Shraddha Prominent
by Shraddha Landmark Private Limited · Kurla, Mumbai 400083
What’s in the report? →Possession date of Shraddha Prominent (MahaRERA P51800046232): 30 April 2027, moved from 31 December 2025 (12 months later). It has 87 homes (1 BHK, 1 Room Kitchen and 2 BHK, 271–671 sq ft carpet), 93% sold or booked. No complaints on MahaRERA. How to check it yourself
Registered on MahaRERA under P51800046232, and currently active. Its completion date has moved from December 2025 to April 2027: 12 months at the builder's request, plus MahaRERA's automatic 4-month extension for all eligible projects.
Source: MahaRERA website — records for P51800046232, read and compiled by GharKundli. Facts as filed on MahaRERA, no opinions.
What do you want to know about Shraddha Prominent?
Title report MahaRERA par nahi dikh rahi. Kya poochna hai?Tap a question. We’ll answer you on WhatsApp, free.
How the possession date of Shraddha Prominent has moved
31 December 2025
Completion date given when the project was registered
31 December 2026
Extended at the builder's request (MahaRERA application EA03022619695)
Reason the builder gave MahaRERA:
“The project construction is substantially completed and only minor finishing works remain. However, the application for Occupancy Certificate (OC) is currently pending due to delay in approvals from the concerned local authority. Since the…” Read the full reason
“The project construction is substantially completed and only minor finishing works remain. However, the application for Occupancy Certificate (OC) is currently pending due to delay in approvals from the concerned local authority. Since the issuance of OC is essential for project completion and handover, additional time is required to obtain the same. The delay is purely administrative and beyond the control of the promoter. Therefore, an extension is sought to complete the remaining minor works and secure the Occupancy Certificate in compliance with RERA provisions.”30 April 2027
MahaRERA's automatic 4-month extension for all eligible projects, not the builder's request
Source: Shraddha Prominent’s extension records on MahaRERA (P51800046232), read by GharKundli in October 2026. The builder’s reasons are quoted as filed. Your own possession date is the one in your agreement for sale.
What builders tell MahaRERA when they’re late: 14,973 applications analysed →GharKundli’s full report on Shraddha Prominent
Read from every filing on MahaRERA when you open it
- Risk & trust score, every point explained
- What the title report says about the land
- Each complaint and court case, and how it ended
- Construction pace against the April 2027 deadline
- Agreement clauses weaker than the RERA model
- Escrow audit, loans and the builder's record
- Questions to get answered in writing before you pay
- MahaRERA registration
- P51800046232
- Status
- Registered and active
- Builder
- Shraddha Landmark Private Limited
- Location
- Kurla, Mumbai · 400083
- Project type
- Residential / Group Housing
- Registered on
- 20 Jun 2022
- Completion date at registration
- December 2025
- Latest completion date
- April 2027
- Delay so far
- 12 months
- MahaRERA's automatic extension
- +4 months (force majeure, all eligible projects)
- Homes
- 87
- Sold or booked
- 93%
- Towers
- 1
- Complaints on MahaRERA
- 0
- Court cases listed
- 0
- Title report on file
- Not found
- Builder's other MahaRERA projects
- 20
Construction progress of Shraddha Prominent, as filed by the builder
What the builder has reported to MahaRERA, as GharKundli read it in October 2026. GharKundli’s full report compares it with the deadline.
| Tower / wing | Plinth | Slabs (structure) | Internal work | Lifts, fire & electrical |
|---|---|---|---|---|
| KANNAMWAR NAGAR OMKAR CHS | 100% | 100% | 99% | 10% |
Commencement certificate (CC), as filed on MahaRERA
- KANNAMWAR NAGAR OMKAR CHS: covers 25 (Basement + Ground + 23 Upper Floors)
Want to know when this changes? Kundli Watch sends a free WhatsApp update on Shraddha Prominent every 1–2 months.
Shraddha Prominent: buildings, flats and land, as filed on MahaRERA
| Type | Carpet area (sq ft) | Units |
|---|---|---|
| 1 BHK | 352 – 368 | 62 |
| 2 BHK | 552 – 671 | 22 |
| 1 Room Kitchen | 271 | 2 |
| Other | 587 | 1 |
- Buildings: KANNAMWAR NAGAR OMKAR CHS (48 floors, 87 units)
- Land: 653 sq m (about 0.2 acres) · sanctioned built-up 3,835 sq m
- Land, as filed: 356 (PT)
- Map: Get directions
The builder’s record and reviews
Shraddha Landmark (a group of 8 linked companies) has 35 projects on MahaRERA since 2017, this one included. Of the 35 GharKundli has checked: 12 finished, 8 within the promised date and 4 needed more time (typically 8 months); 22 still being built, 5 past the promised date (typically 6 months late); 1 lapsed. 7 complaints on MahaRERA across 7 projects.
Read Google reviews of Shraddha Prominent →Reviews on Google are opinions by Google users; GharKundli doesn’t check them.
Kundli Watch
Shraddha Prominent: buyers & owners
Free: a construction progress update on WhatsApp every 1–2 months, and straight away when anything changes on MahaRERA — a later completion date, new complaints, a red flag. Your number stays private: never shown to other members or the builder.
Be the first to watch this project.
How are you connected to this project?
Watching needs only WhatsApp or your number. Bought here? No document needed now. From the builder’s team? Join to answer buyers’ questions; you never see members’ details. Owners and the builder’s team sign in with a one-time code, then come straight back here.
Common questions about Shraddha Prominent
What is the possession date of Shraddha Prominent?
According to GharKundli's check of MahaRERA records (updated October 2026), the latest completion date filed on MahaRERA for Shraddha Prominent in Kurla, Mumbai is 30 April 2027 — 12 months later than 31 December 2025, the date given at registration, plus MahaRERA's automatic 4-month extension for all eligible projects.
The date has already moved 12 months. Will it move again? Check the real pace of construction →
Is the builder's possession date different from the MahaRERA date for Shraddha Prominent?
Builders and listing sites often quote an earlier "target" date for handover. The completion date Shraddha Prominent's builder has filed on MahaRERA, the official one, is 30 April 2027, already 12 months later than the 31 December 2025 given at registration, per GharKundli's check of MahaRERA records. If possession is late, what counts under RERA (Section 18) is the possession date written in your agreement for sale.
Why was the possession date of Shraddha Prominent extended?
According to GharKundli's check of MahaRERA records (updated October 2026), Shraddha Prominent's builder applied to MahaRERA to extend the completion date once: to 31 December 2026, giving the reason "The project construction is substantially completed and only minor finishing works remain. However, the application for Occupancy Certificate (OC) is currently pending due to delay in approvals from the concerned local authority. Since the issuance of OC is essential for project completion and handover, additional time is required to obtain the same. The delay is purely administrative and beyond the control of the promoter. Therefore, an extension is sought to complete the remaining minor works and secure the Occupancy Certificate in compliance with RERA provisions.". MahaRERA also added its automatic 4-month extension for all eligible projects.
What is the RERA number of Shraddha Prominent?
According to GharKundli's check of MahaRERA records (updated October 2026), the MahaRERA registration number of Shraddha Prominent in Kurla, Mumbai is P51800046232.
Is Shraddha Prominent registered with MahaRERA?
According to GharKundli's check of MahaRERA records (updated October 2026), Shraddha Prominent is registered as P51800046232 and its status is "Registered and active".
What is the current construction status of Shraddha Prominent? How much work is done?
According to GharKundli's check of MahaRERA records (updated October 2026), Shraddha Prominent's status on MahaRERA is "Registered and active". As filed by the builder, slab work on KANNAMWAR NAGAR OMKAR CHS is 100% done and internal work 99%. GharKundli's full report compares construction progress with the deadline.
Does Shraddha Prominent have complaints on MahaRERA?
No complaints were listed on MahaRERA as of October 2026, per GharKundli's weekly check.
Is Shraddha Prominent safe to buy?
According to GharKundli's check of MahaRERA records (updated October 2026), Shraddha Prominent is registered on MahaRERA as P51800046232, its completion date has moved 12 months since registration and no complaints are listed against it. GharKundli doesn't call a project safe or unsafe from these numbers alone: its full report gives a risk & trust score with every point explained.
How much GST is payable on a flat in Shraddha Prominent?
Shraddha Prominent is under construction, so GST applies to a new flat: 5% of the price, with no input tax credit. The lower 1% rate is only for "affordable" homes: carpet area up to 60 sq m (about 646 sq ft) in the Mumbai region, and price up to ₹45 lakh. Some flats in Shraddha Prominent are 271 sq ft carpet, small enough for 1% if the price is ₹45 lakh or less. There is no GST on stamp duty or registration, and none once the occupancy certificate is issued.
What is the stamp duty and registration cost for a flat in Shraddha Prominent?
For a flat in Shraddha Prominent (Mumbai), stamp duty is 6% of the agreement value, or of the ready reckoner value if that's higher, including 1% Metro Cess. A woman buying in her own name pays 5%. Registration is 1% of the value, capped at ₹30,000. On a ₹1 crore flat that's about ₹6 lakh in stamp duty plus ₹30,000 registration. GharKundli's property cost calculator works it out for your price: gharkundli.com/tools/property-cost-calculator
Has Shraddha Prominent received its OC? Is it ready to move in?
Not yet. According to GharKundli's check of MahaRERA records (updated October 2026), Shraddha Prominent is still under construction, with 30 April 2027 as the latest completion date filed on MahaRERA. A flat is ready to move in only once the occupancy certificate (OC) is issued, after construction is complete.
Is Shraddha Prominent a redevelopment or SRA project?
According to GharKundli's check of MahaRERA records (updated October 2026), Shraddha Prominent is a redevelopment: 16 of its flats are set aside for existing occupants (rehab), and the rest are for sale.
Has Shraddha Prominent uploaded its title report on MahaRERA?
According to GharKundli's check of MahaRERA records (updated October 2026), no title report for Shraddha Prominent was found on MahaRERA. Builders are expected to upload one; before booking, ask the builder for the advocate's title certificate in writing.
No title report is on MahaRERA for this project. See which documents are missing →
How can I get updates if Shraddha Prominent's possession date changes?
The latest dates are on Shraddha Prominent's MahaRERA page (P51800046232). GharKundli's Kundli Watch sends a free WhatsApp update on Shraddha Prominent every 1–2 months, and straight away when anything changes on MahaRERA: a later completion date, new complaints or a red flag. Your number is never shown to the builder.
How many floors does Shraddha Prominent have?
According to GharKundli's check of MahaRERA records (updated October 2026), Shraddha Prominent has one building filed: KANNAMWAR NAGAR OMKAR CHS with 48 floors and 87 units.
What are the flat sizes (carpet area) in Shraddha Prominent?
According to GharKundli's check of MahaRERA records (updated October 2026), the builder has filed these homes for Shraddha Prominent: 1 BHK: 352 to 368 sq ft carpet (62 homes); 2 BHK: 552 to 671 sq ft carpet (22 homes); 1 Room Kitchen: 271 sq ft carpet (2 homes); Other: 587 sq ft carpet (1 homes). Carpet area is the usable floor area inside the walls, as defined under RERA.
How big is the land of Shraddha Prominent?
According to GharKundli's check of MahaRERA records (updated October 2026), Shraddha Prominent stands on 653 sq m of land (about 0.2 acres), with 3,835 sq m of sanctioned built-up area.
What is the track record of Shraddha Prominent's builder?
According to GharKundli's check of MahaRERA records (updated October 2026), Shraddha Landmark (a group of 8 linked companies) has 35 projects on MahaRERA since 2017, this one included. Of the 35 GharKundli has checked: 12 finished, 8 within the promised date and 4 needed more time (typically 8 months); 22 still being built, 5 past the promised date (typically 6 months late); 1 lapsed. 7 complaints on MahaRERA across 7 projects. GharKundli's full report covers the builder's record in detail.
What are the reviews of Shraddha Prominent?
Google Maps has reviews of Shraddha Prominent written by Google users; GharKundli links to them on this page but doesn't check them. For facts rather than opinions: no complaints are listed on MahaRERA, and Kundli Watch shows verified owners of the project.
What is the address and pincode of Shraddha Prominent?
Shraddha Prominent by Shraddha Landmark Private Limited is in Kurla, Mumbai, pincode 400083, Maharashtra, and is registered on MahaRERA as P51800046232, per GharKundli's check of MahaRERA records. Its land is filed as 356 (PT). GharKundli lists all 176 MahaRERA projects in Vikhroli East (400083).
How many flats are in Shraddha Prominent, and how many are sold?
According to GharKundli's check of MahaRERA records (updated October 2026), Shraddha Prominent has 87 homes in 1 tower registered on MahaRERA, and 93% of them are sold or booked.
When was Shraddha Prominent registered on MahaRERA?
According to GharKundli's check of MahaRERA records (updated October 2026), Shraddha Prominent was registered on MahaRERA on 20 June 2022. GharKundli did not find a title report on the land on file there.
Does Shraddha Prominent have any legal issues or court cases?
No court cases are listed for Shraddha Prominent on MahaRERA, per GharKundli's check of MahaRERA records (updated October 2026).
Who is the builder / developer of Shraddha Prominent?
According to GharKundli's check of MahaRERA records (updated October 2026), the builder is Shraddha Landmark Private Limited, which has 20 other projects registered on MahaRERA.
Check it yourself on MahaRERA
- How to check the possession date of Shraddha Prominent
- How to find and verify a MahaRERA number
- How to check construction status on MahaRERA
- Occupancy certificate (OC): what to check before possession
- Possession delayed? Work out the interest the builder owes
- How to file a MahaRERA complaint against a builder
- Where MahaRERA complaints are: the data
- Why builders ask MahaRERA for more time: the data
All projects with possession due in 2027 in Mumbai Suburban →
Other projects in Vikhroli East (400083)
- DTG Apex
- Jai Shreeram Prasanna CHSL
- Roha Vatika-roha Kumud
- Shivay Serenity
- Elevate 9
- Saffron Residency Phase -1
- Nidhaan Corporate Park
- Sayba Crystal
Other projects by Shraddha Landmark Private Limited
Data compiled by GharKundli (gharkundli.com) from MahaRERA public records, as of October 2026. Check the project’s MahaRERA page for the latest filings. Not legal advice.