Shivay Serenity
by TKJ Enterprises Private Limited · Kurla, Mumbai
Registered on MahaRERA under PR1180002601303, and currently active. Its completion date has moved from October 2029 to February 2030, 4 months later.
Source: GharKundli’s check of MahaRERA records, October 2026.
- MahaRERA registration
- PR1180002601303
- Status
- Registered and active
- Builder
- TKJ Enterprises Private Limited
- Location
- Kurla, Mumbai · 400022
- Project type
- Residential / Group Housing
- Registered on
- 24 Jul 2026
- Completion date at registration
- October 2029
- Latest completion date
- February 2030
- Delay so far
- 4 months
- Homes
- 9
- Sold or booked
- 0%
- Towers
- 1
- Complaints on MahaRERA
- 0
- Court cases listed
- 0
- Title report on file
- Not found
GharKundli’s full report on Shivay Serenity
Read from every filing on MahaRERA when you open it
- Risk & trust score, every point explained
- What the title report says about the land
- Each complaint and court case, and how it ended
- Construction pace against the deadline
- Agreement clauses weaker than the RERA model
- Escrow audit, loans and the builder's record
- Questions to get answered in writing before you pay
Kundli Watch
Shivay Serenity: buyers & owners
Free. You talk to our team privately — no one sees your number.
How are you connected to this project?
You’ll sign in with your mobile number first, then come straight back here.
Common questions about Shivay Serenity
Is Shivay Serenity registered with MahaRERA?
According to GharKundli's check of MahaRERA records (updated October 2026), Shivay Serenity is registered as PR1180002601303 and its status is "Registered and active".
Where is Shivay Serenity?
Shivay Serenity by TKJ Enterprises Private Limited is in Kurla, Mumbai (pincode 400022), Maharashtra, and is registered on MahaRERA as PR1180002601303, per GharKundli's check of MahaRERA records.
When is possession of Shivay Serenity due?
According to GharKundli's check of MahaRERA records (updated October 2026), the latest completion date filed on MahaRERA for Shivay Serenity in Kurla, Mumbai is 1 February 2030 — 4 months later than 1 October 2029, the date given at registration.
Does Shivay Serenity have complaints on MahaRERA?
No complaints were listed on MahaRERA as of October 2026, per GharKundli's weekly check. GharKundli's full report explains each case and how it ended.
Who is the builder of Shivay Serenity?
According to GharKundli's check of MahaRERA records (updated October 2026), the builder is TKJ Enterprises Private Limited.
Other projects in pincode 400022
Data compiled by GharKundli (gharkundli.com) from MahaRERA public records, as of October 2026. Check the project’s MahaRERA page for the latest filings. Not legal advice.