does Kalpataru Elaara have complaints on MahaRERA?
No complaints were listed on MahaRERA as of October 2026, per GharKundli's weekly check.
Is Kalpataru Elaara safe to buy?
According to GharKundli's check of MahaRERA records (updated October 2026), Kalpataru Elaara is registered on MahaRERA as PM1180002600918, its completion date has moved 25 months since registration and no complaints are listed against it. GharKundli doesn't call a project safe or unsafe from these numbers alone: its full report gives a risk & trust score with every point explained.
How much GST is payable on a flat in Kalpataru Elaara?
Kalpataru Elaara is under construction, so GST applies to a new flat: 5% of the price, with no input tax credit. The lower 1% rate is only for "affordable" homes: carpet area up to 60 sq m (about 646 sq ft) in the Mumbai region, and price up to ₹45 lakh. Some flats in Kalpataru Elaara are 635 sq ft carpet, small enough for 1% if the price is ₹45 lakh or less. There is no GST on stamp duty or registration, and none once the occupancy certificate is issued.
What is the stamp duty and registration cost for a flat in Kalpataru Elaara?
For a flat in Kalpataru Elaara (Mumbai), stamp duty is 6% of the agreement value, or of the ready reckoner value if that's higher, including 1% Metro Cess. A woman buying in her own name pays 5%. Registration is 1% of the value, capped at ₹30,000. On a ₹1 crore flat that's about ₹6 lakh in stamp duty plus ₹30,000 registration. GharKundli's property cost calculator works it out for your price: gharkundli.com/tools/property-cost-calculator
Has Kalpataru Elaara received its OC? Is it ready to move in?
Not yet. According to GharKundli's check of MahaRERA records (updated October 2026), Kalpataru Elaara is still under construction, with 30 October 2032 as the latest completion date filed on MahaRERA. A flat is ready to move in only once the occupancy certificate (OC) is issued, after construction is complete.
Is Kalpataru Elaara a redevelopment or SRA project?
According to GharKundli's check of MahaRERA records (updated October 2026), Kalpataru Elaara is a redevelopment: 148 of its flats are set aside for existing occupants (rehab), and the rest are for sale. Its planning authority is MCGM, not the Slum Rehabilitation Authority, so it isn't an SRA scheme.
Has Kalpataru Elaara uploaded its title report on MahaRERA?
According to GharKundli's check of MahaRERA records (updated October 2026), no title report for Kalpataru Elaara was found on MahaRERA. Builders are expected to upload one; before booking, ask the builder for the advocate's title certificate in writing.
No title report is on MahaRERA for this project. See which documents are missing →
How can I get updates if Kalpataru Elaara's possession date changes?
The latest dates are on Kalpataru Elaara's MahaRERA page (PM1180002600918). GharKundli's Kundli Watch sends a free WhatsApp update on Kalpataru Elaara every 1–2 months, and straight away when anything changes on MahaRERA: a later completion date, new complaints or a red flag. Your number is never shown to the builder.
How many floors does Kalpataru Elaara have?
According to GharKundli's check of MahaRERA records (updated October 2026), Kalpataru Elaara has 2 buildings filed: Kalpataru Elaara with 29 floors and 162 units; Kalpataru Elaara with 29 floors and 90 units.
What are the flat sizes (carpet area) in Kalpataru Elaara?
According to GharKundli's check of MahaRERA records (updated October 2026), the builder has filed these homes for Kalpataru Elaara: 2 BHK: 635 to 787 sq ft carpet (162 homes); 3 BHK: 1034 to 1431 sq ft carpet (75 homes). Carpet area is the usable floor area inside the walls, as defined under RERA.
How much parking does Kalpataru Elaara have?
According to GharKundli's check of MahaRERA records (updated October 2026), the builder has filed 571 covered car parking spaces for Kalpataru Elaara.
How big is the land of Kalpataru Elaara?
According to GharKundli's check of MahaRERA records (updated October 2026), Kalpataru Elaara stands on 9,629 sq m of land (about 2.4 acres), with 23,154 sq m of sanctioned built-up area and 1,690 sq m of recreational open space.
What is the track record of Kalpataru Elaara's builder?
According to GharKundli's check of MahaRERA records (updated October 2026), Kalpataru (a group of 21 linked companies) has 96 projects on MahaRERA since 2017, this one included. Of the 96 GharKundli has checked: 61 finished, 57 within the promised date and 4 needed more time (typically 5 months); 33 still being built, 2 past the promised date (typically 5 months late); 2 lapsed. 392 complaints on MahaRERA across 60 projects. GharKundli's full report covers the builder's record in detail.
What are the reviews of Kalpataru Elaara?
Google Maps has reviews of Kalpataru Elaara written by Google users; GharKundli links to them on this page but doesn't check them. For facts rather than opinions: no complaints are listed on MahaRERA, and Kundli Watch shows verified owners of the project.
What is the address and pincode of Kalpataru Elaara?
Kalpataru Elaara by Kalpataru Gardens Limited (Agile) is in Bangur Nagar, Mumbai, pincode 400104 (near Goregaon West, Andheri East, Malad East), Maharashtra, and is registered on MahaRERA as PM1180002600918, per GharKundli's check of MahaRERA records. GharKundli lists all 183 MahaRERA projects in Goregaon West (400104).
How many flats are in Kalpataru Elaara, and how many are sold?
According to GharKundli's check of MahaRERA records (updated October 2026), Kalpataru Elaara has 237 homes in 2 towers registered on MahaRERA, and 0% of them are sold or booked.
When was Kalpataru Elaara registered on MahaRERA?
According to GharKundli's check of MahaRERA records (updated October 2026), Kalpataru Elaara was registered on MahaRERA on 24 June 2026. GharKundli did not find a title report on the land on file there.
Does Kalpataru Elaara have any legal issues or court cases?
No court cases are listed for Kalpataru Elaara on MahaRERA, per GharKundli's check of MahaRERA records (updated October 2026).
Who is the builder / developer of Kalpataru Elaara?
According to GharKundli's check of MahaRERA records (updated October 2026), the builder is Kalpataru Gardens Limited, the company Agile files this project under.
Check it yourself on MahaRERA
- How to check the possession date of Kalpataru Elaara
- How to find and verify a MahaRERA number
- How to check construction status on MahaRERA
- Occupancy certificate (OC): what to check before possession
- Possession delayed? Work out the interest the builder owes
- How to file a MahaRERA complaint against a builder
- Where MahaRERA complaints are: the data
- Why builders ask MahaRERA for more time: the data
Other projects in Goregaon West (400104)
- io Residences by PCPL
- io Tower by PCPL
- Ekta Tripolis Phase II
- Apricus
- Paras Residency
- Bali Ananda
- Sunteck Pinnacle 1
- DRM Sheetal Landmark
Data compiled by GharKundli (gharkundli.com) from MahaRERA public records, as of October 2026. Check the project’s MahaRERA page for the latest filings. Not legal advice.